Loss Contingencies [Line Items]  
Current cost estimate and actual costs incurred
Mississippi Power's Kemper IGCC 2010 project estimate, current cost estimate (which includes the impacts of the Mississippi Supreme Court's (Court) decision), and actual costs incurred as of December 31, 2015, are as follows:
Cost Category
2010
Project Estimate(f)
 
Current Cost Estimate(a)
 
Actual Costs
 
(in billions)
Plant Subject to Cost Cap(b)(g)
$
2.40

 
$
5.29

 
$
4.83

Lignite Mine and Equipment
0.21
 
0.23
 
0.23
CO2 Pipeline Facilities
0.14
 
0.11
 
0.11
AFUDC(c)
0.17
 
0.69
 
0.59
Combined Cycle and Related Assets Placed in
Service – Incremental(d)(g)

 
0.01
 
0.01
General Exceptions
0.05
 
0.10
 
0.09
Deferred Costs(e)(g)

 
0.20
 
0.17
Total Kemper IGCC
$
2.97

 
$
6.63

 
$
6.03

(a)
Amounts in the Current Cost Estimate reflect estimated costs through August 31, 2016.
(b)
The 2012 MPSC CPCN Order approved a construction cost cap of up to $2.88 billion, net of the DOE Grants and excluding the Cost Cap Exceptions. The Current Cost Estimate and the Actual Costs include non-incremental operating and maintenance costs related to the combined cycle and associated common facilities placed in service in August 2014 that are subject to the $2.88 billion cost cap and exclude post-in-service costs for the lignite mine. See "Rate Recovery of Kemper IGCC Costs – 2013 MPSC Rate Order" herein for additional information. The Current Cost Estimate and the Actual Costs reflect 100% of the costs of the Kemper IGCC. See note (g) for additional information.
(c)
Mississippi Power's original estimate included recovery of financing costs during construction rather than the accrual of AFUDC. This approach was not approved by the Mississippi PSC in 2012 as described in "Rate Recovery of Kemper IGCC Costs." The current estimate reflects the impact of a settlement agreement with the wholesale customers for cost-based rates under FERC's jurisdiction.
(d)
Incremental operating and maintenance costs related to the combined cycle and associated common facilities placed in service in August 2014, net of costs related to energy sales. See "Rate Recovery of Kemper IGCC Costs – 2013 MPSC Rate Order" herein for additional information.
(e)
The 2012 MPSC CPCN Order approved deferral of non-capital Kemper IGCC-related costs during construction as described in "Rate Recovery of Kemper IGCC Costs – Regulatory Assets and Liabilities" herein.
(f)
The 2010 Project Estimate is the certificated cost estimate adjusted to include the certificated estimate for the CO2 pipeline facilities which was approved in 2011 by the Mississippi PSC.
(g)
Beginning in the third quarter 2015, certain costs, including debt carrying costs (associated with assets placed in service and other non-CWIP accounts), that previously were deferred as regulatory assets are now being recognized through income; however, such costs continue to be included in the Current Cost Estimate and the Actual Costs at December 31, 2015.
Mississippi Power [Member]  
Loss Contingencies [Line Items]  
Current cost estimate and actual costs incurred
The Company's Kemper IGCC 2010 project estimate, current cost estimate (which includes the impacts of the Mississippi Supreme Court's (Court) decision), and actual costs incurred as of December 31, 2015, are as follows:
Cost Category
2010 Project Estimate(f)
 
Current Cost Estimate(a)
 
Actual Costs
 
(in billions)
Plant Subject to Cost Cap(b)(g)
$
2.40

 
$
5.29

 
$
4.83

Lignite Mine and Equipment
0.21
 
0.23
 
0.23
CO2 Pipeline Facilities
0.14
 
0.11
 
0.11
AFUDC(c)
0.17
 
0.69
 
0.59
Combined Cycle and Related Assets Placed in
Service – Incremental(d)(g)

 
0.01
 
0.01
General Exceptions
0.05
 
0.10
 
0.09
Deferred Costs(e)(g)

 
0.20
 
0.17
Total Kemper IGCC
$
2.97

 
$
6.63

 
$
6.03


(a)
Amounts in the Current Cost Estimate reflect estimated costs through August 31, 2016.
(b)
The 2012 MPSC CPCN Order approved a construction cost cap of up to $2.88 billion, net of the DOE Grants and excluding the Cost Cap Exceptions. The Current Cost Estimate and the Actual Costs include non-incremental operating and maintenance costs related to the combined cycle and associated common facilities placed in service in August 2014 that are subject to the $2.88 billion cost cap and exclude post-in-service costs for the lignite mine. See "Rate Recovery of Kemper IGCC Costs – 2013 MPSC Rate Order" herein for additional information. The Current Cost Estimate and the Actual Costs reflect 100% of the costs of the Kemper IGCC. See note (g) for additional information.
(c)
The Company's original estimate included recovery of financing costs during construction rather than the accrual of AFUDC. This approach was not approved by the Mississippi PSC in 2012 as described in "Rate Recovery of Kemper IGCC Costs." The current estimate reflects the impact of a settlement agreement with the wholesale customers for cost-based rates under FERC's jurisdiction. See "FERC Matters" herein for additional information.
(d)
Incremental operating and maintenance costs related to the combined cycle and associated common facilities placed in service in August 2014, net of costs related to energy sales. See "Rate Recovery of Kemper IGCC Costs 2013 MPSC Rate Order" herein for additional information.
(e)
The 2012 MPSC CPCN Order approved deferral of non-capital Kemper IGCC-related costs during construction as described in "Rate Recovery of Kemper IGCC Costs – Regulatory Assets and Liabilities" herein.
(f)
The 2010 Project Estimate is the certificated cost estimate adjusted to include the certificated estimate for the CO2 pipeline facilities which was approved in 2011 by the Mississippi PSC.
(g)
Beginning in the third quarter 2015, certain costs, including debt carrying costs (associated with assets placed in service and other non-CWIP accounts), that previously were deferred as regulatory assets are now being recognized through income; however, such costs continue to be included in the Current Cost Estimate and the Actual Costs at December 31, 2015.