Acquisitions - Schedule of Construction Projects (Details) - Jun. 30, 2015 - Southern Power [Member]
$ in Millions
USD ($)
MW
Business Acquisition [Line Items]  
Nameplate Capacity (in mw) | MW 146
PPA Contract Period 25 years
Minimum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost $ 260
Maximum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost $ 280
Decatur Parkway Solar Project, LLC [Member]  
Business Acquisition [Line Items]  
Nameplate Capacity (in mw) | MW 84
PPA Contract Period 25 years
Decatur Parkway Solar Project, LLC [Member] | Minimum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 170
Decatur Parkway Solar Project, LLC [Member] | Maximum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 173
Decatur County Solar Project, LLC [Member]  
Business Acquisition [Line Items]  
Nameplate Capacity (in mw) | MW 20
PPA Contract Period 20 years
Decatur County Solar Project, LLC [Member] | Minimum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 45
Decatur County Solar Project, LLC [Member] | Maximum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 47
Butler Solar LLC [Member]  
Business Acquisition [Line Items]  
Nameplate Capacity (in mw) | MW 103
PPA Contract Period 30 years
Butler Solar LLC [Member] | Minimum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 220
Butler Solar LLC [Member] | Maximum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 230
LS Pawpaw, LLC [Member]  
Business Acquisition [Line Items]  
Nameplate Capacity (in mw) | MW 30
PPA Contract Period 30 years
LS Pawpaw, LLC [Member] | Minimum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 70
LS Pawpaw, LLC [Member] | Maximum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 80
Butler Solar Farm, LLC [Member]  
Business Acquisition [Line Items]  
Nameplate Capacity (in mw) | MW 20
PPA Contract Period 20 years
Butler Solar Farm, LLC [Member] | Minimum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 42
Butler Solar Farm, LLC [Member] | Maximum [Member]  
Business Acquisition [Line Items]  
Estimated Construction Cost [1] $ 48
[1] Includes the acquisition price of all outstanding membership interests.