Contingencies and Regulatory Matters Contingencies and Regulatory Matters (Tables)
3 Months Ended
Mar. 31, 2014
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Recovery Balance of Each Regulatory Clause
The recovery balance of each regulatory clause follows:
Regulatory Clause
 
Balance Sheet Line Item
 
March 31, 2014
 
December 31, 2013
 
 
 
 
(in millions)
Rate CNP Environmental – Under
 
Deferred under recovered regulatory clause revenues
 
$
13

 
$
7

Rate CNP PPA – Under
 
Deferred under recovered regulatory clause revenues
 
23

 
18

Retail Energy Cost Recovery – Over
 
Other regulatory liabilities, current
 
22

 
27

 
 
Deferred over recovered regulatory clause revenues
 

 
15

Natural Disaster Reserve
 
Other regulatory liabilities, deferred
 
91

 
96

Recovery Position of Each Regulatory Clause
The recovery balance of each regulatory clause follows:
Recovery Clause
 
Balance Sheet Location
 
March 31, 2014
 
December 31, 2013
 
 
 
 
(in millions)
Fuel Cost Recovery – Under
 
Under recovered regulatory clause revenues
 
$
35.7

 
$
21.0

Purchased Power Capacity Recovery – Over
 
Other regulatory liabilities, current
 
5.5

 

Purchased Power Capacity Recovery – Under
 
Under recovered regulatory clause revenues
 

 
2.8

Environmental Cost Recovery – Under
 
Under recovered regulatory clause revenues
 
17.1

 
14.4

Energy Conservation Cost Recovery – Under
 
Under recovered regulatory clause revenues
 
6.3

 
7.0

Current And Actual Cost Estimate for Kemper IGC
Mississippi Power's 2010 project estimate, current cost estimate, and actual costs incurred as of March 31, 2014 for the Kemper IGCC are as follows:
Cost Category
2010 Project Estimate(e)
Current Estimate
Actual Costs at March 31, 2014
 
(in billions)
Plant Subject to Cost Cap(a)
$
2.40

$
4.44

$
3.52

Lignite Mine and Equipment
0.21
0.23
0.23
CO2 Pipeline Facilities
0.14
0.11
0.10
AFUDC(b)(c)
0.17
0.55
0.32
General Exceptions
0.05
0.10
0.07
Regulatory Asset(c)(d)

0.10
0.08
Total Kemper IGCC(a)(c)
$
2.97

$
5.53

$
4.32

(a)
The 2012 MPSC CPCN Order approved a construction cost cap of up to $2.88 billion, net of the DOE Grants and excluding the Cost Cap Exceptions.
(b)
Mississippi Power's original estimate included recovery of financing costs during construction rather than the accrual of AFUDC. This approach was not approved by the Mississippi PSC in 2012 as described in "Rate Recovery of Kemper IGCC Costs."
(c)
Amounts in the Current Estimate reflect costs through May 31, 2015, but do not reflect any adjustments as a result of the expected placement of the combined cycle and the associated common facilities portion of the Kemper IGCC in service in the summer of 2014.
(d)
The 2012 MPSC CPCN Order approved deferral of non-capital Kemper IGCC-related costs during construction as described in "Rate Recovery of Kemper IGCC Costs – Regulatory Assets."
(e)
The 2010 Project Estimate is the certificated cost estimate adjusted to include the certificated estimate for the CO2 pipeline facilities which was approved in 2011 by the Mississippi PSC.