XML 105 R77.htm IDEA: XBRL DOCUMENT v3.20.1
SAN ONOFRE NUCLEAR GENERATING STATION (Details)
$ in Millions
3 Months Ended
Mar. 31, 2020
USD ($)
Jointly Owned Utility Plant Interests [Line Items]  
Anticipated term of dismantlement work 10 years
San Diego Gas and Electric Company [Member]  
Jointly Owned Utility Plant Interests [Line Items]  
Percent of dismantlement work expense 20.00%
ARO related to decommissioning costs $ 608
Cost study estimate decommissioning escalated $ 860
Jointly Owned Nuclear Power Plant [Member] | San Diego Gas and Electric Company [Member]  
Jointly Owned Utility Plant Interests [Line Items]  
Jointly owned utility plant, proportionate ownership share 20.00%
SONGS 2 and 3 Decommissioning [Member] | San Diego Gas and Electric Company [Member]  
Jointly Owned Utility Plant Interests [Line Items]  
Nuclear decommissioning trust authorized withdrawal amount $ 109