XML 105 R19.htm IDEA: XBRL DOCUMENT v3.19.3
COMMITMENTS AND CONTINGENCIES
9 Months Ended
Sep. 30, 2019
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies COMMITMENTS AND CONTINGENCIES
LEGAL PROCEEDINGS
We accrue losses for a legal proceeding when it is probable that a loss has been incurred and the amount of the loss can be reasonably estimated. However, the uncertainties inherent in legal proceedings make it difficult to reasonably estimate the costs and effects of resolving these matters. Accordingly, actual costs incurred may differ materially from amounts accrued, may exceed applicable insurance coverage and could materially adversely affect our business, cash flows, results of operations, financial condition and prospects. Unless otherwise indicated, we are unable to estimate reasonably possible losses in excess of any amounts accrued.
At September 30, 2019, loss contingency accruals for legal matters, including associated legal fees, that are probable and estimable were $97 million for Sempra Energy Consolidated, including $50 million for SoCalGas. Amounts for Sempra Energy and SoCalGas include $49 million for matters related to the Aliso Canyon natural gas storage facility gas leak, which we discuss below.
SDG&E
2007 Wildfire Litigation and Net Cost Recovery Status
SDG&E has resolved all civil litigation associated with three wildfires that occurred in October 2007.
As a result of a CPUC decision denying SDG&E’s request to recover wildfire costs, SDG&E wrote off the wildfire regulatory asset, resulting in a charge of $351 million ($208 million after-tax) in the third quarter of 2017. SDG&E applied to the CPUC for rehearing of its decision but, in July 2018, the CPUC denied SDG&E’s rehearing request. In November 2018, the California Court of Appeal denied SDG&E’s petition to reverse the CPUC’s decision. In January 2019, the California Supreme Court denied SDG&E’s petition to reverse the decisions of the CPUC and the California Court of Appeal. In October 2019, the U.S. Supreme Court declined to review the case, effectively ending SDG&E’s efforts to recover the wildfire regulatory asset.
SoCalGas
Aliso Canyon Natural Gas Storage Facility Gas Leak
On October 23, 2015, SoCalGas discovered a leak at one of its injection-and-withdrawal wells, SS25, at its Aliso Canyon natural gas storage facility in Los Angeles County. The Aliso Canyon natural gas storage facility has been operated by SoCalGas since 1972. SS25 is one of more than 100 injection-and-withdrawal wells at the storage facility. SoCalGas worked closely with several of the world’s leading experts to stop the Leak, and on February 18, 2016, DOGGR confirmed that the well was permanently sealed.
As discussed in “Cost Estimates and Accounting Impact” below, SoCalGas incurred significant costs for temporary relocation, to control the well and to stop the Leak, as well as to purchase natural gas to replace that lost through the Leak. As discussed in “Local Community Mitigation Efforts” below, during the Leak and in the months following the sealing of the well, SoCalGas provided support to nearby residents who wished to temporarily relocate as a result of the Leak. These programs ended in July 2016.
SoCalGas has additionally incurred significant costs to defend against and, in certain cases, settle, civil and criminal litigation arising from the Leak; to pay the costs of the government-ordered response to the Leak including the costs for an independent third party to conduct a root cause analysis to investigate the technical cause of the Leak; to respond to various government and agency investigations regarding the Leak; and to comply with increased regulation imposed as a result of the Leak. As further described below in “Civil and Criminal Litigation,” “Regulatory Proceedings” and “Governmental Investigations and Orders and Additional Regulation,” these activities are ongoing and SoCalGas anticipates that it will incur additional such costs, which may also be significant.
Local Community Mitigation Efforts. Pursuant to a directive by the DPH and orders by the LA Superior Court, SoCalGas provided temporary relocation support to residents in the nearby community who requested it. The DPH issued a second directive generally requiring SoCalGas to professionally clean the homes of Porter Ranch residents (the Directive), which is addressed within the Government Plaintiffs Settlement that we discuss below in “Civil and Criminal Litigation.”
The costs incurred to mitigate local community impacts have been significant. If any of these costs are not covered by insurance (including any costs in excess of applicable policy limits), if there are significant delays in receiving insurance recoveries, or if the insurance recoveries are subject to income taxes while the associated costs are not tax deductible, such amounts could have a material adverse effect on SoCalGas’ and Sempra Energy’s cash flows, financial condition and results of operations.
Civil and Criminal Litigation. As of October 28, 2019, 390 lawsuits, including approximately 36,000 plaintiffs, are pending against SoCalGas, some of which have also named Sempra Energy. All these cases, other than a matter brought by the Los Angeles County District Attorney and the federal securities class action discussed below, are coordinated before a single court in the LA Superior Court for pretrial management.
In November 2017, the individuals and business entities asserting tort and Proposition 65 claims filed a Third Amended Consolidated Master Case Complaint for Individual Actions, through which their separate lawsuits will be managed for pretrial purposes. The consolidated complaint asserts causes of action for negligence, negligence per se, private and public nuisance (continuing and permanent), trespass, inverse condemnation, strict liability, negligent and intentional infliction of emotional distress, fraudulent concealment, loss of consortium, wrongful death and violations of Proposition 65 against SoCalGas, with certain causes also naming Sempra Energy. The consolidated complaint seeks compensatory and punitive damages for personal injuries, lost wages and/or lost profits, property damage and diminution in property value, injunctive relief, costs of future medical monitoring, civil penalties (including penalties associated with Proposition 65 claims alleging violation of requirements for warning about certain chemical exposures), and attorneys’ fees. The court has scheduled an initial trial for June 24, 2020 for a small number of randomly selected individual plaintiffs.
In January 2017, two consolidated class action complaints were filed against SoCalGas and Sempra Energy, one on behalf of a putative class of persons and businesses who own or lease real property within a five-mile radius of the well (the Property Class Action), and a second on behalf of a putative class of all persons and entities conducting business within five miles of the facility (the Business Class Action). Both complaints assert claims for strict liability for ultra-hazardous activities, negligence and violation of the California Unfair Competition Law. The Property Class Action also asserts claims for negligence per se, trespass, permanent and continuing public and private nuisance, and inverse condemnation. The Business Class Action also asserts a claim for negligent interference with prospective economic advantage. Both complaints seek compensatory, statutory and punitive damages, injunctive relief and attorneys’ fees. In May 2019, the California Supreme Court ruled that the purely economic damages alleged in the Business Class Action are not recoverable under the law, and in September 2019, in accordance with the ruling, the LA Superior Court dismissed the strict liability, negligence and negligent interference with prospective economic advantage causes of action in the Business Class Action complaint.
Complaints by property developers were filed in 2017 and 2018 against SoCalGas and Sempra Energy alleging causes of action for strict liability, negligence per se, negligence, continuing nuisance, permanent nuisance and violation of the California Unfair Competition Law, as well as claims for negligence against certain directors of SoCalGas. The complaints seek compensatory, statutory and punitive damages, injunctive relief and attorneys’ fees.
In October 2018 and January 2019, complaints were filed on behalf of 51 plaintiffs who are firefighters stationed near the Aliso Canyon natural gas storage facility and allege they were injured by exposure to chemicals released during the Leak. The complaints against SoCalGas and Sempra Energy assert causes of actions for negligence, negligence per se, private and public nuisance (continuing and permanent), trespass, inverse condemnation, strict liability, negligent and intentional infliction of emotional distress, fraudulent concealment and loss of consortium. The complaints seek compensatory and punitive damages for personal injuries, lost wages and/or lost profits, property damage and diminution in property value, and attorney’s fees.
In addition, a federal securities class action alleging violation of the federal securities laws was filed against Sempra Energy and certain of its officers and certain of its directors in the U.S. District Court for the Southern District of California. In March 2018, the court dismissed the action with prejudice. The plaintiffs filed a notice of appeal of the dismissal.
Five shareholder derivative actions are also pending alleging breach of fiduciary duties against certain officers and certain directors of Sempra Energy and/or SoCalGas, four of which were joined in a Consolidated Shareholder Derivative Complaint in August 2017.
Three actions by public entities were filed, including complaints by the County of Los Angeles, on behalf of itself and the people of the State of California, the California Attorney General, acting in an independent capacity and on behalf of the people of the State of California and the CARB, and the Los Angeles City Attorney alleging public nuisance, unfair competition, and violations
of California Health and Safety Code provisions regarding discharge of contaminants, among other things, which sought injunctive relief, abatement, civil penalties and damages. The County of Los Angeles also filed a petition seeking a writ of mandate requiring DOGGR and the State Oil and Gas Supervisor to comply with SB 380 and the California Environmental Quality Act, as well as declaratory and injunctive relief against their authorization allowing SoCalGas to inject natural gas at the facility.
In August 2018, SoCalGas entered into a settlement agreement with the Los Angeles City Attorney’s Office, the County of Los Angeles, the California Office of the Attorney General and CARB (collectively, the Government Plaintiffs) to settle these public entity actions and the Directive for payments and funding for environmental projects totaling $120 million, including $21 million in civil penalties (the Government Plaintiffs Settlement). Under the settlement agreement, SoCalGas also agreed to continue its fence-line methane monitoring program, establish a safety committee and hire an independent ombudsman to monitor and report on the safety at the facility. This settlement also fully resolves SoCalGas’ commitment to mitigate the actual natural gas released during the Leak and fulfills the requirements of the Governor’s Order, described below, for SoCalGas to pay for a mitigation program developed by CARB. The Government Plaintiffs Settlement was approved by the LA Superior Court in February 2019.
Separately, in February 2016, the Los Angeles County District Attorney’s Office filed a misdemeanor criminal complaint against SoCalGas seeking penalties and other remedies for alleged failure to provide timely notice of the Leak pursuant to California Health and Safety Code section 25510(a), Los Angeles County Code section 12.56.030, and Title 19 California Code of Regulations section 2703(a), and for allegedly violating California Health and Safety Code section 41700 prohibiting discharge of air contaminants that cause annoyance to the public. Pursuant to a settlement agreement with the Los Angeles County District Attorney’s Office, SoCalGas agreed to plead no contest to the notice charge under Health and Safety Code section 25510(a) and agreed to pay the maximum fine of $75,000, penalty assessments of approximately $233,500, and operational commitments estimated to cost approximately $6 million, reimbursements and assessments in exchange for the Los Angeles County District Attorney’s Office moving to dismiss the remaining counts at sentencing and settling the complaint (the District Attorney Settlement). SoCalGas completed the commitments and obligations under the District Attorney Settlement, and in November 2016, the LA Superior Court approved the settlement and entered judgment on the notice charge. Certain individuals who object to the settlement petitioned the Court of Appeal to vacate the judgment, contending they should be granted restitution. In July 2019, the Court of Appeal denied the petition in part, but remanded the matter to the trial court to permit the petitioners to prove damages stemming only from the three-day delay in reporting the Leak.
The costs of defending against these civil and criminal lawsuits, and any compensatory, statutory or punitive damages, restitution, and civil, administrative and criminal fines, penalties and other costs, if awarded or imposed, as well as the costs of mitigating the actual natural gas released, could be significant. If any of these costs are not covered by insurance (including any costs in excess of applicable policy limits), if there are significant delays in receiving insurance recoveries, or if the insurance recoveries are subject to income taxes while the associated costs are not tax deductible, such amounts could have a material adverse effect on SoCalGas’ and Sempra Energy’s cash flows, financial condition and results of operations.
Regulatory Proceedings. In January 2016, DOGGR and the CPUC selected Blade to conduct, under their supervision, an independent analysis of the technical root cause of the Leak, to be funded by SoCalGas. In May 2019, Blade released its report regarding its root cause analysis of the Leak. The report concludes that the Leak occurred on the morning of October 23, 2015, beginning with an axial rupture of the production casing of the well caused by external microbial corrosion as a result of contact with groundwater, followed within hours by the complete separation of the casing. Blade asserts that attempts to stop the Leak were unsuccessful due to insufficient kill fluid density and pump rates. Blade’s report assesses whether SoCalGas complied with gas storage regulations in existence at the time of the Leak, and did not identify any instances of non-compliance by SoCalGas. Blade concludes that SoCalGas’ compliance activities conducted prior to the Leak did not find indications of a casing integrity issue. In Blade’s opinion, however, there were measures, none of which were required by gas storage regulations at the time, that could have been taken to aid in the early identification of corrosion and that, in Blade’s opinion, would have prevented or mitigated the Leak. The report also identified well safety practices and regulations that have since been adopted by DOGGR and implemented by SoCalGas, which address most of the root cause of the Leak identified during Blade’s investigation.
In February 2017, the CPUC opened a proceeding pursuant to SB 380 to determine the feasibility of minimizing or eliminating the use of the Aliso Canyon natural gas storage facility, while still maintaining energy and electric reliability for the region. The CPUC indicated it intends to conduct the proceeding in two phases, with Phase 1 undertaking a comprehensive effort to develop the appropriate analyses and scenarios to evaluate the impact of reducing or eliminating the use of the Aliso Canyon natural gas storage facility and Phase 2 using those analyses and scenarios to evaluate the impacts of reducing or eliminating the use of the Aliso Canyon natural gas storage facility.
The order establishing the scope of the proceeding expressly excludes issues with respect to air quality, public health, causation, culpability or cost responsibility regarding the Leak. In January 2019, the CPUC concluded Phase 1 of the proceeding by
establishing a framework for the hydraulic, production cost and economic modeling assumptions for the potential reduction in usage or elimination of the Aliso Canyon natural gas storage facility. Phase 2 of the proceeding, which will evaluate the impacts of reducing or eliminating the Aliso Canyon natural gas storage facility using the established framework and models, began in the first quarter of 2019. The CPUC has indicated that it expects to issue its report in 2020.
In June 2019, the CPUC opened an OII to consider penalties against SoCalGas for the Leak. In September 2019, the CPUC issued an order bifurcating the proceeding into two phases and establishing the scope and schedule for the first phase. The issues to be determined in the first phase are whether SoCalGas violated Public Utilities Code section 451 or other laws, CPUC orders or decisions, rules or requirements, whether SoCalGas engaged in unreasonable and/or imprudent practices with respect to its operation and maintenance of the Aliso Canyon natural gas storage facility or its related record-keeping practices, whether SoCalGas cooperated sufficiently with the Safety Enforcement Division and Blade during the pre-formal investigation, and whether any of the mitigation proposed by Blade should be implemented to the extent not already done. The second phase will consider whether SoCalGas should be sanctioned for the Leak and what penalties, if any, should be imposed for any violations proven in the first phase, as well as determine the amounts of various costs incurred by SoCalGas and other parties in connection with the Leak and the ratemaking treatment or other disposition of such costs.
The costs to respond to this investigation and any sanctions, fines, penalties or other remedies imposed by the CPUC could be significant and may not be covered completely by insurance (including costs in excess of applicable policy limits). Such amounts could have a material adverse effect on SoCalGas’ and Sempra Energy’s cash flows, financial condition and results of operations.
Governmental Investigations and Orders and Additional Regulation. Various governmental agencies, including DOE, DOGGR, DPH, South Coast Air Quality Management District, CARB, Los Angeles Regional Water Quality Control Board, California Division of Occupational Safety and Health, CPUC, PHMSA, EPA, Los Angeles County District Attorney’s Office and California Attorney General’s Office, have investigated or are investigating this incident.
In January 2016, the Governor of the State of California proclaimed a state of emergency in Los Angeles County due to the Leak. The proclamation ordered various actions with respect to the Leak, including: (1) applicable agencies must convene an independent panel of scientific and medical experts to review public health concerns stemming from the Leak and evaluate whether additional measures are needed to protect public health; (2) the CPUC must ensure that SoCalGas covers costs related to the Leak and its response while protecting ratepayers; (3) CARB must develop a program, to be funded by SoCalGas, to fully mitigate the Leak’s emissions of methane; and (4) DOGGR, CPUC, CARB and the CEC must submit to the Governor’s Office a report that assesses the long-term viability of natural gas storage facilities in California. The Government Plaintiffs Settlement described above satisfies the mitigation requirement of the Governor’s emergency proclamation.
Cost Estimates and Accounting Impact. At September 30, 2019, SoCalGas estimates its costs related to the Leak are $1,099 million (the cost estimate), which includes $1,069 million of costs recovered or probable of recovery from insurance. Approximately 52 percent of the cost estimate is for the temporary relocation program (including cleaning costs and certain labor costs). The remaining portion of the cost estimate includes costs incurred to defend litigation, the costs of the government-ordered response to the Leak including the costs for an independent third party to conduct a root cause analysis, efforts to control the well, to mitigate the natural gas released, the cost of replacing the lost gas, the costs of settlements with government entities and other costs. The cost estimate does not include potential additional litigation costs, regulatory-related costs or other costs described below, which could be material. SoCalGas adjusts the cost estimate as additional information becomes available. A substantial portion of the cost estimate has been paid, and $45 million is accrued in Reserve for Aliso Canyon Costs and $9 million is accrued in Deferred Credits and Other as of September 30, 2019 on SoCalGas’ and Sempra Energy’s Condensed Consolidated Balance Sheets.
As of September 30, 2019, we recorded the expected recovery of the cost estimate related to the Leak of $354 million as Insurance Receivable for Aliso Canyon Costs on SoCalGas’ and Sempra Energy’s Condensed Consolidated Balance Sheets. This amount is net of insurance retentions and $715 million of insurance proceeds we received through September 30, 2019. The Insurance Receivable for Aliso Canyon Costs and insurance proceeds received to date relate to portions of the cost estimate described above, including temporary relocation and associated processing costs, control-of-well expenses, costs of the government-ordered response including for an independent third party to conduct a root cause analysis, the costs to settle certain claims as described above, the estimated costs to perform obligations pursuant to settlement of some of those claims, legal costs and lost gas. If we were to conclude that this receivable or a portion of it is no longer probable of recovery from insurers, some or all of this receivable would be charged against earnings, which could have a material adverse effect on SoCalGas’ and Sempra Energy’s cash flows, financial condition and results of operations.
As described in “Civil and Criminal Litigation” above, the actions seek compensatory, statutory and punitive damages, restitution, and civil, administrative and criminal fines, penalties and other costs, which, except for the amounts paid or estimated to settle certain actions as described above, are not included in the cost estimate as it is not possible at this time to predict the outcome of
these actions or reasonably estimate the amount of damages, restitution or civil, administrative or criminal fines, penalties or other costs that may be imposed. The recorded amounts above also do not include future legal costs necessary to defend litigation, and other potential costs that we currently do not anticipate incurring or that we cannot reasonably estimate. Furthermore, the cost estimate does not include any sanctions, fines, penalties or other costs that may be imposed by the CPUC in connection with the OII opened in June 2019 and certain other costs incurred by Sempra Energy associated with defending against shareholder derivative lawsuits.
Insurance. Excluding directors’ and officers’ liability insurance, we have at least four kinds of insurance policies that together we estimate provide between $1.2 billion to $1.4 billion in insurance coverage, depending on the nature of the claims. At September 30, 2019, SoCalGas’ estimate of costs related to the Leak of $1,099 million include $1,069 million of costs recovered or probable of recovery from insurance. This estimate may rise significantly as more information becomes available. Costs not included in the $1,099 million cost estimate could be material. We cannot predict all of the potential categories of costs or the total amount of costs that we may incur as a result of the Leak. Subject to various policy limits, exclusions and conditions, based on what we know as of the filing date of this report, we believe that costs in the following categories should be recoverable through insurance: costs incurred for temporary relocation and associated processing costs (including cleaning costs and certain labor costs), costs to address the Leak and stop or reduce emissions, costs of the government-ordered response to the Leak including the costs for an independent third party to conduct a root cause analysis, the value of lost gas, costs incurred to mitigate the actual natural gas released, costs associated with litigation and claims by nearby residents and businesses, and, in some circumstances depending on their nature and manner of assessment, fines and penalties. We have been communicating with our insurance carriers and, as discussed above, we have received insurance payments for portions of the costs described above, including temporary relocation and associated processing costs, control-of-well expenses, costs of the government-ordered response to the Leak, legal costs and lost gas. We intend to pursue the full extent of our insurance coverage for the costs we have incurred or may incur. There can be no assurance that we will be successful in obtaining additional insurance recovery for these costs.
If any costs are not covered by insurance (including any costs in excess of applicable policy limits), if there are significant delays in receiving insurance recoveries, or if the insurance recoveries are subject to income taxes while the associated costs are not tax deductible, such amounts could have a material adverse effect on SoCalGas’ and Sempra Energy’s cash flows, financial condition and results of operations.
Natural Gas Storage Operations and Reliability. Natural gas withdrawn from storage is important for service reliability during peak demand periods, including peak electric generation needs in the summer and heating needs in the winter. The Aliso Canyon natural gas storage facility, with a capacity of 86 Bcf (representing 63 percent of SoCalGas’ natural gas storage capacity), is the largest SoCalGas storage facility and an important element of SoCalGas’ delivery system. As a result of the Leak, SoCalGas suspended injection of natural gas into the Aliso Canyon natural gas storage facility beginning in October 2015, and following a comprehensive safety review and authorization by DOGGR and the CPUC’s Executive Director, resumed limited injection operations in July 2017.
During the suspension period, SoCalGas advised the California ISO, CEC, CPUC and PHMSA of its concerns that the inability to inject natural gas into the Aliso Canyon natural gas storage facility posed a risk to energy reliability in Southern California. Following the resumption of injection operations, the CPUC has issued a series of directives to SoCalGas specifying the range of working gas to be maintained in the Aliso Canyon natural gas storage facility to help ensure safety and reliability for the region and just and reasonable rates in California, the most recent of which, issued in July 2018, directed SoCalGas to maintain up to 34 Bcf of working gas. Limited withdrawals of natural gas from the facility were made in 2018 and 2019 to augment natural gas supplies during critical demand periods. In July 2019, the CPUC issued a protocol authorizing withdrawals of natural gas from the facility if gas supply is low in the region, to maintain system reliability and price stability.
If the Aliso Canyon natural gas storage facility were to be permanently closed, or if future cash flows were otherwise insufficient to recover its carrying value, it could result in an impairment of the facility and significantly higher than expected operating costs and/or additional capital expenditures, and natural gas reliability and electric generation could be jeopardized. At September 30, 2019, the Aliso Canyon natural gas storage facility had a net book value of $771 million. Any significant impairment of this asset could have a material adverse effect on SoCalGas’ and Sempra Energy’s results of operations for the period in which it is recorded. Higher operating costs and additional capital expenditures incurred by SoCalGas may not be recoverable in customer rates and could have a material adverse effect on SoCalGas’ and Sempra Energy’s cash flows, financial condition and results of operations.
Sempra Mexico
Property Disputes and Permit Challenges
Energía Costa Azul. IEnova has been engaged in a long-running land dispute relating to property adjacent to its ECA LNG terminal near Ensenada, Mexico. A claimant to the adjacent property filed complaints in the federal Agrarian Court challenging the refusal of SEDATU in 2006 to issue a title to him for the disputed property. In November 2013, the federal Agrarian Court ordered that SEDATU issue the requested title and cause it to be registered. Both SEDATU and IEnova challenged the ruling, due to lack of notification of the underlying process. In May 2019, a federal court in Mexico reversed the ruling. IEnova expects additional proceedings regarding the claims.
Several administrative challenges are pending in Mexico before the Mexican environmental protection agency and the Federal Tax and Administrative Courts seeking revocation of the environmental impact authorization issued to ECA in 2003. These cases generally allege that the conditions and mitigation measures in the environmental impact authorization are inadequate and challenge findings that the activities of the terminal are consistent with regional development guidelines.
Additionally, in August 2018, a claimant filed a challenge in the federal district court in Ensenada, Baja California in relation to the environmental and social impact permits issued to ECA in September 2017 and December 2017, respectively, to allow natural gas liquefaction activities at the ECA LNG terminal. The court issued a provisional injunction on September 28, 2018 and maintained that provisional injunction at an April 11, 2019 hearing. In December 2018, the relevant Mexican regulators approved modifications to the environmental permit that facilitate the development of the proposed natural gas liquefaction facility at the ECA LNG terminal in two phases. On May 17, 2019, the court canceled the provisional injunction. The claimant has appealed the court’s decision. That appeal and the claimant’s underlying challenge to the permits remain pending.
Cases involving two parcels of real property have been filed against ECA. In one case, filed in the federal Agrarian Court in 2006, the plaintiffs seek to annul the recorded property title for a parcel on which the ECA LNG terminal is situated and to obtain possession of a different parcel that allegedly sits in the same place. Another civil complaint filed in the state court was served in April 2012 seeking to invalidate the contract by which ECA purchased another of the terminal parcels, on the grounds the purchase price was unfair; the plaintiff filed a second complaint in 2013 in the federal Agrarian Court seeking an order that SEDATU issue title to her. In January 2016, the federal Agrarian Court ruled against the plaintiff, and the plaintiff appealed the ruling. In May 2018, the state court dismissed the civil complaint, and the plaintiff has appealed. IEnova expects further proceedings on these two matters.
An unfavorable final decision on these property disputes or permit challenges could materially and adversely affect our existing natural gasification operations and our planned natural gas liquefaction projects currently in development at ECA.
Guaymas-El Oro Segment of the Sonora Pipeline. IEnova’s Sonora natural gas pipeline consists of two segments, the Sasabe-Puerto Libertad-Guaymas segment, and the Guaymas-El Oro segment. Each segment has its own service agreement with the CFE. In 2015, the Yaqui tribe, with the exception of some members living in the Bácum community, granted its consent and a right-of-way easement agreement for the construction of the Guaymas-El Oro segment of the Sonora natural gas pipeline that crosses its territory. Representatives of the Bácum community filed a legal challenge in Mexican federal court demanding the right to withhold consent for the project, the stoppage of work in the Yaqui territory and damages. In 2016, the judge granted a suspension order that prohibited the construction of such segment through the Bácum community territory. Because the pipeline does not pass through the Bácum community, IEnova did not believe the 2016 suspension order prohibited construction in the remainder of the Yaqui territory. Construction of the Guaymas-El Oro segment was completed, and commercial operations began in May 2017.
Following the start of commercial operations of the Guaymas-El Oro segment, IEnova reported damage to the Guaymas-El Oro segment of the Sonora pipeline in the Yaqui territory that has made that section inoperable since August 23, 2017 and, as a result, IEnova declared a force majeure event. In 2017, an appellate court ruled that the scope of the 2016 suspension order encompassed the wider Yaqui territory, which has prevented IEnova from making repairs to put the pipeline back in service. In July 2019, a federal district court ruled in favor of IEnova and held that the Yaqui tribe was properly consulted and that consent from the Yaqui tribe was properly received. Representatives of the Bácum community appealed this decision, causing the suspension order preventing IEnova from repairing the damage to the Guaymas-El Oro segment of the Sonora pipeline in the Yaqui territory to remain in place until the appeals process is exhausted.
IEnova exercised its rights under the contract, which included seeking force majeure payments for the two-year period such force majeure payments were required to be made, which ended on August 22, 2019.
In July 2019, the CFE filed a request for arbitration generally to nullify certain contract terms that provide for fixed capacity payments in instances of force majeure and made a demand for substantial damages in connection with the force majeure event. In September 2019, the arbitration process ended when IEnova and the CFE reached an agreement to restart natural gas transportation service on the earlier of completion of repair of the damaged pipeline or January 15, 2020, and to modify the tariff structure and extend the term of the contract by 10 years. Under the revised agreement, the CFE will resume making payments only when the damaged section of the Guaymas-El Oro segment of the Sonora pipeline is repaired. If the pipeline is not repaired
by January 15, 2020 and the parties do not agree on a new service start date, IEnova retains the right to terminate the contract and seek to recover its reasonable and documented costs and lost profits.
If IEnova is unable to make such repairs and resume operations in the Guaymas-El Oro segment of the Sonora pipeline within this time frame or if IEnova terminates the contract and is unable to obtain recovery, there may be a material adverse impact on Sempra Energy’s results of operations and cash flows and our ability to recover the carrying value of our investment. The Sasabe-Puerto Libertad-Guaymas segment of the Sonora pipeline remains in full operation and is not impacted by these developments.
Sur de Texas-Tuxpan Marine Pipeline. Sempra Mexico has a 40-percent interest in IMG, a JV with a subsidiary of TC Energy to build, own and operate the Sur de Texas-Tuxpan natural gas marine pipeline in Mexico. The JV has an agreement to provide the CFE with natural gas transportation services under a 25-year agreement, denominated in U.S. dollars. IMG previously received force majeure payments from the CFE from November 2018 through April 2019, after construction delays extended the commercial operation date. In June 2019, the CFE filed a request for arbitration generally to nullify certain contract terms that provide for fixed capacity payments in instances of force majeure and made a demand for substantial damages in connection with the force majeure event. In September 2019, the JV and the CFE amended the gas transportation services agreement to modify the tariff structure and extend the term of the contract by 10 years, which ended the arbitration process. Construction and commissioning activities on the pipeline were completed in June 2019, and, in September 2019, IMG received acceptance from the CFE allowing the pipeline to enter commercial operation and for service under the gas transportation contract to commence.
Other Litigation
Sempra Energy holds an NCI in RBS Sempra Commodities, a limited liability partnership in the process of being liquidated. NatWest Markets plc, formerly RBS, our partner in the JV, paid an assessment of £86 million (approximately $138 million in U.S. dollars) in October 2014 to HMRC for denied VAT refund claims filed in connection with the purchase of carbon credit allowances by RBS SEE, a subsidiary of RBS Sempra Commodities. RBS SEE has since been sold to JP Morgan and later to Mercuria Energy Group, Ltd. HMRC asserted that RBS was not entitled to reduce its VAT liability by VAT paid on certain carbon credit purchases during 2009 because RBS knew or should have known that certain vendors in the trading chain did not remit their own VAT to HMRC. After paying the assessment, RBS filed a Notice of Appeal of the assessment with the First-Tier Tribunal. Trial on the matter has been scheduled between November 2, 2020 and December 11, 2020.
In 2015, liquidators filed a claim in the High Court of Justice against RBS and Mercuria Energy Europe Trading Limited (the Defendants) on behalf of 10 companies (the Liquidating Companies) that engaged in carbon credit trading via chains that included a company that traded directly with RBS SEE. The claim alleges that the Defendants’ participation in the purchase and sale of carbon credits resulted in the Liquidating Companies’ carbon credit trading transactions creating a VAT liability they were unable to pay, and that the Defendants are liable to provide for equitable compensation due to dishonest assistance and for compensation under the U.K. Insolvency Act of 1986. Trial on the matter was held in June and July of 2018, at the close of which the Liquidating Companies asserted that the Defendants were liable to the Liquidating Companies in the amount of £71.5 million (approximately $88 million in U.S. dollars at September 30, 2019) for dishonest assistance and, to the extent that claim is unsuccessful, to the liquidators in the same amount under the U.K. Insolvency Act of 1986. If the High Court of Justice finds the Defendants liable, it will determine the amount. JP Morgan has notified us that Mercuria Energy Group, Ltd. has sought indemnity for the claim, and JP Morgan has in turn sought indemnity from Sempra Energy and RBS.
While the ultimate outcome remains uncertain, in the third quarter of 2018, we impaired our remaining $65 million equity method investment in RBS Sempra Commodities.
Certain EFH subsidiaries that we acquired as part of the Merger are defendants in personal injury lawsuits brought in state courts throughout the U.S. As of October 28, 2019, 103 such lawsuits are pending and 1,608 such lawsuits have been filed but not served. These cases allege illness or death as a result of exposure to asbestos in power plants designed and/or built by companies whose assets were purchased by predecessor entities to the EFH subsidiaries, and generally assert claims for product defects, negligence, strict liability and wrongful death. They seek compensatory and punitive damages. Additionally, in connection with the EFH bankruptcy proceeding, approximately 28,000 proofs of claim were filed on behalf of persons who allege exposure to asbestos under similar circumstances and assert the right to file such lawsuits in the future. We anticipate additional lawsuits will be filed. None of these claims or lawsuits were discharged in the EFH bankruptcy proceeding.
We are also defendants in ordinary routine litigation incidental to our businesses, including personal injury, employment litigation, product liability, property damage and other claims. Juries have demonstrated an increasing willingness to grant large awards, including punitive damages, in these types of cases.
LEASES
A lease exists when a contract conveys the right to control the use of an identified asset for a period of time in exchange for consideration. We determine if an arrangement is or contains a lease at inception of the contract.
Some of our lease agreements contain nonlease components, which represent activities that transfer a separate good or service to the lessee. As the lessee for both operating and finance leases, we combine lease components and nonlease components for all existing classes of underlying assets as a single lease component, whereby fixed or in-substance fixed payments allocable to the nonlease component are accounted for as part of the related lease liability and ROU asset. As the lessor, if the timing and pattern of transfer of the lease components and nonlease components are the same, and the lease component would be classified as an operating lease if accounted for separately, we combine the lease components and nonlease components.
Lessee Accounting
We have operating and finance leases for real and personal property (including office space, land, fleet vehicles, machinery and equipment, warehouses and other operational facilities) and PPAs with renewable energy and peaker plant facilities.
Some of our leases include options to extend the lease terms for up to 25 years, while others include options to terminate the lease within one year. Our lease liabilities and ROU assets are based on lease terms that may include such options to extend or terminate the lease when it is reasonably certain that we will exercise that option.
Certain of our contracts are short-term leases, which have a lease term of 12 months or less at lease commencement. We do not recognize a lease liability or ROU asset arising from short-term leases for all existing classes of underlying assets. In such cases, we recognize short-term lease costs on a straight-line basis over the lease term. Our short-term lease costs for the period reasonably reflect our short-term lease commitments.
Certain of our leases contain escalation clauses requiring annual increases in rent ranging from 2 percent to 5 percent or based on the Consumer Price Index. The rentals payable under these leases may increase by a fixed amount each year or by a percentage of a base year. Variable lease payments that are based on an index or rate are included in the initial measurement of our lease liability and ROU asset based on the index or rate at lease commencement and are not remeasured because of changes to the index or rate. Rather, changes to the index or rate are treated as variable lease payments and recognized in the period in which the obligation for those payments is incurred.
Similarly, PPAs for the purchase of renewable energy at SDG&E require lease payments based on a stated rate per MWh produced by the facilities, and we are required to purchase substantially all the output from the facilities. SDG&E is required to pay additional amounts for capacity charges and actual purchases of energy that exceed the minimum energy commitments. Under these contracts, we do not recognize a lease liability or ROU asset for leases for which there are no fixed lease payments. Rather, these variable lease payments are recognized separately as variable lease costs.
As of the lease commencement date, we recognize a lease liability for our obligation to make future lease payments, which we initially measure at present value using our incremental borrowing rate at the date of lease commencement, unless the rate implicit in the lease is readily determinable. We determine our incremental borrowing rate based on the rate of interest that we would have to pay to borrow, on a collateralized basis over a similar term, an amount equal to the lease payments in a similar economic environment. We also record a ROU asset for our right to use the underlying asset, which is initially equal to the lease liability and adjusted for lease payments made at or before lease commencement, lease incentives, and any initial direct costs. Like other long-lived assets, we test ROU assets for recoverability whenever events or changes in circumstances have occurred that may affect the recoverability or the estimated useful lives of the ROU assets.
For our operating leases, our non-regulated entities recognize a single lease cost on a straight-line basis over the lease term in operating expenses. The California Utilities recognize this single lease cost on a basis that is consistent with the recovery of such costs in accordance with U.S. GAAP governing rate-regulated operations.
For our finance leases, the interest expense on the lease liability and amortization of the ROU asset are accounted for separately. Our non-regulated entities use the effective interest rate method to account for the imputed interest on the lease liability and amortize the ROU asset on a straight-line basis over the lease term. The California Utilities recognize amortization of the ROU asset on a basis that is consistent with the recovery of such costs in accordance with U.S. GAAP governing rate-regulated operations.
Our leases do not contain any material residual value guarantees, restrictions or covenants.
Classification of ROU assets and lease liabilities and the weighted-average remaining lease term and discount rate associated with operating and finance leases are summarized in the table below.
LESSEE INFORMATION ON THE CONDENSED CONSOLIDATED BALANCE SHEETS
(Dollars in millions)
 
September 30, 2019
 
Sempra Energy Consolidated
 
SDG&E
 
SoCalGas
Right-of-use assets:
 
 
 
 
 
Operating leases:
 
 
 
 
 
Right-of-use assets
$
595

 
$
126

 
$
99

 

 

 

Finance leases:
 
 
 
 
 
Property, plant and equipment
1,342

 
1,322

 
20

Accumulated depreciation
(57
)
 
(52
)
 
(5
)
Property, plant and equipment, net
1,285

 
1,270

 
15

Total right-of-use assets
$
1,880

 
$
1,396

 
$
114

 
 
 
 
 
 
Lease liabilities:
 
 
 
 
 
Operating leases:
 
 
 
 
 
Other current liabilities
$
47

 
$
22

 
$
19

Deferred credits and other
447

 
102

 
79

 
494

 
124

 
98

Finance leases:
 
 
 
 
 
Current portion of long-term debt and finance leases
24

 
19

 
5

Long-term debt and finance leases
1,261

 
1,251

 
10

 
1,285

 
1,270

 
15

Total lease liabilities
$
1,779

 
$
1,394

 
$
113

 
 
 
 
 
 
Weighted-average remaining lease term (in years):
 
 
 
 
 
Operating leases
14

 
7

 
6

Finance leases
20

 
20

 
6

Weighted-average discount rate:
 
 
 
 
 
Operating leases
6.02
%
 
3.69
%
 
3.75
%
Finance leases
14.81
%
 
14.86
%
 
3.41
%


The components of lease costs were as follows:
LESSEE INFORMATION ON THE CONDENSED CONSOLIDATED STATEMENTS OF OPERATIONS(1)
(Dollars in millions)
 
 
 
 
 
 
 
Three months ended September 30, 2019
 
Nine months ended September 30, 2019
 
Sempra Energy Consolidated
 
SDG&E
 
SoCalGas
 
Sempra Energy Consolidated
 
SDG&E
 
SoCalGas
Operating lease costs
$
23

 
$
8

 
$
7

 
$
72

 
$
25

 
$
21

 

 

 

 
 
 
 
 
 
Finance lease costs:
 
 
 
 
 
 
 
 
 
 
 
Amortization of ROU assets
6

 
4

 
2

 
17

 
13

 
4

Interest on lease liabilities
47

 
47

 

 
141

 
141

 

Total finance lease costs
53

 
51

 
2

 
158

 
154

 
4

 
 
 
 
 
 
 
 
 
 
 
 
Short-term lease costs(2)
3

 
1

 

 
5

 
1

 

Variable lease costs(2)
156

 
155

 
1

 
396

 
389

 
7

Total lease costs
$
235

 
$
215

 
$
10

 
$
631

 
$
569

 
$
32

(1) 
Includes costs capitalized in PP&E.
(2) 
Short-term leases with variable lease costs are recorded and presented as variable lease costs.

Cash paid for amounts included in the measurement of lease liabilities was as follows:
LESSEE INFORMATION ON THE CONDENSED CONSOLIDATED STATEMENTS OF CASH FLOWS
(Dollars in millions)
 
Nine months ended September 30, 2019
 
Sempra Energy Consolidated
 
SDG&E
 
SoCalGas
Operating activities:
 
 
 
 
 
Cash paid for operating leases
$
81

 
$
25

 
$
21

Cash paid for finance leases
130

 
130

 

Financing activities:
 
 
 
 
 
Cash paid for finance leases
17

 
13

 
4

Increase in operating lease obligations for right-of-use assets
571

 
147

 
117

Increase in finance lease obligations for investment in PP&E
27

 
12

 
15


The table below presents the maturity analysis of our lease liabilities and reconciliation to the present value of lease liabilities:
LESSEE MATURITY ANALYSIS OF LIABILITIES
(Dollars in millions)
 
September 30, 2019
 
Sempra Energy Consolidated
 
SDG&E
 
SoCalGas
 
Operating leases
 
Finance leases
 
Operating leases
 
Finance leases
 
Operating leases
 
Finance leases
2019 (excluding first nine months of 2019)
$
17

 
$
50

 
$
7

 
$
48

 
$
6

 
$
2

2020
72

 
195

 
26

 
191

 
23

 
4

2021
69

 
192

 
26

 
190

 
20

 
2

2022
62

 
191

 
22

 
189

 
17

 
2

2023
53

 
191

 
17

 
189

 
13

 
2

Thereafter
494

 
2,811

 
43

 
2,807

 
30

 
4

Total undiscounted lease payments
767

 
3,630

 
141

 
3,614

 
109

 
16

Less: imputed interest
(273
)
 
(2,345
)
 
(17
)
 
(2,344
)
 
(11
)
 
(1
)
Total lease liabilities
494

 
1,285

 
124

 
1,270

 
98

 
15

Less: current lease liabilities
(47
)
 
(24
)
 
(22
)
 
(19
)
 
(19
)
 
(5
)
Long-term lease liabilities
$
447

 
$
1,261

 
$
102

 
$
1,251

 
$
79

 
$
10



Leases that Have Not Yet Commenced
SDG&E has PPAs for three battery storage facilities that are currently under construction. When construction is complete and delivery of contracted power commences, which is scheduled to occur in 2019 through 2021, we will account for the PPAs as finance leases. The future minimum lease payments are expected to be $1 million per year in 2020 through 2023 and $18 million thereafter. These PPAs expire at various dates from 2031 through 2039.
SDG&E and SoCalGas have lease agreements for future acquisitions of fleet vehicles with an aggregate maximum lease limit of $180 million. SDG&E and SoCalGas have utilized $53 million and $74 million, respectively, as of September 30, 2019.
Lease Disclosures Under Previous U.S. GAAP
The table below presents the future minimum lease payments under previous U.S. GAAP:
FUTURE MINIMUM LEASE PAYMENTS
(Dollars in millions)
 
December 31, 2018
 
Sempra Energy Consolidated
 
SDG&E
 
SoCalGas
 
Build-to-suit lease
 
Operating leases
 
Capital leases
 
Operating leases
 
Capital leases
 
Operating leases
 
Capital leases
2019
$
10

 
$
77

 
$
215

 
$
23

 
$
212

 
$
26

 
$
3

2020
11

 
55

 
210

 
22

 
210

 
22

 

2021
11

 
53

 
211

 
22

 
211

 
21

 

2022
11

 
50

 
211

 
21

 
211

 
20

 

2023
11

 
42

 
211

 
17

 
211

 
16

 

Thereafter
217

 
253

 
3,196

 
48

 
3,196

 
28

 

Total undiscounted lease payments
$
271

 
$
530

 
4,254

 
$
153

 
4,251

 
$
133

 
3

Less: estimated executory costs
 
 
 
 
(480
)
 
 
 
(480
)
 
 
 

Less: imputed interest
 
 
 
 
(2,483
)
 
 
 
(2,483
)
 
 
 

Total future minimum lease payments
 
 
 
 
$
1,291

 
 
 
$
1,288

 
 
 
$
3


Lessor Accounting
Sempra Mexico is a lessor for certain of its natural gas and ethane pipelines, compressor stations and LPG storage facilities. These operating leases expire at various dates from 2021 through 2039.
Sempra Mexico expects to continue to derive value from the underlying assets associated with its pipelines following the end of their respective lease terms based on the expected remaining useful life, expected market conditions and plans to re-market and re-contract the underlying assets.
Generally, we recognize operating lease income on a straight-line basis over the lease term and evaluate the underlying asset for impairment. Certain of our leases contain rate adjustments or are based on foreign currency exchange rates that may result in lease payments received that vary from one period to the next.
We provide information below for leases for which we are the lessor.
LESSOR INFORMATION – SEMPRA ENERGY
 
(Dollars in millions)
 
 
September 30, 2019
Assets subject to operating leases:
 
Property, plant and equipment(1)
$
1,112

Accumulated depreciation
(181
)
Property, plant and equipment, net
$
931

Maturity analysis of operating lease payments:
 
2019 (excluding first nine months of 2019)
$
50

2020
199

2021
199

2022
199

2023
199

Thereafter
2,588

Total undiscounted cash flows
$
3,434

(1)  
Included in Machinery and Equipment — Pipelines and Storage within the major functional categories of PP&E.

LESSOR INFORMATION ON THE CONDENSED CONSOLIDATED STATEMENTS OF OPERATIONS  SEMPRA ENERGY
(Dollars in millions)
 
Three months ended September 30,
 
Nine months ended September 30,
 
2019
 
2018
 
2019
 
2018
Minimum lease payments
$
51

 
$
47

 
$
150

 
$
143

Variable lease payments

 
26

 
6

 
63

Total revenues from operating leases
$
51

 
$
73

 
$
156

 
$
206

 
 
 
 
 
 
 
 
Depreciation expense
$
10

 
$
19

 
$
29

 
$
55


CONTRACTUAL COMMITMENTS
We discuss below significant changes in the first nine months of 2019 to contractual commitments discussed in Notes 1 and 16 of the Notes to Consolidated Financial Statements in the Annual Report.
LNG Purchase Agreement
Sempra LNG has a sale and purchase agreement for the supply of LNG to the ECA terminal. The commitment amount is calculated using a predetermined formula based on estimated forward prices of the index applicable from 2019 to 2029. At September 30, 2019, we expect the commitment amount to decrease by $281 million in 2019, $9 million in 2020, $16 million in 2021, $8 million in 2022, $1 million in 2023 and $24 million thereafter (through contract termination in 2029) compared to December 31, 2018, reflecting changes in estimated forward prices since December 31, 2018 and actual transactions for the first nine months of 2019. These LNG commitment amounts are based on the assumption that all LNG cargoes, less those already confirmed to be diverted, under the agreement are delivered. Although this agreement specifies a number of cargoes to be delivered, under its terms, the customer may divert certain cargoes, which would reduce amounts paid under the agreement by Sempra LNG. Actual LNG purchases in the current and prior years have been significantly lower than the maximum amount provided under the agreement due to the customer electing to divert cargoes as allowed by the agreement.
Purchased-Power Contracts
SDG&E’s commitments under purchased-power contracts increased by $372 million since December 31, 2018, primarily due to $262 million from the resource adequacy capacity agreement that SDG&E entered into with OMEC LLC, which we discuss in “Variable Interest Entities – SDG&E – Otay Mesa VIE” in Note 1. Net future payments are expected to increase by $13 million in 2019, $45 million in 2020, $52 million in 2021, $69 million in 2022, $74 million in 2023, and $119 million thereafter compared to December 31, 2018.
CONCENTRATION OF CREDIT RISK
We maintain credit policies and systems designed to manage our overall credit risk. These policies include an evaluation of potential counterparties’ financial condition and an assignment of credit limits. These credit limits are established based on risk and return considerations under terms customarily available in the industry. We grant credit to utility customers and counterparties, substantially all of whom are located in our service territory, which covers most of Southern California and a portion of central California for SoCalGas, and all of San Diego County and an adjacent portion of Orange County for SDG&E. Sempra Mexico also grants credit to its utility customers and counterparties in Mexico.
Projects and businesses owned or partially owned by Sempra Energy place significant reliance on the ability of their suppliers, customers and partners to perform on long-term agreements and on our ability to enforce contract terms in the event of nonperformance. We consider many factors, including the negotiation of supplier and customer agreements, when we evaluate and approve development projects and investment opportunities.