XML 101 R64.htm IDEA: XBRL DOCUMENT v3.7.0.1
COMMITMENTS AND CONTINGENCIES - CONTRACTUAL COMMITMENTS (Details)
$ in Millions
3 Months Ended
Apr. 25, 2017
USD ($)
Mar. 13, 2017
USD ($)
Mar. 31, 2017
USD ($)
MW
Unrecorded Unconditional Purchase Obligation [Line Items]      
Settlement amount   $ 118  
Sempra LNG & Midstream [Member] | Natural Gas Contracts [Member]      
Unrecorded Unconditional Purchase Obligation [Line Items]      
Increase (decrease) in commitment amount     $ (90)
Increase (decrease) in commitment amount, 2017     (77)
Increase (decrease) in commitment amount, 2018     (13)
Sempra LNG & Midstream [Member] | Liquefied Natural Gas Contracts [Member]      
Unrecorded Unconditional Purchase Obligation [Line Items]      
Increase (decrease) in commitment amount, 2017     (174)
Increase (decrease) in commitment amount, 2018     (41)
Increase (decrease) in commitment amount, 2019     (32)
Increase (decrease) in commitment amount, 2020     (38)
Increase (decrease) in commitment amount, 2021     (40)
Increase (decrease) in commitment amount, thereafter     (677)
San Diego Gas and Electric Company [Member]      
Unrecorded Unconditional Purchase Obligation [Line Items]      
Settlement amount   $ 24  
Increase (decrease) in commitment amount     68
Increase (decrease) in commitment amount, 2017     31
Increase (decrease) in commitment amount, 2018     42
Increase (decrease) in commitment amount, 2019     (2)
Increase (decrease) in commitment amount, 2020     3
Increase (decrease) in commitment amount, 2021     1
Increase (decrease) in commitment amount, thereafter     (7)
San Diego Gas and Electric Company [Member] | Purchased Power Contracts [Member]      
Unrecorded Unconditional Purchase Obligation [Line Items]      
2017     0
2018     88
2019     105
2020     105
2021     105
Thereafter     1,706
Total minimum lease payments     2,109
Less: interest     (1,559)
Present value of net minimum lease payments     $ 550
San Diego Gas and Electric Company [Member] | Intermediate Stage Power Plant Facility [Member]      
Unrecorded Unconditional Purchase Obligation [Line Items]      
Term of power purchase agreement     20 years
Power generating capacity | MW     500
Subsequent Event [Member] | Sempra LNG & Midstream [Member]      
Unrecorded Unconditional Purchase Obligation [Line Items]      
Settlement amount $ 57