CALIFORNIA UTILITIES' REGULATORY MATTERS - SCHEDULE OF UTILITY PROJECTS 2 (Details) - Sunrise Powerlink Electric Transmission Line [Member] - San Diego Gas and Electric Company [Member]
$ in Thousands
Sep. 30, 2015
USD ($)
Schedule Of Utility Projects [Line Items]  
Final Status Report $ 1,887,400
2008 CPUC Approval Decision 1,883,000
Difference 4,400
Construction Costs And AFUDC [Member]  
Schedule Of Utility Projects [Line Items]  
Final Status Report 1,490,900
2008 CPUC Approval Decision 1,594,200
Difference (103,300)
Undergrounding On Alpine Boulevard [Member]  
Schedule Of Utility Projects [Line Items]  
Final Status Report 11,700
2008 CPUC Approval Decision 91,000
Difference (79,300)
Undergrounding Savings Per Quarter Mile 11,000
Mitigation And Monitoring Costs [Member]  
Schedule Of Utility Projects [Line Items]  
Final Status Report 384,800
2008 CPUC Approval Decision 197,800
Difference $ 187,000