XML 79 R15.htm IDEA: XBRL DOCUMENT v2.4.1.9
NUCLEAR PLANT
3 Months Ended
Mar. 31, 2015
Notes to Consolidated Financial Statements [Abstract]  
Nuclear Plant

NOTE 9. SAN ONOFRE NUCLEAR GENERATING STATION (SONGS)

SDG&E has a 20-percent ownership interest in SONGS, a nuclear generating facility near San Clemente, California, which ceased operations in June 2013. On June 6, 2013, Southern California Edison Company (Edison), the majority owner and operator of SONGS, notified SDG&E that it had reached a decision to permanently retire SONGS and seek approval from the Nuclear Regulatory Commission (NRC) to start the decommissioning activities for the entire facility. SONGS is subject to the jurisdiction of the NRC and the CPUC.

SDG&E, and each of the other owners, holds its undivided interest as a tenant in common in the property. Each owner is responsible for financing its share of expenses and capital expenditures. SDG&E’s share of operating expenses is included in Sempra Energy’s and SDG&E’s Condensed Consolidated Statements of Operations.

SONGS Outage and Retirement

Background

As part of the Steam Generator Replacement Project (SGRP), the steam generators were replaced in SONGS Units 2 and 3, and the Units returned to service in 2010 and 2011, respectively. Both Units were shut down in early 2012 after a water leak occurred in the Unit 3 steam generator. Edison concluded that the leak was due to unexpected wear from tube-to-tube contact. At the time the leak was identified, Edison also inspected and tested Unit 2 and subsequently found unexpected tube wear in Unit 2’s steam generator. In March 2012, in response to the shutdown of SONGS, the NRC issued a Confirmatory Action Letter (CAL) which, among other things, outlined the requirements for Edison to meet before the NRC would approve a restart of either of the Units.

In October 2012, Edison submitted a restart plan to the NRC proposing to operate Unit 2 at a reduced power level for a period of five months, at which time the Unit would be brought down for further inspection. Edison did not file a restart plan for Unit 3, pending further inspection and analysis of what repairs or modifications would be required to return the Unit to service in a safe manner. The NRC was reviewing the restart plan for Unit 2 proposed by Edison when in May 2013, the Atomic Safety and Licensing Board (ASLB), an adjudicatory arm of the NRC, concluded that the CAL process constituted a de facto license amendment proceeding that was subject to a public hearing. This conclusion by the ASLB resulted in further uncertainty regarding when a final decision might be made on restarting Unit 2.

The replacement steam generators were designed and provided by Mitsubishi Heavy Industries, Ltd., Mitsubishi Nuclear Energy Systems, Inc., and Mitsubishi Heavy Industries America, Inc. (collectively MHI). In July 2013, SDG&E filed a lawsuit against MHI seeking to recover damages SDG&E has incurred and will incur related to the design defects in the steam generators. In October 2013, Edison instituted arbitration proceedings against MHI seeking damages as well. We discuss these proceedings in Note 11.

Settlement Agreement to Resolve the CPUC’s Order Instituting Investigation (OII) into the SONGS Outage (SONGS OII)

SONGS OII

In November 2012, in response to the outage, the CPUC issued the SONGS OII, pursuant to California Public Utilities’ Code Section 455.5, which applies to cost recovery issues resulting from long-term outages of operating assets. The SONGS OII consolidated most SONGS outage-related issues into a single proceeding. The SONGS OII, among other things, designated all revenues associated with the investment in, and operation of, SONGS since January 1, 2012 as subject to refund to customers, pending the outcome of all phases of the proceeding. The SONGS OII proceeding was intended to determine the ultimate recovery of the investment in SONGS and the costs incurred since the commencement of this outage, including purchased replacement power costs, which are typically recovered through the Energy Resource Recovery Account (ERRA).

Entry Into Settlement Agreement

Pursuant to CPUC rules concerning settlements, SDG&E, Edison, The Utility Reform Network (TURN), and the CPUC Office of Ratepayer Advocates (ORA) held a settlement conference in March 2014 to discuss the terms to resolve the SONGS OII, and in April 2014, SDG&E, along with Edison, TURN, ORA and two other intervenors who joined the Settlement Agreement to the SONGS OII proceeding (collectively, the Settling Parties), filed a Settlement Agreement with the CPUC. On September 5, 2014, the CPUC issued a ruling proposing specific changes that included, as they relate to SDG&E, greater ratepayer benefit from third party cost recoveries and funding of a research program to reduce greenhouse gas emissions at a shareholder cost of $1 million per year for 5 years.

On September 23, 2014, the Settling Parties executed an Amended and Restated Settlement Agreement (Amended Settlement Agreement), which amended the Settlement Agreement to adopt all of the modifications and clarifications requested in the CPUC ruling. On October 9, 2014, the CPUC issued a proposed decision approving the Amended Settlement Agreement, which was adopted by the CPUC as a final decision on November 20, 2014.

As approved by the CPUC, the Amended Settlement Agreement constitutes a complete and final resolution of the SONGS OII and related CPUC proceedings regarding the SGRP at SONGS and the related outage and subsequent shutdown of SONGS. This resolution also required the compliance filing referenced below under “Accounting and Financial Impacts.” The Amended Settlement Agreement does not affect on-going or future proceedings before the NRC, or litigation or arbitration related to potential future recoveries from third parties (except for the allocation to ratepayers of any recoveries as described below) or proceedings addressing decommissioning activities and costs.

In November 2014, in accordance with the Amended Settlement Agreement, SDG&E filed an advice letter seeking authority from the CPUC, among other things, to implement the terms and establish the revenue requirement in accordance with the Amended Settlement Agreement in rates starting January 1, 2015. In December 2014, the CPUC approved the advice letter and authorized SDG&E to update rates accordingly, subject to revision pending the results of a CPUC review of the changes to the revenue requirement proposed by SDG&E for consistency with the terms of the approved settlement decision. In March 2015, SDG&E received a final disposition letter from the CPUC confirming that SDG&E’s proposed rate changes were in compliance with the approved settlement decision.

In April 2015, a petition for modification (PFM) was filed with the CPUC by Alliance for Nuclear Responsibility (A4NR), an intervenor in the SONGS OII proceeding, regarding the CPUC decision approving the Amended Settlement Agreement. SDG&E is unable to determine what actions the CPUC will take in response to the PFM.

We discuss the terms of the Amended Settlement Agreement in Note 13 of the Notes to Consolidated Financial Statements in the Annual Report.

Accounting and Financial Impacts

Through March 31, 2015, the cumulative after-tax loss from plant closure recorded by Sempra Energy and SDG&E is $127 million, including a reduction in the after-tax loss of $13 million recorded in the first quarter of 2015 based on the CPUC’s approval in March 2015 of SDG&E’s compliance filing and establishment of the SONGS settlement revenue requirement.

In the second quarter of 2013, based on an initial assessment of the financial impact of the outcome of the SONGS OII proceeding, SDG&E reported an after-tax loss from plant closure of $119 million. In the first quarter of 2014, after entering into the Settlement Agreement, SDG&E recorded a $9 million increase in the after-tax loss. In the fourth quarter of 2014, based on the compliance filing regarding SDG&E’s annual revenue requirement and the timing of refunds to ratepayers, SDG&E recorded an increase to the loss, after-tax, of $12 million.

The regulatory asset for the expected recovery of SONGS costs, consistent with the Amended Settlement Agreement, is $294 million ($41 million current and $253 million long-term) at March 31, 2015 and is recorded on the Condensed Consolidated Balance Sheets in Other Current Assets and Regulatory Assets Noncurrent at Sempra Energy and in Regulatory Assets Current and Other Regulatory Assets Noncurrent at SDG&E.

NRC Proceedings

In December 2013, Edison received a final NRC Inspection Report that identified a violation for the failure to verify the adequacy of the thermal-hydraulic and flow-induced vibration design of the Unit 3 replacement steam generator. In January 2014, Edison provided a response to the NRC Inspection Report stating that MHI, as contracted by Edison to prepare the SONGS replacement steam generator design, was the party responsible for validating the design of the steam generators.

In addition, the NRC issued an Inspection Report to MHI containing a Notice of Nonconformance for its flawed computer modeling in the design of the replacement steam generators.

Because SONGS has ceased operation, NRC inspection oversight of SONGS will now be continued through the NRC’s Decommissioning Power Reactor Inspection Program to verify that decommissioning activities are being conducted safely, that spent fuel is safely stored onsite or transferred to another licensed location, and that the site operations and licensee termination activities conform to applicable regulatory requirements, licensee commitments and management controls.

Nuclear Decommissioning and Funding

As a result of Edison’s decision to permanently retire SONGS Units 2 and 3, Edison has begun the decommissioning phase of the plant. We discuss the process of decommissioning SONGS in Note 13 of the Notes to Consolidated Financial Statements in the Annual Report.

In accordance with state and federal requirements and regulations, SDG&E has assets held in trusts, referred to as the Nuclear Decommissioning Trusts (NDT), to fund decommissioning costs for SONGS Units 1, 2 and 3. Decommissioning of Unit 1, removed from service in 1992, is largely complete. The remaining work will be done when Units 2 and 3 are decommissioned. At March 31, 2015, the fair value of SDG&E’s NDT assets was $1.2 billion. Except for the use of funds for the planning of decommissioning activities or NDT administrative costs, CPUC approval is required for SDG&E to access the NDT assets to fund SONGS decommissioning costs for Units 2 and 3. In February 2014, SDG&E filed a request with the CPUC for such authorization for costs incurred in 2013. In April 2015, SDG&E withdrew its pending request and filed a new request based on updated decommissioning cost information, seeking authorization to access trust funds for decommissioning costs incurred in 2013. SDG&E expects CPUC approval of the request in 2015. Until CPUC approval to access the NDT to pay for such costs is received, SDG&E will use working capital to pay for any SONGS Units 2 and 3 decommissioning costs incurred, and such expenditures will be reimbursed from the NDT upon that approval.

We discuss the NDT and matters related to its funding and the funding of decommissioning costs by the NDT further in Note 13 of the Notes to Consolidated Financial Statements in the Annual Report.

Nuclear Decommissioning Trusts

The amounts collected in rates for SONGS’ decommissioning are invested in externally managed trust funds. Amounts held by the trusts are invested in accordance with CPUC regulations. These trusts are shown on the Sempra Energy and SDG&E Condensed Consolidated Balance Sheets at fair value with the offsetting credits recorded in Regulatory Liabilities Arising from Removal Obligations.

The following table shows the fair values and gross unrealized gains and losses for the securities held in the NDT:

NUCLEAR DECOMMISSIONING TRUSTS
(Dollars in millions)
GrossGrossEstimated
unrealizedunrealizedfair
Costgainslossesvalue
At March 31, 2015:
Debt securities:
Debt securities issued by the U.S. Treasury and other
U.S. government corporations and agencies(1)$103$8$$111
Municipal bonds(2)1348142
Other securities(3)2119(8)212
Total debt securities44825(8)465
Equity securities218452(4)666
Cash and cash equivalents1919
Total $685$477$(12)$1,150
At December 31, 2014:
Debt securities:
Debt securities issued by the U.S. Treasury and other
U.S. government corporations and agencies$103$6$$109
Municipal bonds1218129
Other securities2067(6)207
Total debt securities43021(6)445
Equity securities215444(4)655
Cash and cash equivalents30131
Total $675$466$(10)$1,131
(1)Maturity dates are 2015-2060.
(2)Maturity dates are 2015-2114.
(3)Maturity dates are 2015-2111.

The following table shows the proceeds from sales of securities in the NDT and gross realized gains and losses on those sales:

SALES OF SECURITIES
(Dollars in millions)
Three months ended March 31,
20152014
Proceeds from sales(1)$94$195
Gross realized gains24
Gross realized losses(4)(4)
(1)Excludes securities that are held to maturity.

Net unrealized gains (losses) are included in Regulatory Liabilities Arising from Removal Obligations on Sempra Energy’s and SDG&E’s Condensed Consolidated Balance Sheets. We determine the cost of securities in the trusts on the basis of specific identification.

We provide additional information about SONGS in Note 11.