SUBSEQUENT EVENTS
0 Months Ended
Oct. 01, 2014
Subsequent Events (Abstract)  
Subsequent Events

NOTE 13. SUBSEQUENT EVENT

SEMPRA NATURAL GAS

Cameron LNG Holdings Joint Venture

On August 6, 2014, Sempra Natural Gas and its project partners, comprised of affiliates of GDF SUEZ S.A., Mitsui & Co., Ltd., and Mitsubishi Corporation (through a related company jointly established with Nippon Yusen Kabushiki Kaisha), provided their respective final investment decision with respect to the investment in the development, construction and operation of the natural gas liquefaction export facility at the terminal in Hackberry, Louisiana, owned by Cameron LNG, LLC (Cameron LNG). The Cameron liquefaction project utilizes Cameron LNG’s existing facilities, including two marine berths, three LNG storage tanks, and vaporization capability of 1.5 billion cubic feet (Bcf) per day. The Cameron liquefaction project is comprised of three liquefaction trains and is being designed to a nameplate capacity of 13.5 million tonnes per annum (Mtpa) of LNG, with an expected export capability of 12 Mtpa of LNG, or approximately 1.7 Bcf per day. Commercial operation of all three trains is expected to commence in 2018, with the first year of full operations in 2019. The effective date of the Cameron LNG joint venture, Cameron LNG Holdings, LLC (Cameron LNG Holdings), among Sempra Energy and its project partners occurred on October 1, 2014 after satisfaction of various conditions, including receipt of final regulatory approval and satisfaction of conditions precedent to the first disbursement of the project financing.

In 2013, Sempra Natural Gas signed 20-year liquefaction and regasification tolling capacity agreements with GDF SUEZ S.A. and affiliates of Mitsubishi Corporation and Mitsui & Co., Ltd. which subscribe the full nameplate capacity of the facility. Each tolling agreement is for 4.5 Mtpa of capacity to enable 4.0 Mtpa of LNG export. Also in 2013, Sempra Natural Gas signed agreements totaling 1.45 Bcf per day of firm natural gas transportation service to Cameron LNG on the Cameron Interstate Pipeline with GDF SUEZ S.A. and affiliates of Mitsubishi Corporation and Mitsui & Co., Ltd. The terms of these agreements are concurrent with the liquefaction and regasification tolling capacity agreements.

Our equity in Cameron LNG Holdings was derived from our contribution of Cameron LNG to the joint venture at its historical carrying value. Each of the partners were issued indirect equity interests in Cameron LNG in an aggregate of 49.8 percent. Cameron LNG thereby ceased to be wholly owned or controlled by Sempra Natural Gas, which retained a 50.2 percent of Cameron LNG. As of the October 1, 2014 effective date, Sempra Natural Gas will account for its investment in Cameron LNG Holdings under the equity method. Sempra Energy did not recognize a gain or loss related to the contribution of Cameron LNG to the joint venture.

The following table summarizes the deconsolidation of the Cameron liquefaction project:

DECONSOLIDATION OF SUBSIDIARY
(Dollars in millions)
Cameron LNG, LLC
October 1, 2014
Cash$ (6)
Other current assets (11)
Property, plant and equipment, net (1,022)
Other assets (30)
Accounts payable and accrued expenses 93
Equity method investment upon deconsolidation$ (976)

Joint Venture Financing

General

On August 6, 2014, Cameron LNG also entered into finance documents (collectively, Loan Facility Agreements) for senior secured financing in an initial aggregate principal amount of up to $7.4 billion under three debt facilities provided by the Japan Bank for International Cooperation (JBIC) and 29 international commercial banks, some of which will benefit from insurance coverage provided by Nippon Export and Investment Insurance (NEXI).

The Cameron LNG Loan Facility Agreements and related finance documents provide senior secured term loans with a maturity date of July 15, 2030. The proceeds of the loans will be used for financing the cost of development and construction of the Cameron LNG project. The Loan Facility Agreements and related finance documents contain customary representations and affirmative and negative covenants for project finance facilities of this type with the lenders of the type participating in the Cameron LNG financing. On August 6, 2014, Sempra Energy entered into a completion agreement in favor of HSBC Bank USA, National Association, as security trustee for the benefit of all of Cameron LNG Holdings’ creditors. Pursuant to this completion agreement, Sempra Energy has severally guaranteed 50.2 percent of Cameron LNG Holdings’ senior debt obligations under the Loan Facility Agreements, or a maximum principal amount of $3.7 billion. Completion guarantees for the remaining 49.8 percent of Cameron LNG Holdings’ senior secured financing have been provided by the other project partners. The occurrence of the effectiveness of the Cameron LNG Holdings joint venture on October 1, 2014 was a condition precedent to first disbursement of funds under the Loan Facility Agreements, and the Sempra Energy completion guarantee of 50.2 percent of the Cameron LNG Holdings financing also became effective upon effectiveness of the Cameron LNG Holdings joint venture. Sempra Energy’s completion agreement and guarantee will terminate upon financial completion of the Cameron LNG project, which is subject to satisfaction of certain conditions, including all three trains achieving commercial operations and meeting certain operational performance tests. Financial completion is scheduled for the second half of 2019.

Interest

The weighted average all-in cost of the loans outstanding under all the Loan Facility Agreements (and based on certain assumptions as to timing of drawdown) is 1.59 percent per annum over LIBOR prior to financial completion of the project and 1.78 per annum over LIBOR following financial completion of the project. The Loan Facility Agreements require Cameron LNG to hedge 50 percent of outstanding borrowings to fix the interest rate, beginning in 2016. The hedges are to remain in place until the debt principal has been amortized by 50 percent.

Mandatory Prepayments

Cameron LNG also must make mandatory prepayments of all loans made under the Loan Facility Agreements under certain circumstances, including: upon receipt of certain insurance proceeds and expropriation compensation; upon receipt of certain performance liquidated damages under Cameron LNG’s engineering, procurement and construction contract for the liquefaction terminal; in connection with the loss of its tolling agreements or export permits that result in a reduction of Cameron LNG’s debt service coverage ratios below a specified threshold; if it becomes unlawful in any applicable jurisdiction for a lender to fund or maintain its loans; or in connection with any mandatory prepayment of senior notes outstanding (if any).

The loans under the NEXI Covered Loan Facility Agreement and the loans held by JBIC under the JBIC Loan Facility Agreement are subject to certain additional mandatory prepayments that would be triggered if the Japanese sponsors fail to maintain certain ownership interests in Cameron LNG, if Cameron LNG’s Japanese tolling customers do not hold commitments for a certain quantum of nameplate capacity at the liquefaction terminal or if the aggregate annual contracted LNG commitments by Cameron LNG’s tolling customers to Japanese LNG buyers fall below a certain minimum threshold under certain circumstances.

Events of Default

Cameron LNG’s Loan Facility Agreements and related finance documents also contain events of default customary for such financings, including events of default for: failure to pay principal and interest on the due date; insolvency of Cameron LNG; abandonment of the project; expropriation; unenforceability or termination of the finance documents; and a failure to achieve financial completion of the project by a financial completion deadline date of September 30, 2021 (with up to additional 365 days extension beyond such date permitted in cases of force majeure). A delay in construction that results in a failure to achieve financial completion of the project by this financial completion deadline date would therefore result in an event of default under Cameron LNG’s financing and a potential demand on Sempra Energy’s guarantee.

Security

To support Cameron LNG’s obligations under the Loan Facility Agreements and related finance documents, Cameron LNG has granted security over all of its assets, subject to customary exceptions, and all equity interests in Cameron LNG have been pledged to HSBC Bank USA, National Association, as security trustee for the benefit of all Cameron LNG’s creditors. As a result, an enforcement action by the lenders taken in accordance with the finance documents could result in the exercise of such security interests by the lenders and the loss of ownership interests in Cameron LNG by Sempra Energy and the other project partners.

The security trustee under Cameron LNG’s financing can demand that a payment be made by Sempra Energy under its guarantee of Sempra Energy’s 50.2 percent share of senior debt obligations due and payable either on the date such amounts were due from Cameron LNG (taking into account cure periods) in the event of a failure by Cameron LNG to pay such senior debt obligations when they become due or within 10 business days in the event of an acceleration of senior debt obligations under the terms of the finance documents. If an event of default occurs under the Sempra Energy completion agreement, the security trustee can demand that Sempra Energy purchase its 50.2 percent share of all then outstanding senior debt obligations within five business days (other than in the case of a bankruptcy default, which is automatic).

Terminal Services Agreement

At September 30, 2014, Cameron LNG had a terminal services agreement with one customer that required the customer to pay capacity reservation and usage fees to use its Cameron LNG facilities to receive, store and regasify the customer’s LNG. There is a termination agreement in place that will result in the termination of this agreement at the point during construction of the new liquefaction facilities where piping tie-ins to the existing regasification terminal become necessary. Based on the full notice to proceed that was issued to Cameron LNG’s engineering, procurement and construction contractor in October 2014, we expect this termination date to occur during the first quarter of 2017.