Pipeline Safety Phase 1 [Member] | San Diego Gas and Electric Company and Subsidiary [Member]
 
Schedule Of Utility Projects [Line Items]  
Pipeline Safety Plan Regulatory Account $ 1
Pipeline Safety Phase 1 [Member] | Southern California Gas Company [Member]
 
Schedule Of Utility Projects [Line Items]  
Pipeline Safety Plan Regulatory Account 48
Disallowed Costs Impact On Earnings After Tax 6
South Orange County Reliability Enhancement [Member] | San Diego Gas and Electric Company and Subsidiary [Member]
 
Schedule Of Utility Projects [Line Items]  
Estimated Project Cost, Lower Range 400
Estimated Project Cost, Upper Range 500
South Bay Substation [Member] | San Diego Gas and Electric Company and Subsidiary [Member]
 
Schedule Of Utility Projects [Line Items]  
Estimated Project Cost, Lower Range 145
Estimated Project Cost, Upper Range 175
Southern Gas System Member [Member] | Utility Subsidiaries [Member]
 
Schedule Of Utility Projects [Line Items]  
Estimated Project Cost, Lower Range 800
Estimated Project Cost, Upper Range 850
Sycamore Penasquitos Transmission Project [Member] | San Diego Gas and Electric Company and Subsidiary [Member]
 
Schedule Of Utility Projects [Line Items]  
Estimated Project Cost, Lower Range 120
Estimated Project Cost, Upper Range $ 150