XML 80 R15.htm IDEA: XBRL DOCUMENT v2.4.0.8
NUCLEAR PLANT
3 Months Ended
Jun. 30, 2014
Notes to Consolidated Financial Statements [Abstract]  
Nuclear Plant

NOTE 9. SAN ONOFRE NUCLEAR GENERATING STATION (SONGS)

SDG&E has a 20-percent ownership interest in SONGS, a nuclear generating facility near San Clemente, California, which ceased operations in June 2013. On June 6, 2013, Southern California Edison Company (Edison), the majority owner and operator of SONGS, notified SDG&E that it had reached a decision to permanently retire SONGS and seek approval from the Nuclear Regulatory Commission (NRC) to start the decommissioning activities for the entire facility. SONGS is subject to the jurisdiction of the NRC and the CPUC.

SDG&E, and each of the other owners, holds its undivided interest as a tenant in common in the property. Each owner is responsible for financing its share of expenses and capital expenditures. SDG&E's share of operating expenses is included in Sempra Energy's and SDG&E's Condensed Consolidated Statements of Operations.

SONGS Outage and Retirement

Background

As part of the Steam Generator Replacement Project (SGRP), the steam generators were replaced in SONGS Units 2 and 3, and the Units returned to service in 2010 and 2011, respectively. Both Units were shut down in early 2012 after a water leak occurred in the Unit 3 steam generator. Edison concluded that the leak was due to unexpected wear from tube-to-tube contact. At the time the leak was identified, Edison also inspected and tested Unit 2 and subsequently found unexpected tube wear in Unit 2's steam generators as well. In March 2012, in response to the shutdown of SONGS, the NRC issued a Confirmatory Action Letter (CAL) which, among other things, outlined the requirements for Edison to meet before the NRC would approve a restart of either of the Units.

In October 2012, Edison submitted a restart plan to the NRC proposing to operate Unit 2 at a reduced power level for a period of five months, at which time the Unit would be brought down for further inspection. Edison did not file a restart plan for Unit 3, pending further inspection and analysis of what repairs or modifications would be required to return the Unit to service in a safe manner. The NRC was reviewing the restart plan for Unit 2 proposed by Edison when in May 2013, the Atomic Safety and Licensing Board (ASLB), an adjudicatory arm of the NRC, concluded that the CAL process constituted a de facto license amendment proceeding that was subject to a public hearing. This conclusion by the ASLB resulted in further uncertainty regarding when a final decision might be made on restarting Unit 2.

The replacement steam generators were designed and provided by Mitsubishi Heavy Industries, Ltd., Mitsubishi Nuclear Energy Systems, Inc., and Mitsubishi Heavy Industries America, Inc. (collectively MHI). In July 2013, SDG&E filed a lawsuit against MHI seeking to recover damages SDG&E has incurred and will incur related to the design defects in the steam generators. In October 2013, Edison instituted arbitration proceedings against MHI seeking damages as well. We discuss these proceedings in Note 11.

Proposed Settlement Agreement to Resolve the CPUC's Order Instituting Investigation (OII) into the SONGS Outage (SONGS OII)

SONGS OII

In November 2012, in response to the outage, the CPUC issued the SONGS OII, pursuant to California Public Utilities' Code Section 455.5, which applies to cost recovery issues resulting from long-term outages of operating assets. The SONGS OII consolidated most SONGS outage-related issues into a single proceeding. The SONGS OII, among other things, designated all revenues associated with the investment in, and operation of, SONGS since January 1, 2012 as subject to refund to customers, pending the outcome of all phases of the proceeding. The SONGS OII proceeding is also intended to determine the ultimate recovery of the investment in SONGS and the costs incurred since the commencement of this outage, including purchased replacement power costs, which are typically recovered through the Energy Resource Recovery Account (ERRA) subject only to a reasonableness review by the CPUC. We provide additional information on the SONGS OII in Notes 13 and 15 of the Notes to Consolidated Financial Statements in the Annual Report.

Entry Into Settlement Agreement

Pursuant to CPUC rules concerning settlements, SDG&E, Edison, The Utility Reform Network (TURN), and the CPUC Office of Ratepayer Advocates (ORA) gave advance written notice to all parties in the SONGS OII of a conference to discuss the terms to resolve the SONGS OII. The settlement conference was held on March 27, 2014. On April 3, 2014, SDG&E, along with Edison, TURN, ORA and two other intervenors to the SONGS OII proceeding, filed a Settlement Agreement with the CPUC. If approved by the CPUC, the Settlement Agreement will constitute a complete and final resolution of the SONGS OII and related CPUC proceedings regarding the SGRP at SONGS and the related outage and subsequent shutdown of SONGS. The Settlement Agreement does not affect on-going or future proceedings before the NRC, or litigation or arbitration related to potential future recoveries from third parties or proceedings addressing decommissioning activities and costs.

Implementation of the terms of the Settlement Agreement is subject to the approval of the CPUC. The parties to the Settlement Agreement (Settling Parties) have agreed to exercise their best efforts to obtain CPUC approval. While we expect the CPUC to issue a final decision on the Settlement Agreement by the end of 2014, there is no assurance that the CPUC will do so. In addition, the Settlement Agreement is subject to termination by any of the Settling Parties if CPUC approval has not been issued before October 3, 2014, and there is no assurance that one or more of the Settling Parties won't do so.

The following is a summary of the Settlement Agreement.

Disallowances, Refunds and Rate Recoveries

If the Settlement Agreement is approved as filed with the CPUC, SDG&E will

  • remove from rate base, as of February 1, 2012, its investment in the SGRP and refund to its customers the amount collected for its investment in and any return on its investment in the SGRP since such date. As of February 1, 2012, SDG&E's net book value in the SGRP was approximately $160 million;
  • be authorized to recover in rates its remaining investment in SONGS, including base plant and construction work in progress (CWIP), generally over a ten-year period commencing February 1, 2012, together with a return on investment at a reduced rate equal to:

  • SDG&E's weighted average return on debt, plus
  • 50 percent of SDG&E's weighted average return on preferred stock, as authorized in the CPUC's Cost of Capital proceeding then in effect (collectively, SONGS rate of return or SONGS ROR).

This results in a SONGS ROR of 2.75 percent for the period February 1, 2012 through December 31, 2012 and 2.35 percent for the period January 1, 2013 through December 31, 2014. The SONGS ROR for future periods will fluctuate based on SDG&E's authorized weighted average returns on debt and preferred stock in effect for those future periods;

  • be authorized to recover in rates its recorded operations and maintenance expenses for 2012, 2013 and 2014 as well as the recorded costs for the 2012 refueling outage of Unit 2, subject to customary prudency review;

  • be authorized to recover in rates its remaining investment in materials and supplies over a ten-year period commencing February 1, 2012, together with a return on investment at the SONGS ROR;
  • be authorized to recover in rates its remaining investment in nuclear fuel inventory and any costs incurred, or to be incurred, associated with nuclear fuel supply contracts over a ten-year period, together with a return equal to SDG&E's commercial paper borrowing rate; and

  • be authorized to recover in rates through its fuel and purchased power balancing account (ERRA) all costs incurred to purchase power in the market to replace the power that would have been generated at SONGS if not for the outage and shutdown of SONGS, and to recover by December 31, 2015 any SONGS-related ERRA undercollections. SDG&E's market power costs through June 6, 2013 (the date of SONGS' retirement) were approximately $165 million, using the methodology followed in the SONGS OII.

    The Settlement Agreement also provides SDG&E with an incentive in the event proceeds are secured from the sale of materials and supplies and/or nuclear fuel, as well as in the event that nuclear fuel investments are reduced by contract cancellations. This incentive allows SDG&E to retain 5 percent of its proportionate share of any sales proceeds and to recover 5 percent of its proportionate share of the excess of cancelled contract obligations over cancellation costs. The balance of the sale proceeds and cancellation benefits would be credited to ratepayers.

    Potential Third Party Recoveries

    The Settlement Agreement also addresses how potential recoveries from third parties will be allocated between ratepayers and SDG&E.

    As we discuss in Note 11, SDG&E and the other owners of SONGS carry accidental property damage and accidental outage insurance issued by Nuclear Electric Insurance Limited (NEIL), a mutual insurance company. Edison, on behalf of itself and the other minority owners in SONGS (including SDG&E), has placed NEIL on notice of claims under both policies. Under the Settlement Agreement, recoveries from NEIL, if any, will first be applied to reimburse costs incurred in pursuing such recoveries, including litigation costs. To the extent SDG&E's share of recoveries from NEIL exceeds such costs, recoveries will be allocated 82.5 percent to ratepayers and 17.5 percent to SDG&E.

    As we discuss in Note 11, SDG&E has filed a lawsuit against MHI, which designed and provided the steam generators that failed. This proceeding was stayed in favor of an arbitration proceeding instituted by Edison. Under the Settlement Agreement, recoveries from MHI, if any, will first be applied to reimburse costs incurred in pursuing such recoveries, including litigation costs. We provide additional information on the proceedings against MHI in Note 11.

    To the extent SDG&E's share of recoveries from MHI exceeds such costs, they will be allocated as follows:

  • 85 percent of the first $25 million to SDG&E, and 15 percent to ratepayers;
  • 66.67 percent of the next $200 million to SDG&E, and 33.33 percent to ratepayers; and

  • 25 percent of any additional recoveries to SDG&E, and 75 percent to ratepayers.

The Settlement Agreement provides for the resolution of the claims with NEIL and the dispute with MHI without requiring CPUC review or approval, but requires that Edison and SDG&E use their best efforts to inform the CPUC of any settlements or resolutions of the issues to the extent possible without compromising any aspect of such settlements or resolutions.

There is no assurance that there will be any recoveries from NEIL or MHI or that if there are recoveries, that they will exceed the costs incurred to pursue them. Were there to be recoveries, SDG&E cannot provide any assurance as to when they would be received or the amount of any such recoveries. SDG&E currently expects that NEIL will make a coverage determination by the end of 2014.

Accounting and Financial Impacts

As a result of the execution of the Settlement Agreement by the Settling Parties, SDG&E concluded that the probable outcome of the SONGS OII is the approval and implementation of the Settlement Agreement, although such outcome is dependent on approval by the CPUC.

As disclosed in Note 13 of the Notes to Consolidated Financial Statements in the Annual Report, SDG&E reported a pretax loss from plant closure of $200 million ($119 million after-tax) in the second quarter of 2013 as a result of its initial assessment of the financial impact of the outcome of the SONGS OII proceeding. As a result of entering into the Settlement Agreement in the first quarter of 2014, SDG&E recorded a $13 million reduction to the pretax loss from plant closure, but a $9 million increase in the after-tax loss from plant closure. The after-tax loss includes a $17 million charge to reduce certain tax regulatory assets which may no longer be recoverable in rates pursuant to the Settlement Agreement. After adjustment for the Settlement Agreement, the total loss from plant closure, including amounts previously recorded in 2013, is $187 million pretax ($128 million after-tax). A regulatory asset for the expected recovery of SONGS costs, consistent with the Settlement Agreement, is recorded on the Condensed Consolidated Balance Sheets of Sempra Energy and SDG&E in Other Regulatory Assets (long-term). The amount of this regulatory asset is $232 million as of June 30, 2014.

Assuming the Settlement Agreement is approved, and except for the impact of the amount and timing of any potential future recoveries from third parties, which SDG&E cannot estimate at this time, SDG&E does not expect that implementation of the Settlement Agreement will have a material adverse impact on its future results of operations or financial condition.

Procedure

Under the Settlement Agreement, the Settling Parties are required to use their best efforts to obtain CPUC approval. In April 2014, the Settling Parties filed a Motion requesting the CPUC to:

  • approve the Settlement Agreement without change;
  • find the Settlement Agreement reasonable;
  • withdraw the November 19, 2013 Proposed Decision on Phase 1 and Phase 1A issues in the SONGS OII; and

  • expedite consideration of the Settlement Agreement in order to provide its benefits to ratepayers as soon as possible.

    Subject to the right of any settling party to terminate the Settlement Agreement if it is not approved by the CPUC by October 3, 2014, during the pendency of proceedings regarding the Settlement Agreement, the Settling Parties are further bound to:

  • support and mutually defend the Settlement Agreement in its entirety;
  • oppose any modifications proposed by any non-settling party to the SONGS OII unless all Settling Parties agree; and

  • cooperate reasonably on all submissions necessary to achieve CPUC approval.

The Settling Parties further agree to review any CPUC orders regarding the Settlement Agreement to determine if the CPUC has changed or modified it, deleted a term or imposed a new term. If any Settling Party is unwilling to accept any such change, modification, deletion or addition of a new term, then the Settling Parties will negotiate in good faith to seek a resolution acceptable to all Settling Parties. If they are unable to resolve the matter to the satisfaction of all Settling Parties, or to obtain prompt CPUC approval of an agreed upon resolution, then any Settling Party can terminate the Settlement Agreement upon prompt notice.

In May 2014, comments on the Motion and Settlement Agreement were filed, and the CPUC held an evidentiary hearing. The Settling Parties also hosted a community meeting in June 2014.

Pursuant to the CPUC's rules, no settlement becomes binding unless the CPUC approves the settlement based on a finding that it is reasonable in light of the whole record, consistent with law, and in the public interest. The CPUC has discretion to approve or disapprove a settlement, or to condition its approval on changes to the settlement, which the parties may accept or reject. CPUC rules do not provide for any fixed time period for the CPUC to act on the Settlement Agreement.

Unless and until the CPUC approves the Settlement Agreement as filed, there can be no assurance that the SONGS OII proceeding will provide for recoveries as currently estimated by SDG&E in accordance with the Settlement Agreement, including the recovery of costs recorded as a regulatory asset, or that the CPUC will not order refunds to customers above those contemplated by the Settlement Agreement. Therefore, the regulatory asset of $232 million in Other Regulatory Assets (long-term) on the Condensed Consolidated Balance Sheets of Sempra Energy and SDG&E at June 30, 2014 related to the SONGS plant closure could be subject to further change based upon future developments and the application of SDG&E's judgment to those events.

NRC Proceedings

In December 2013, Edison received a final NRC Inspection Report that identified a violation for the failure to verify the adequacy of the thermal-hydraulic and flow-induced vibration design of the Unit 3 replacement steam generators. In January 2014, Edison provided a response to the NRC Inspection Report stating that MHI, as contracted by Edison to prepare the SONGS replacement steam generator design, was the party responsible for validating the design of the steam generators.

In addition, the NRC issued an Inspection Report to MHI containing a Notice of Nonconformance for its flawed computer modeling in the design of the replacement steam generators.

Because SONGS has ceased operation, NRC inspection oversight of SONGS will now be continued through the NRC's Decommissioning Power Reactor Inspection Program to verify that decommissioning activities are being conducted safely, that spent fuel is safely stored onsite or transferred to another licensed location, and that the site operations and licensee termination activities conform to applicable regulatory requirements, licensee commitments and management controls.

Nuclear Decommissioning and Funding

As a result of Edison's decision to permanently retire SONGS Units 2 and 3, Edison has begun the decommissioning phase of the plant. The process of decommissioning a nuclear power plant is governed by the regulations of various governmental and other agencies, including but not limited to, those of the NRC, the U.S. Department of the Navy (the land owner) and the CPUC. The NRC regulations generally categorize the decommissioning activities into three phases: initial activities, major decommissioning and storage activities, and license termination. Initial activities include providing notice of permanent cessation of operations (provided by Edison to the NRC on June 12, 2013) and notice of permanent removal of fuel from the reactor vessels (provided by Edison on June 28 and July 22, 2013 for Units 3 and 2, respectively). Within two years after the cessation of operations, the licensee (Edison) must submit a post-shutdown decommissioning activities report, an irradiated fuel management plan and a site-specific decommissioning cost estimate. Edison currently estimates that it will provide these documents to the NRC by the end of 2014.

In accordance with state and federal requirements and regulations, SDG&E has assets held in trusts, referred to as the Nuclear Decommissioning Trusts (NDT), to fund decommissioning costs for SONGS Units 1, 2 and 3. At June 30, 2014, the fair value of SDG&E's NDT assets was $1.1 billion. Except for the use of funds for the planning of decommissioning activities, CPUC approval is required for SDG&E to access the NDT assets to fund SONGS decommissioning costs. In February 2014, SDG&E filed a request with the CPUC for such authorization for costs incurred in 2013. Until CPUC approval to access the NDT to pay for such costs is received, SDG&E will use working capital to pay for any SONGS Units 2 and 3 decommissioning costs incurred, and such expenditures will be reimbursed from the NDT upon that approval. The timing of SDG&E's access to the NDT assets may also depend on the NRC's approval of an exemption that would permit the monies in the SONGS trust funds to be used to pay for each of the three general categories of decommissioning activities. These activities are as follows:

  • NRC-jurisdictional radiological decommissioning (also known as “license termination”)
  • spent fuel management and decommissioning at an independent spent fuel storage installation

  • non-radiological purposes, i.e., site restoration 

SDG&E currently anticipates a decision regarding its ability to use the monies in the NDT by the end of 2014.

SDG&E and Edison have a joint application pending with the CPUC requesting continued rate recovery to fund the NDT to ensure that the NDT has sufficient funding to pay for the estimated cost of decommissioning SONGS. SDG&E is currently authorized to recover $8 million annually to fund additional investments in the NDT to pay for the cost of decommissioning SONGS. In its pending application with the CPUC, SDG&E is requesting to recover $16 million on an annual basis to fund additional investments in the NDT. We expect a decision on this application by the end of 2014.

Nuclear Decommissioning Trusts

The amounts collected in rates for SONGS' decommissioning are invested in externally managed trust funds. Amounts held by the trusts are invested in accordance with CPUC regulations. These trusts are shown on the Sempra Energy and SDG&E Condensed Consolidated Balance Sheets at fair value with the offsetting credits recorded in Regulatory Liabilities Arising from Removal Obligations.

The following table shows the fair values and gross unrealized gains and losses for the securities held in the trust funds:

 

NUCLEAR DECOMMISSIONING TRUSTS
(Dollars in millions)
     Gross Gross Estimated
     Unrealized Unrealized Fair
   Cost Gains Losses Value
At June 30, 2014:        
Debt securities:        
Debt securities issued by the U.S. Treasury and other         
U.S. government corporations and agencies(1)$ 101$ 5$$ 106
Municipal bonds(2)  109  6  (1)  114
Other securities(3)  190  8  (2)  196
Total debt securities  400  19  (3)  416
Equity securities  213  440  (1)  652
Cash and cash equivalents  28    28
Total $ 641$ 459$ (4)$ 1,096
At December 31, 2013:        
Debt securities:        
Debt securities issued by the U.S. Treasury and other         
U.S. government corporations and agencies$ 116$ 3$ (2)$ 117
Municipal bonds  110  2  (1)  111
Other securities  155  3  (5)  153
Total debt securities  381  8  (8)  381
Equity securities  207  409  (2)  614
Cash and cash equivalents  39    39
Total $ 627$ 417$ (10)$ 1,034
(1)Maturity dates are 2016-2060
(2)Maturity dates are 2014-2062
(3)Maturity dates are 2014-2096

The following table shows the proceeds from sales of securities in the trusts and gross realized gains and losses on those sales:

SALES OF SECURITIES
(Dollars in millions)
 Three months ended June 30,Six months ended June 30,
 2014201320142013
Proceeds from sales(1)$ 155$ 192$ 350$ 326
Gross realized gains   6  4  11
Gross realized losses  (1)  (4)  (5)  (7)
(1) Excludes securities that are held to maturity.    

Net unrealized gains (losses) are included in Regulatory Liabilities Arising from Removal Obligations on Sempra Energy's and SDG&E's Condensed Consolidated Balance Sheets. We determine the cost of securities in the trusts on the basis of specific identification.

We provide additional information about SONGS in Note 11.