EX-99.1 2 o39288exv99w1.htm ANNUAL INFORMATION FORM ANNUAL INFORMATION FORM
 

Exhibit 99.1
(GOLDCORP INC. LOGO)
ANNUAL INFORMATION FORM
FOR THE FINANCIAL YEAR ENDED DECEMBER 31, 2007
March 25, 2008
Suite 3400, 666 Burrard Street
Vancouver, BC V6C 2X8

 


 

GOLDCORP INC.
ANNUAL INFORMATION FORM
FOR THE FINANCIAL YEAR ENDED DECEMBER 31, 2007
TABLE OF CONTENTS
         
DESCRIPTION   PAGE NO.
INTRODUCTORY NOTES
    1  
CORPORATE STRUCTURE
    4  
GENERAL DEVELOPMENT OF THE BUSINESS
    6  
DESCRIPTION OF THE BUSINESS
    10  
Principal Products
    10  
Competitive Conditions
    10  
Operations
    10  
Environmental Policy
    11  
Technical Information
    12  
Summary of Ore Reserve/Mineral Reserve and Mineral Resource Estimates
    15  
Mineral Properties
    21  
CANADA AND THE UNITED STATES
    21  
RED LAKE GOLD MINES, CANADA
    21  
PORCUPINE JOINT VENTURE, CANADA
    29  
MUSSELWHITE JOINT VENTURE, CANADA
    29  
MARIGOLD MINE, UNITED STATES
    29  
WHARF MINES, UNITED STATES
    29  
ÉLÉONORE PROJECT, QUÉBEC
    30  
SOUTH ARTURO PROJECT, UNITED STATES
    31  
IMPERIAL PROJECT, UNITED STATES
    31  
MEXICO
    31  
LOS FILOS MINE, MEXICO
    32  
EL SAUZAL MINE, MEXICO
    40  
SAN DIMAS MINES, MEXICO
    40  
NUKAY MINE, MEXICO
    41  
PEÑASQUITO PROJECT, MEXICO
    41  
CENTRAL AND SOUTH AMERICA
    50   
ALUMBRERA MINE, ARGENTINA
    50   
MARLIN MINE, GUATEMALA
    60   
SAN MARTIN MINE, HONDURAS
    64   
PUEBLO VIEJO PROJECT, DOMINICAN REPUBLIC
    65   
CERRO BLANCO PROJECT, GUATEMALA
    80   
RISK FACTORS
    80   
DIVIDENDS
    91   
DESCRIPTION OF CAPITAL STRUCTURE
    91   
TRADING PRICE AND VOLUME
    92   
DIRECTORS AND OFFICERS
    93   
INTEREST OF MANAGEMENT AND OTHERS IN MATERIAL TRANSACTIONS
    100   
TRANSFER AGENT AND REGISTRAR
    101   
MATERIAL CONTRACTS
    101   
INTERESTS OF EXPERTS
    101   
AUDIT COMMITTEE
    103   
ADDITIONAL INFORMATION
    105   
SCHEDULE “A” GOLDCORP INC. AUDIT COMMITTEE CHARTER
    -A1-  

 


 

INTRODUCTORY NOTES
Cautionary Note Regarding Forward-Looking Statements
     This annual information form contains “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities legislation. Forward-looking statements include, but are not limited to, statements with respect to the future price of gold, silver, copper, lead and zinc, the estimation of mineral reserves and resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of production, capital expenditures, costs and timing of the development of new deposits, success of exploration activities, permitting time lines, currency exchange rate fluctuations, requirements for additional capital, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “plans”, “expects” or “does not expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or “does not anticipate”, or “believes”, or variations of such words and phrases or state that certain actions, events or results “may”, “could”, “would”, “might” or “will be taken”, “occur” or “be achieved”. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Goldcorp Inc. to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to the integration of acquisitions; risks related to international operations; risks related to joint venture operations; actual results of current exploration activities; actual results of current reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of gold, silver, copper, lead and zinc; possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of development or construction activities, as well as those factors discussed in the section entitled “Risk Factors” in this annual information form. Although Goldcorp Inc. has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Goldcorp Inc. does not undertake to update any forward-looking statements that are incorporated by reference herein, except in accordance with applicable securities laws.
Currency Presentation and Exchange Rate Information
     This annual information form contains references to United States dollars and Canadian dollars. All dollar amounts referenced, unless otherwise indicated, are expressed in United States dollars and Canadian dollars are referred to as “Canadian dollars” or “C$”.
     The high, low, average and closing exchange rates for Canadian dollars in terms of the United States dollar for each of the three years ended December 31, 2007, as quoted by the Bank of Canada, were as follows:
                         
    Year ended December 31
    2007   2006   2005
High
    C$1.1855       C$1.1726       C$1.2841  
Low
    0.9215       1.0990       1.1507  
Average (1)
    1.0750       1.1341       1.2118  
Closing
    0.9801       1.1653       1.1659  
 
(1)   Calculated as an average of the daily noon rates for each period.
     On March 24, 2008, the closing exchange rate for Canadian dollars in terms of the United States dollar, as quoted by the Bank of Canada, was US$1.00 = C$1.0179.

 


 

Gold, Silver, Copper, Lead and Zinc Prices
Gold Prices
     The high, low, average and closing afternoon fixing gold prices in United States dollars per troy ounce for each of the three years ended December 31, 2007, as quoted by the London Bullion Market Association, were as follows:
                         
    Year ended December 31
    2007   2006   2005
High
  $ 841.10     $ 725.00     $ 536.50  
Low
    608.40       524.75       411.10  
Average
    695.39       603.46       444.74  
Closing
    833.75       632.00       513.00  
     On March 20, 2008, the closing afternoon fixing gold price in United States dollars per troy ounce, as quoted on the London Bullion Market Association, was $925.75.
Silver Prices
     The high, low, average and closing afternoon fixing silver prices in United States dollars per troy ounce for each of the three years ended December 31, 2007, as quoted by the London Bullion Market Association, were as follows:
                         
    Year ended December 31
    2007   2006   2005
High
  $ 15.82     $ 14.94     $ 9.23  
Low
    11.67       8.83       6.39  
Average
    13.38       11.55       7.32  
Closing
    14.76       12.90       8.83  
     On March 20, 2008, the closing afternoon fixing silver price in United States dollars per troy ounce, as quoted on the London Bullion Market Association, was $17.53.
Copper Prices
     The high, low, average and closing official cash settlement copper prices in United States dollars per pound for each of the three years ended December 31, 2007, as quoted on the London Metal Exchange, were as follows:
                         
    Year ended December 31
    2007   2006   2005
High
  $ 3.76     $ 3.99     $ 2.11  
Low
    2.37       2.06       1.39  
Average
    3.23       3.05       1.67  
Closing
    3.03       2.85       2.08  
     On March 24, 2008, the closing official cash settlement copper price in United States dollars per pound, as quoted on the London Metal Exchange, was $3.53.

- 2 -


 

Lead Prices
     The high, low, average and closing official cash settlement lead prices in United States dollars per pound for each of the three years ended December 31, 2007, as quoted on the London Metal Exchange, were as follows:
                         
    Year ended December 31
    2007   2006   2005
High
  $ 1.809     $ 0.816     $ 0.518  
Low
    0.716       0.416       0.374  
Average
    1.177       0.583       0.442  
Closing
    1.167       0.774       0.489  
     On March 24, 2008, the closing official cash settlement lead price in United States dollars per pound, as quoted on the London Metal Exchange, was $1.20.
Zinc Prices
     The high, low, average and closing official cash settlement zinc prices in United States dollars per pound for each of the three years ended December 31, 2007, as quoted on the London Metal Exchange, were as follows:
                         
    Year ended December 31
    2007   2006   2005
High
  $ 1.906     $ 2.088     $ 0.862  
Low
    1.007       0.868       0.524  
Average
    1.478       1.480       0.626  
Closing
    1.094       1.946       0.862  
     On March 24, 2008, the closing official cash settlement zinc price in United States dollars per pound, as quoted on the London Metal Exchange, was $1.03.

- 3 -


 

CORPORATE STRUCTURE
     Goldcorp Inc. (“Goldcorp” or the “Corporation”) is a corporation governed by the Business Corporations Act (Ontario). Effective December 1, 2006, the Corporation amalgamated with Glamis Gold Ltd. (“Glamis”).
     The Corporation’s head office is located at Suite 3400, Park Place, 666 Burrard Street, Vancouver, British Columbia, V6C 2X8 and its registered office is located at Suite 2100, 40 King Street West, Toronto, Ontario, M5H 3C2.
     The following chart illustrates the Corporation’s principal subsidiaries (collectively, the “Subsidiaries”), together with the governing law of each company and the percentage of voting securities beneficially owned or over which control or direction is exercised by the Corporation, as well as the Corporation’s principal mineral properties. As used in this annual information form, except as otherwise required by the context, reference to “Goldcorp” or the “Corporation” means, collectively, Goldcorp Inc. and the Subsidiaries.

- 4 -


 

GOLDCORP PRINCIPAL SUBSIDIARIES AND NI 43-101 MATERIAL MINERAL PROJECTS
(FLOW CHART)
 
(1)   Companies in Mexico require a minimum of two shareholders.

- 5 -


 

GENERAL DEVELOPMENT OF THE BUSINESS
     Goldcorp is engaged in the acquisition, exploration, development and operation of precious metal properties in Canada, the United States, Mexico and Central and South America. The principal products and sources of cash flow for Goldcorp are derived from the sale of gold, silver, copper, lead and zinc. Goldcorp’s mineral properties by jurisdiction are as follows:
Canada and the United States
    a 100% interest in the Red Lake gold mine (the “Red Lake Gold Mine”) in Canada, a 72% interest held by Goldcorp and a 28% interest held by Goldcorp Canada Ltd., a wholly-owned subsidiary of the Corporation (“Goldcorp Canada”) (the Red Lake Gold Mine is considered to be a material mineral project to Goldcorp);
 
    a 100% interest in the Porcupine gold mine (the “Porcupine Mine”) in Canada, a 49% interest held by Goldcorp and a 51% interest held by Goldcorp Canada;
 
    a 100% interest in the Musselwhite gold mine (the “Musselwhite Mine”) in Canada, a 32% interest held by Goldcorp and a 68% interest held by Goldcorp Canada;
 
    a 66 2/3% interest in the Marigold gold mine (the “Marigold Mine”) in the United States;
 
    a 100% interest in the Wharf gold mine (the “Wharf Mine”) in the United States;
 
    a 100% interest in the Éléonore gold project (the “Éléonore Project”) in Québec;
 
    a 40% interest in the South Arturo gold exploration project (the “South Arturo Project”) in the United States; and
 
    a 100% interest in the Imperial gold exploration project (the “Imperial Project”) in the United States.
Mexico
    a 100% interest in the Los Filos gold mine (1) (the “Los Filos Mine”) in Mexico (the Los Filos Mine is considered to be a material mineral project to Goldcorp);
 
    a 100% interest in the El Sauzal gold mine (the “El Sauzal Mine”) in Mexico;
 
    a 100% interest in the San Dimas gold-silver mines (the “San Dimas Mines”) in Mexico;
 
    a 100% interest in the Nukay gold-silver mine (the “Nukay Mine”) in Mexico; and
 
    a 100% interest in the Peñasquito gold project (the “Peñasquito Project”) in Mexico (the Peñasquito Project is considered to be a material mineral project to Goldcorp).
 
(1)   Commercial production was achieved at Los Filos on January 1, 2008. Prior thereto, this was referred to as the Los Filos Project.
Central and South America
    a 37.5% interest in the Bajo de la Alumbrera gold-copper mine (the “Alumbrera Mine”) in Argentina (the Alumbrera Mine is considered to be a material mineral project to Goldcorp);

- 6 -


 

    a 100% interest in the Marlin gold-silver mine (the “Marlin Mine”) in Guatemala (the Marlin Mine is considered to be a material mineral project to Goldcorp);
 
    a 100% interest in the San Martin gold mine (the “San Martin Mine”) in Honduras;
 
    a 40% interest in the Pueblo Viejo gold development stage project (the “Pueblo Viejo Project”) in the Dominican Republic (the Pueblo Viejo Project is considered to be a material mineral project to Goldcorp); and
 
    a 100% interest in the Cerro Blanco gold project (the “Cerro Blanco Project”) in Guatemala.
     The following map illustrates the Corporation’s properties which are located in Canada, the United States, Mexico and Central and South America.
(GOLDCORP MAP)

- 7 -


 

     Goldcorp also owns approximately 21% of Peak Gold Ltd. (“Peak Gold”), a mining company which operates the Amapari gold mine in Brazil and the Peak gold mines in Australia, which is listed on the TSX Venture Exchange (the “TSXV”) under the symbol “PIK”.
     Goldcorp Canada owns an approximate 68% equity interest, on an as-converted basis, in Terrane Metals Corp. (“Terrane”), an exploration and mine development company focused on the development of the Mt. Milligan copper-gold and Berg copper-molybdenum-silver projects in British Columbia, Canada, which is listed on the TSXV under the symbol “TRX”. Terrane has granted Goldcorp the right to maintain its pro rata equity position in Terrane as long as Goldcorp is required to include Terrane’s financial information on a consolidated basis in Goldcorp’s financial statements.
Sale of Silver Wheaton Shares
     On December 7, 2006, Goldcorp sold 18 million common shares of Silver Wheaton Corp. (“Silver Wheaton”) pursuant to a public offering for proceeds to Goldcorp of approximately C$217.9 million. Following such sale, the Corporation owned approximately 48% of Silver Wheaton. On February 14, 2008, Goldcorp sold its remaining 108 million common shares of Silver Wheaton (the “Silver Wheaton Sale”) pursuant to a public offering for gross proceeds to Goldcorp of C$1.566 billion. The Corporation currently does not own any common shares of Silver Wheaton.
     The Silver Wheaton Sale is consistent with Goldcorp’s commitment to simplifying its corporate structure and strengthening its balance sheet. The proceeds from the transaction provide Goldcorp with the financial flexibility to fund an expected 50% growth in gold production over the next five-year period and will provide financial flexibility for future growth opportunities.
Acquisition of Remaining Interests in Porcupine and Musselwhite Mines and Sale of La Coipa Mine
     On December 21, 2007, the Corporation completed the acquisition of the 49% joint venture interest in the Porcupine Mine and the 32% joint venture interest in the Musselwhite Mine held by Kinross Gold Corporation in exchange for Goldcorp’s 50% stake in the La Coipa silver-gold mine in Chile and $200 million in cash. As a result of this transaction, the Porcupine Joint Venture is owned by Goldcorp Canada (51% interest) and Goldcorp Inc. (49% interest) and the Musselwhite Joint Venture is owned by Goldcorp Canada (68% interest) and Goldcorp Inc. (32% interest).
Sale of 25% of Life of Mine Silver Production from Peñasquito Project
     On July 25, 2007, the Corporation completed the sale to Silver Wheaton of 25% of the life of mine silver production from the Peñasquito Project for a cash payment of $485 million. The agreement also requires Silver Wheaton to pay an ongoing per-ounce payment equal to the lesser of $3.90 (subject to annual inflationary adjustments) and the prevailing market price per ounce of silver delivered under the contract.
     As a result of this transaction, Silver Wheaton extended Goldcorp’s right to maintain its pro rata interest in Silver Wheaton to December 31, 2009 so long as it owned at least 20% of Silver Wheaton. As a result of the Silver Wheaton Sale, Goldcorp no longer owns any of the issued and outstanding shares in Silver Wheaton. Silver Wheaton also retained a right of first refusal on any further sales of silver streams from Peñasquito for the life of the mine as long as Goldcorp maintained at least a 20% interest in Silver Wheaton. As a result of the Silver Wheaton Sale, Silver Wheaton’s right of first refusal on any further sales of silver streams from Peñasquito for the mine life was extinguished.
Sale of Amapari and Peak Mines
     On April 3, 2007 and April 27, 2007, respectively, the Corporation completed the sale of the Amapari gold mine (the “Amapari Mine”) located in Brazil (the “Amapari Mine Sale”) and the Peak gold mines (the “Peak Mines”) located in Australia (the “Peak Mines Sale”) to Peak Gold. The Peak Mines Sale occurred at a later date due to regulatory delays in Australia. In consideration for the acquisition of the Amapari and Peak Mines, Peak

- 8 -


 

Gold issued to Goldcorp 155 million common shares of Peak Gold with a value of $100 million and paid $200 million in cash, respectively. Such shares are subject to certain exchange escrow conditions and Goldcorp has agreed not to sell any of such common shares held by it until April 4, 2008, the first anniversary of the completion of these transactions, and thereafter not more than 500,000 in any month unless it gives Peak Gold a 24 hour notice period to find a buyer for the common shares. Goldcorp has the right to nominate one director to Peak Gold’s board of directors for so long as it holds not less than 15% of the outstanding common shares. Peak Gold has entered into a three year non-competition agreement with Goldcorp under which it has agreed not to acquire any mineral interest in the Americas with reasonably expected annual production exceeding 200,000 ounces of gold or in any property worldwide that is within 20 kilometres of any Goldcorp property.
Sale of San Martin Mine, Mexico
     On January 31, 2007, Goldcorp completed the sale of the San Martin mine in Mexico to Starcore International Ventures Ltd. (“Starcore”) for $24,000,000 and 4,729,000 common shares in the capital of Starcore.
Glamis Acquisition
     On November 4, 2006, Goldcorp completed its acquisition of Glamis (the “Glamis Acquisition”). In connection with the Glamis Acquisition, each Glamis share was exchanged for 1.69 Goldcorp shares and $0.0001 in cash, resulting in former Glamis shareholders holding approximately 40% of the total issued and outstanding common shares (the “Common Shares”) of Goldcorp and Goldcorp shareholders holding approximately 60% of the total issued and outstanding common shares of Goldcorp. The assets acquired by Goldcorp included a 100% interest in the Peñasquito Project, a 100% interest in the Marlin Mine, a 662/3% interest in the Marigold Mine, a 100% interest in the El Sauzal Mine and a 100% interest in the San Martin Mine. Effective November 15, 2006, in connection with the Glamis Acquisition, Ian Telfer, former President and Chief Executive Officer of Goldcorp, was appointed Chairman of Goldcorp, C. Kevin McArthur, former President and Chief Executive Officer of Glamis, was appointed a director, President and Chief Executive Officer of Goldcorp, Charles Jeannes, former Executive Vice President, Administration, General Counsel and Secretary of Glamis, was appointed Executive Vice President, Corporate Development of Goldcorp, and Douglas Holtby, former Chairman of Goldcorp, was appointed Vice Chairman and Lead Director of Goldcorp. Also effective November 15, 2006, the board of directors of Goldcorp was reconstituted with six members from the board of directors of Goldcorp (Ian Telfer, Douglas Holtby, John Bell, Lawrence Bell, Beverley Briscoe and Peter Dey) and four members from the board of directors of Glamis (C. Kevin McArthur, P. Randy Reifel, A. Dan Rovig and Kenneth F. Williamson). The Corporation filed a business acquisition report dated January 17, 2007 relating to the Glamis Acquisition and a copy of such report is available under the Corporation’s profile at www.sedar.com.
Sale of Mt. Milligan
     On July 24, 2006, the Corporation completed the sale of Mt. Milligan and certain other Canadian exploration interests to Terrane. Goldcorp acquired these interests from Barrick in May 2006. In consideration, the Corporation received 240 million convertible Series A preferred shares of Terrane at a price of C$0.50 per share. The preferred shares are convertible into common shares of Terrane at the option of Goldcorp at any time without any further consideration. As of July 24, 2006 (the date of the transaction), on an as-converted basis, Goldcorp would have owned an 81% equity interest in Terrane’s issued and outstanding shares. Due to subsequent action by Terrane, Goldcorp’s interest on an as-converted basis has been diluted to an approximate 68% equity interest. The preferred shares are not entitled to dividends, are non-transferable without the prior written consent of Terrane, are non-redeemable, non-retractable, non-voting and if not previously converted will be automatically converted into common shares on the 20th anniversary of their issuance.
Warrant Transaction
     In June 2006, Goldcorp received proceeds of more than $450 million upon the early exercise of five series of listed common share purchase warrants. These proceeds were subsequently used to repay credit facilities drawn down to fund the acquisition of Placer Dome (CLA) Limited (“Placer CLA”).

- 9 -


 

Placer CLA Acquisition
     On May 12, 2006, Goldcorp acquired all of the issued and outstanding shares of Placer CLA from Barrick Gold Corporation (“Barrick”) for a purchase price of approximately $1.6 billion (the “Placer CLA Acquisition”). The assets acquired by Goldcorp included a 100% interest in the Campbell Complex, a 50% interest in the La Coipa Mine, a 40% interest in the Pueblo Viejo Project, a 51% interest in the Porcupine Mine and a 68% interest in the Musselwhite Mine. Goldcorp used a portion of its then current cash balances and existing credit facilities to fund the Placer CLA Acquisition. The Corporation filed a business acquisition report dated July 26, 2006 relating to the Placer CLA Acquisition and a copy of such report is available under the Corporation’s profile at www.sedar.com.
Acquisition of Virginia Gold Mines
     On March 31, 2006, Goldcorp completed the acquisition of Virginia Gold Mines Inc. and retained the Éléonore Project in the James Bay region of Québec pursuant to a plan of arrangement. Goldcorp is continuing aggressive exploration and development on the Éléonore property, with resource and scoping studies continuing throughout 2007.
Wheaton Merger
     On April 15, 2005, Goldcorp completed its merger (the “Wheaton Merger”) with Wheaton River Minerals Ltd. (“Wheaton”). The Corporation filed a business acquisition report dated April 5, 2005 relating to the Wheaton Merger and a copy of such report is available under the Corporation’s profile at www.sedar.com.
DESCRIPTION OF THE BUSINESS
     Goldcorp is engaged in the acquisition, exploration, development and operation of precious metal properties. The Corporation continues to investigate and negotiate the acquisition of additional precious metal mining properties or interests in such properties. There is no assurance that any such investigations or negotiations will result in the completion of an acquisition.
Principal Products
     The Corporation’s principal product is gold. As a result of the Wheaton Merger, in addition to gold, the Corporation also produces silver and copper. As a result of the Glamis Acquisition, the Corporation is expected to be a future producer of lead and zinc from the Peñasquito Project. There are worldwide gold, silver, copper, lead and zinc markets into which the Corporation can sell and, as a result, the Corporation will not be dependent on a particular purchaser with regard to the sale of the gold, silver, copper, lead and zinc which it produces.
Competitive Conditions
     The precious metal mineral exploration and mining business is a competitive business. The Corporation competes with numerous other companies and individuals in the search for and the acquisition of attractive precious metal mineral properties. The ability of the Corporation to acquire precious metal mineral properties in the future will depend not only on its ability to develop its present properties, but also on its ability to select and acquire suitable producing properties or prospects for precious metal development or mineral exploration.
Operations
Raw Materials
     The Corporation has (i) gold mineral reserves at the Red Lake Gold Mines, the Porcupine Mine, the Musselwhite Mine, the Marigold Mine, the Wharf Mine, the El Sauzal Mine and the Nukay Mine; (ii) gold and silver mineral reserves at the Los Filos Mine, the San Dimas Mines and the Marlin Mine; (iii) gold and copper mineral reserves at the Alumbrera Mine; (iv) gold, silver and copper mineral reserves at the Pueblo Viejo Project; and (v) gold, silver, lead and zinc mineral reserves at the Peñasquito Project.

- 10 -


 

Environmental Protection Requirements
     The Corporation’s mining, exploration and development activities are subject to various levels of federal, provincial and state laws and regulations relating to the protection of the environment, including requirements for closure and reclamation of mining properties. See disclosure regarding environmental matters under the respective descriptions of the Corporation’s mineral projects herein for further details.
Employees
     As at December 31, 2007, the Corporation had the following employees and contractors:
                                 
Location   Full-Time Salaried   Hourly (Non-Union)   Hourly (Union)   Contractors
Vancouver Office
    55       0       0       1  
Toronto Office
    14       0       0       0  
Reno Office
    18       0       0       0  
Mexico Offices (1)
    115       0       0       0  
Red Lake Gold Mines
    229       317       0       624 (2)
Porcupine Mine
    179       194       251       128  
Musselwhite Mine
    396       0       0       114  
Marigold Mine
    27       183       0       3  
Wharf Mine
    25       113       0       3  
Éléonore Project
    36       10       0       106  
Los Filos Mine
    133       0       462       654  
El Sauzal Mine
    94       201       0       112  
San Dimas Mines
    100       0       487       548  
Nukay Mine
    29       0       79       190  
Peñasquito Project
    120       279       0       2,018  
Marlin Mine
    246       698       0       460  
San Martin Mine
    18       0       154       0  
Cerro Blanco Project
    28       14       0       34  
 
    1862       2009       1433       4,995  
 
(1)   This represents the Corporation’s regional offices in Mexico.
 
(2)   This number represents the total number of active contractors as of December 31, 2007. As of January 1, 2008, 300 hourly and 17 salaried employees from Dynatec Corporation (“Dynatec”) of Richmond Hill, Ontario were hired by Red Lake Gold Mines. As of January 1, 2008, Red Lake Gold Mines had 246 salaried employees and 617 hourly employees.
Foreign Operations Risks
     The Corporation currently owns 66 2/3% of the Marigold Mine in the United States, 100% of the Wharf Mine in the United States, 40% of the South Arturo Project in the United States, 100% of the Imperial Project in the United States, 100% of the Los Filos Mine in Mexico, 100% of the El Sauzal Mine in Mexico, 100% of the San Dimas Mines in Mexico, 100% of the Nukay Mine in Mexico, 100% of the Peñasquito Project in Mexico, 37.5% of the Alumbrera Mine in Argentina, 100% of the Marlin Mine in Guatemala, 100% of the San Martin Mine in Honduras, 40% of the Pueblo Viejo Project in the Dominican Republic and 100% of the Cerro Blanco Project in Guatemala. Any changes in regulations or shifts in political attitudes in such foreign countries are beyond the control of the Corporation and may adversely affect its business. Future development and operations may be affected in varying degrees by such factors as government regulations (or changes thereto) with respect to the restrictions on production, export controls, income taxes, expropriation of property, repatriation of profits, environmental legislation, land use, water use, land claims of local people and mine safety. The effect of these factors cannot be accurately predicted. See “Risk Factors — Foreign Operations” and “Risk Factors —Subsidiaries”.
Environmental Policy
     Goldcorp has implemented an environmental and sustainability policy which states that the Corporation and its subsidiaries are committed to the protection of life, health and the environment for present and future

- 11 -


 

generations. Resources will be focused to achieve shareholder profitability in all operations without neglecting Goldcorp’s commitment to sustainable development. The needs and culture of the local communities will be respected. All employees are responsible for incorporating into their planning and work the actions necessary to fulfill this commitment.
     To meet these responsibilities, Goldcorp and its subsidiaries will provide its employees with the necessary resources to:
    Design, construct, operate and close the Corporation’s facilities to comply with applicable local regulations and laws and to meet international guidelines.
 
    Promote employee commitment and accountability to this policy and enhance their capabilities in its implementation through the use of integrated management systems.
 
    Promote the development and implementation of effective, realistic systems to minimize risks to health, safety and the environment.
 
    Be proactive in community development programs so the communities are not reliant on the mines for their future.
 
    Communicate openly with employees, local stakeholders and governments on the Corporation’s plans, programs and performance.
 
    Work cooperatively with government agencies, local communities, educational institutions and suppliers to achieve safe handling, use and disposal of all of the Corporation’s materials, resources and products.
 
    Use the best technologies to continuously improve the safe, efficient use of resources, processes and materials.
Technical Information
CIM Standards Definitions
     The estimated mineral reserves and mineral resources for the Red Lake Gold Mines, the Porcupine Mine, the Musselwhite Mine, the Marigold Mine, the Wharf Mine, the Éléonore Project, the South Arturo Project, the Imperial Project, the Los Filos Mine, the El Sauzal Mine, the San Dimas Mines, the Nukay Mine, the Peñasquito Project, the Marlin Mine, the Pueblo Viejo Project and the Cerro Blanco Project, and have been calculated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) — Definitions Adopted by CIM Council on December 11, 2005 (the “CIM Standards”) which were adopted by the Canadian Securities Administrators’ National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”). The following definitions are reproduced from the CIM Standards:
     The term “Mineral Resourcemeans a concentration or occurrence of natural, solid, inorganic or fossilized organic material in or on the Earth’s crust in such form and quantity and of such grade or quality that it has reasonable prospects for economic extraction. The location, quantity, grade, geological characteristics and continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge. Mineral Resources are sub-divided, in order of increasing geological confidence, into Inferred, Indicated and Measured categories.
     The term “Inferred Mineral Resourcemeans that part of a Mineral Resource for which quantity and grade or quality can be estimated on the basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The estimate is based on limited information and sampling gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes.
     The term “Indicated Mineral Resourcemeans that part of a Mineral Resource for which quantity, grade or quality, densities, shape and physical characteristics, can be estimated with a level of confidence sufficient to

- 12 -


 

allow the appropriate application of technical and economic parameters, to support mine planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough for geological and grade continuity to be reasonably assumed.
     The term Measured Mineral Resourcemeans that part of a Mineral Resource for which quantity, grade or quality, densities, shape, physical characteristics are so well established that they can be estimated with confidence sufficient to allow the appropriate application of technical and economic parameters, to support production planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough to confirm both geological and grade continuity.
     The term Mineral Reservemeans the economically mineable part of a Measured or Indicated Mineral Resource demonstrated by at least a Preliminary Feasibility Study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified. A Mineral Reserve includes diluting materials and allowances for losses that may occur when the material is mined.
     The term Probable Mineral Reservemeans the economically mineable part of an Indicated Mineral Resource and, in some circumstances, a Measured Mineral Resource demonstrated by at least a Preliminary Feasibility Study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified.
     The term Proven Mineral Reservemeans the economically mineable part of a Measured Mineral Resource demonstrated by at least a Preliminary Feasibility Study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction is justified.
JORC Code Definitions
     The estimated ore reserves and mineral resources for the Alumbrera Mine have been calculated in accordance with the current (1999) version of the Australasian Code for Reporting of Mineral Resources and Ore Reserves (the “JORC Code”), the Australian worldwide standards. The JORC Code has been accepted for current disclosure rules in Canada under NI 43-101. The following definitions are reproduced from the JORC Code:
     The term “Mineral Resourcemeans a concentration or occurrence of material of intrinsic economic interest in or on the Earth’s crust in such form and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade, geological characteristics and continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge. Mineral Resources are sub-divided, in order of increasing geological confidence, into Inferred, Indicated and Measured categories.
     The term “Inferred Mineral Resourcemeans that part of a Mineral Resource for which tonnage, grade and mineral content can be estimated with a low level of confidence. It is inferred from geological evidence and assumed but not verified geological and/or grade continuity. It is based on information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes which may be limited or of uncertain quality and reliability.
     The term “Indicated Mineral Resourcemeans that part of a Mineral Resource for which tonnage, densities, shape, physical characteristics, grade and mineral content can be estimated with a reasonable level of confidence. It is based on exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes. The locations are too widely or inappropriately spaced to confirm geological and/or grade continuity but are spaced closely enough for continuity to be assumed.

- 13 -


 

     The term Measured Mineral Resourcemeans that part of a Mineral Resource for which tonnage, densities, shape, physical characteristics, grade and mineral content can be estimated with a high level of confidence. It is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes. The locations are spaced closely enough to confirm geological and/or grade continuity.
     The term Ore Reservemeans the economically mineable part of a Measured or Indicated Mineral Resource. It includes diluting materials and allowances for losses which may occur when the material is mined. Appropriate assessments, which may include feasibility studies, have been carried out, and include consideration of and modification by realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors. These assessments demonstrate at the time of reporting that extraction could reasonably be justified. Ore Reserves are sub-divided in order of increasing confidence into Probable Ore Reserves and Proved Ore Reserves.
     The term Probable Ore Reservemeans the economically mineable part of an Indicated, and in some circumstances Measured Mineral Resource. It includes diluting materials and allowances for losses which may occur when the material is mined. Appropriate assessments, which may include feasibility studies, have been carried out, and include consideration of and modification by realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors. These assessments demonstrate at the time of reporting that extraction could reasonably be justified.
     The term Proved Ore Reservemeans the economically mineable part of a Measured Mineral Resource. It includes diluting materials and allowances for losses which may occur when the material is mined. Appropriate assessments, which may include feasibility studies, have been carried out, and include consideration of and modification by realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors. These assessments demonstrate at the time of reporting that extraction could reasonably be justified.
     The foregoing definitions of Ore Reserves and Mineral Resources as set forth in the JORC Code have been reconciled to the definitions set forth in the CIM Standards. If the Ore Reserves and Mineral Resources for the Alumbrera Mine were estimated in accordance with the definitions in the CIM Standards, there would be no substantive difference in such Ore Reserves and Mineral Resources.
Cautionary Note to United States Investors Concerning Estimates of Measured, Indicated and Inferred Resources
     This section uses the terms “Measured”, “Indicated” and “Inferred” Resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize them. “Inferred Mineral Resources” have a great amount of uncertainty as to their existence, and as to their economic and legal feasibility. It cannot be assumed that all or any part of an Inferred Mineral Resource will ever be upgraded to a higher category. Under Canadian rules, estimates of Inferred Mineral Resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assume that all or any part of Measured or Indicated Mineral Resources will ever be converted into Mineral Reserves. United States investors are also cautioned not to assume that all or any part of an Inferred Mineral Resource exists, or is economically or legally mineable.
Average Total Cash Costs
     “Average total cash costs” figures are calculated in accordance with a standard developed by The Gold Institute, which was a worldwide association of suppliers of gold and gold products and included leading North American gold producers. The Gold Institute ceased operations in 2002, but the standard is the accepted standard of reporting cash costs of production in North America. Adoption of the standard is voluntary and the cost measures presented herein may not be comparable to other similarly titled measures of other companies. Costs include mine site operating costs such as mining, processing, administration, royalties and production taxes, but are exclusive of amortization, reclamation, capital, development and exploration costs. These costs are then divided by ounces sold to arrive at the total cash costs of sales. The measure, along with sales, is considered to be a key indicator of a

- 14 -


 

company’s ability to generate operating earnings and cash flow from its mining operations. This data is furnished to provide additional information and is a non-GAAP measure. It should not be considered in isolation as a substitute for measures of performance prepared in accordance with GAAP and is not necessarily indicative of operating costs presented under GAAP.
Exemption Order
     The Corporation has obtained an order from the appropriate securities regulatory authorities granting it relief from the requirement in NI 43-101 that it file a technical report for the Pueblo Viejo Project not later than filing this annual information form, provided that:
1.   this annual information form includes the following cautionary language:
 
    “The technical disclosure, including the Mineral Reserve and Mineral Resource estimates, in this annual information form with respect to the Pueblo Viejo Project have not been supported by a technical report prepared in accordance with NI 43-101. A technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed.”; and
3.   the Corporation files the technical report for the Pueblo Viejo Project as soon as practicable but, in any event, not later than May 15, 2008.
Summary of Ore Reserve/Mineral Reserve and Mineral Resource Estimates
Ore Reserve/Mineral Reserve Estimates
     The following table sets forth the estimated gold, silver and copper Ore Reserves/Mineral Reserves for the Red Lake Gold Mines, the Porcupine Mine, the Musselwhite Mine, the Marigold Mine, the Wharf Mine, the Los Filos Mine, the El Sauzal Mine, the San Dimas Mines, the Nukay Mine, the Peñasquito Project, the Alumbrera Mine, the Marlin Mine and the Pueblo Viejo Project as of December 31, 2007, except as set forth in the notes to the table:
Proved/Proven and Probable Gold, Silver and Copper Ore/Mineral Reserves (1)(15)
                                                                 
                    Grade   Contained Metal
Deposit   Category   Tonnes   Gold   Silver   Copper   Gold   Silver   Copper
            (millions)   (grams   (grams   (%)   (millions of   (millions of   (millions of
                    per tonne)   per tonne)           ounces)   ounces)   pounds)
Red Lake Gold Mines (2)
  Proven     0.96       36.12                   1.12              
 
  Probable     5.90       17.86                   3.39              
 
                                                               
 
  Proven + Probable     6.87       20.42                   4.51              
 
                                                               
 
                                                               
Porcupine Mine (3)
  Proven     26.12       1.35                   1.13              
 
  Probable     32.56       1.67                   1.75              
 
                                                               
 
  Proven + Probable     58.67       1.53                   2.88              
 
                                                               
 
                                                               
Musselwhite Mine (4)
  Proven     8.59       6.23                   1.72              
 
  Probable     1.16       7.05                   0.26              
 
                                                               
 
  Proven + Probable     9.74       6.32                   1.98              
 
                                                               
 
                                                               
Marigold Mine (5)
  Proven     26.79       0.72                   0.62              
(Goldcorp’s 662/3%
  Probable     29.65       0.67                   0.64              
 
                                                               
interest)
  Proven + Probable     56.44       0.70                   1.26              
 
                                                               
 
                                                               
Wharf Mine (6)
  Proven     2.34       0.82                   0.06              
 
  Probable     5.78       0.85                   0.16              
 
                                                               
 
  Proven + Probable     8.12       0.84                   0.22              
 
                                                               
 
                                                               
Los Filos Mine (7)
  Proven     33.71       0.83       3.4             0.90       3.7        
 
  Probable     243.77       0.61       6.2             4.75       48.8        
 
                                                               
 
  Proven + Probable     277.47       0.63       5.9             5.64       52.5        
 
                                                               
 
                                                               
El Sauzal Mine (8)
  Proven     6.03       2.24                   0.43              
 
  Probable     1.08       4.02                   0.14              
 
                                                               
 
  Proven + Probable     7.10       2.51                   0.57              
 
                                                               
 
                                                               
San Dimas Mines (9)
  Proven     1.60       5.76       387.1             0.30       19.9        
 
  Probable     3.08       5.23       378.2             0.52       37.5        
 
                                                               
 
  Proven + Probable     4.68       5.41       381.2             0.81       57.3        
 
                                                               
 
                                                               
Nukay Mine (10)
  Proven     1.36       6.99                   0.31              
 
  Probable     3.15       5.97                   0.61              
 
                                                               
 
  Proven + Probable     4.51       6.28                   0.91              
 
                                                               
 
                                                               
Peñasquito Project (11)
  Proven     426.80       0.57       34.0             7.85       466.9        
Mill
  Probable     380.30       0.37       27.2             4.55       332.6        
 
                                                               
 
  Proven + Probable     807.10       0.48       30.8             12.40       799.5        
 
                                                               
 
                                                               
Peñasquito Project (11)
  Proven     42.20       0.21       20.9             0.28       28.3        
Heap Leach
  Probable     68.30       0.17       16.4             0.37       36.1        
 
                                                               
 
  Proven + Probable     110.50       0.18       18.1             0.65       64.4        
 
                                                               
 
                                                               
Alumbrera Mine (12)
  Proved     138.75       0.45             0.43       2.00             1,317  
(Goldcorp’s 37.5%
  Probable     3.75       0.35             0.38       0.04             31  
 
                                                               
interest)
  Proved + Probable     142.50       0.45             0.43       2.04             1,348  
 
                                                               

- 15 -


 

                                                                 
                    Grade   Contained Metal
Deposit   Category   Tonnes   Gold   Silver   Copper   Gold   Silver   Copper
            (millions)   (grams   (grams   (%)   (millions of   (millions of   (millions of
                    per tonne)   per tonne)           ounces)   ounces)   pounds)
Marlin Mine (13)
  Proven     4.10       5.61       152.8             0.74       20.1        
 
  Probable     11.46       4.11       98.1             1.51       36.1        
 
                                                               
 
  Proven + Probable     15.56       4.50       112.5             2.25       56.3        
 
                                                               
 
                                                               
Pueblo Viejo Project (14)
  Proven     4.50       3.39       18.9       0.10       0.49       2.7       10  
(Goldcorp’s 40%
  Probable     81.16       2.88       14.6       0.09       7.53       36.4       145  
 
                                                               
interest)
  Proven + Probable     85.65       2.91       14.8       0.09       8.02       39.2       155  
 
                                                               
 
                                                               
Total
  Proved/Proven                                     17.95       541.6       1,327  
 
  Probable                                     26.20       527.5       176  
 
                                                               
 
  Proved/Proven + Probable                                     44.15       1,069.2       1,503  
 
                                                               
 
(1)   All Mineral Reserves or Ore Reserves have been calculated in accordance with the CIM Standards or the JORC Code. The JORC Code has been accepted for current disclosure rules in Canada under NI 43-101. All Mineral Reserves and Ore Reserves have been reported as of December 31, 2007, with the following exceptions:
 
       •   Mineral Reserves for the Alumbrera Mine are reported as of June 30, 2007
 
 
     •   Mineral Reserves for the Pueblo Viejo Project have not been supported by a technical report prepared in accordance with NI 43-101. See note 14 below.
 
(2)   The Mineral Reserves for Red Lake Gold Mines set out in the table above have been estimated by Stephane Blais, P.Eng. at Red Lake Gold Mines who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Canada and the United States — Red Lake Gold Mines, Canada — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(3)   The Mineral Reserves for the Porcupine Mine set out in the table above have been estimated by Stephen Price, P.Geo. and Imola Götz, P.Eng., each at the Porcupine Mine, who are qualified persons under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(4)   The Mineral Reserves for the Musselwhite Mine set out in the table above have been estimated by Andrew Cheatle, P.Geo. and Tim Sanford, P.Eng., both at the Musselwhite Mine, who are qualified persons under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(5)   The Mineral Reserves for the Marigold Mine set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, and Patricia A. Maloney, P.Eng., Marigold Mining Co., who are qualified persons under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(6)   The Mineral Reserves for the Wharf Mine set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, and Fred H. Brown, CPG, Independent Geological Consultant, who are qualified persons under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(7)   The Mineral Reserves of the Los Filos Mine set out in the above table have been estimated by Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, S.A. de C.V. (“Luismin”), who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Mexico — Los Filos Mine, Mexico — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(8)   The Mineral Reserves for the El Sauzal Mine set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(9)   The Mineral Reserves for the San Dimas Mines set out in the table above have been estimated by Velasquez Spring, P.Eng., Senior Geologist, and Gordon Watts, P.Eng., Senior Associate Mineral Economist, both with Watts, Griffis and McOuat Limited, who are qualified persons under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(10)   The Mineral Reserves for the Nukay Mine set out in the table above have been estimated by Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(11)   The Mineral Reserves for the Peñasquito Project set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Mexico — Peñasquito Project, Mexico — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(12)   The Ore Reserves for the Alumbrera Mine set out in the table above have been estimated by Luis Rivera, MAusIMM at Minera Alumbrera Limited, who is a qualified person under NI 43-101 and a competent person under the JORC Code. The Mineral Reserves are classified as proved and probable, and are based on the JORC Code. See “Description of the Business — Mineral Properties — Central and South America — Alumbrera Mine, Argentina — Ore Reserve and Mineral Resource Estimates” for further details.
 
(13)   The Mineral Reserves for the Marlin Mine set out in the table above have been estimated by Michael G. Hester, FAusIMM, B.Sc., M.S., Independent Mining Consultants, Inc., who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Central and South America — Marlin Mine, Guatemala — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(14)   The Mineral Reserves for the Pueblo Viejo Project set out in the table above have not been supported by a technical report prepared in accordance with NI 43-101. A technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed. See “Description of the Business — Mineral Properties — Central and South America — Pueblo Viejo Project, Dominican Republic — Mineral Reserve and Mineral Resource Estimates” for further details.

- 16 -


 

(15)   Numbers may not add up due to rounding.
     The following table sets forth the estimated lead and zinc Mineral Reserves for the Peñasquito Project – Mill as of December 31, 2007:
Proven and Probable Lead and Zinc Mineral Reserves (1)(2)(3)
                                         
            Grade   Contained Metal
Category   Tonnes   Lead   Zinc   Lead   Zinc
    (millions)   (%)   (%)   (millions of   (millions of
                            pounds)   pounds)
Proven
    426.80       0.36       0.78       3,432       7,365  
Probable
    380.30       0.29       0.65       2,444       5,442  
 
                                       
Proven + Probable
    807.10       0.33       0.72       5,876       12,806  
 
                                       
 
(1)   All Mineral Reserves have been calculated in accordance with the CIM Standards.
 
(2)   The Mineral Reserves for the Peñasquito Project set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Mexico — Peñasquito Project, Mexico — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(3)   Numbers may not add up due to rounding.
Mineral Resource Estimates
Cautionary Note to United States Investors Concerning Estimates of Measured, Indicated and Inferred Resources
     This section uses the terms “Measured”, “Indicated” and “Inferred” Resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize them. “Inferred Mineral Resources” have a great amount of uncertainty as to their existence, and as to their economic and legal feasibility. It cannot be assumed that all or any part of an Inferred Mineral Resource will ever be upgraded to a higher category. Under Canadian rules, estimates of Inferred Mineral Resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assume that all or any part of Measured or Indicated Mineral Resources will ever be converted into Mineral Reserves. United States investors are also cautioned not to assume that all or any part of an Inferred Mineral Resource exists, or is economically or legally mineable.
     The following table sets forth the estimated gold, silver and copper Mineral Resources for the Red Lake Gold Mines, the Porcupine Mine, the Musselwhite Mine, the Marigold Mine, the Wharf Mine, the Éléonore Project, the South Arturo Project, the Imperial Project, the Los Filos Mine, the El Sauzal Mine, the San Dimas Mines, the Nukay Mine, the Peñasquito Project, the Marlin Mine, the Pueblo Viejo Project and the Cerro Blanco Project as of December 31, 2007:

- 17 -


 

Measured, Indicated and Inferred Gold, Silver and Copper Mineral Resources (1)(18)(19)
(excluding Proved/Proven and Probable Mineral Reserves)
                                                                 
                    Grade   Contained Metal
Deposit   Category   Tonnes   Gold   Silver   Copper   Gold   Silver   Copper
            (millions)   (grams   (grams   (%)   (millions of   (millions of   (millions of
                    per tonne)   per tonne)           ounces)   ounces)   pounds)
Red Lake Gold Mines (2)
  Measured     0.73       24.03                   0.56              
 
  Indicated     3.17       17.10                   1.74              
 
                                                               
 
  Measured + Indicated     3.89       18.39                   2.30              
 
                                                               
 
  Inferred     6.41       18.26                   3.76              
 
                                                               
Porcupine Mine (3)
  Measured     5.34       2.27                   0.39              
 
  Indicated     68.05       1.61                   3.52              
 
                                                               
 
  Measured + Indicated     73.38       1.66                   3.91              
 
                                                               
 
  Inferred     43.94       1.67                   2.35              
 
                                                               
Musselwhite Mine (4)
  Measured     1.15       5.62                   0.21              
 
  Indicated     1.86       6.14                   0.37              
 
                                                               
 
  Measured + Indicated     3.00       5.94                   0.57              
 
                                                               
 
  Inferred     3.86       6.19                   0.77              
 
                                                               
Marigold Mine (5)
  Measured     12.70       0.67                   0.27              
(Goldcorp’s 662/3%
  Indicated     18.24       0.71                   0.42              
 
                                                               
interest)
  Measured + Indicated     30.94       0.70                   0.69              
 
                                                               
 
  Inferred     122.53       0.43                   1.68              
 
                                                               
Wharf Mine (6)
  Measured     3.10       0.74                   0.07              
 
  Indicated     4.77       0.72                   0.11              
 
                                                               
 
  Measured + Indicated     7.86       0.73                   0.18              
 
                                                               
 
  Inferred     4.01       0.82                   0.11              
 
                                                               
Éléonore Project (7)
  Measured                                          
 
  Indicated     10.78       7.23                   2.51              
 
                                                               
 
  Measured + Indicated     10.78       7.23                   2.51              
 
                                                               
 
  Inferred     5.63       6.47                   1.17              
 
                                                               
South Arturo Project (8)
  Measured                                          
(Goldcorp’s 40%
  Indicated     6.51       2.40       11.7             0.50       2.5        
 
                                                               
interest)
  Measured + Indicated     6.51       2.40       11.7             0.50       2.5        
 
                                                               
 
  Inferred     0.22       0.70       3.4             0.01       0.0        
 
                                                               
Imperial Project (9)
  Measured     67.88       0.59                   1.29              
 
  Indicated     14.88       0.51                   0.24              
 
                                                               
 
  Measured + Indicated     82.76       0.58                   1.53              
 
                                                               
 
  Inferred     43.83       0.40                   0.56              
 
                                                               
Los Filos Mine (10)
  Measured     6.26       0.69       3.4             0.14       0.7        
 
  Indicated     78.11       0.53       5.3             1.33       13.3        
 
                                                               
 
  Measured + Indicated     84.37       0.54       5.1             1.47       14.0        
 
                                                               
 
  Inferred     73.49       0.56       5.5             1.33       13.0        
 
                                                               
El Sauzal Mine (11)
  Measured     0.48       2.25                   0.04              
 
  Indicated     0.42       2.02                   0.03              
 
                                                               
 
  Measured + Indicated     0.91       2.14                   0.06              
 
                                                               
 
  Inferred     0.02       2.38                   0.00              
 
                                                               
San Dimas Mines (12)
  Measured                                          
 
  Indicated                                          
 
                                                               
 
  Measured + Indicated                                          
 
                                                               
 
  Inferred     17.55       3.29       324.4             1.85       183.0        
 
                                                               
Nukay Mine (13)
  Measured                                          
 
  Indicated     0.90       5.41                   0.16              
 
                                                               
 
  Measured + Indicated     0.90       5.41                   0.16              
 
                                                               
 
  Inferred     8.84       5.70                   1.62              
 
                                                               
Peñasquito Project (14)
  Measured     107.02       0.25       21.2             0.86       73.0        
 
  Indicated     571.44       0.21       18.5             3.87       340.3        
 
                                                               
 
  Measured + Indicated     678.46       0.22       18.9             4.73       413.3        
 
                                                               
 
  Inferred     1,220.00       0.23       13.0             9.02       509.9        

- 18 -


 

                                                                 
                    Grade   Contained Metal
Deposit   Category   Tonnes   Gold   Silver   Copper   Gold   Silver   Copper
            (millions)   (grams   (grams   (%)   (millions of   (millions of   (millions of
                    per tonne)   per tonne)           ounces)   ounces)   pounds)
Marlin Mine (15)
  Measured     0.70       1.67       44.4             0.04       1.0        
 
  Indicated     2.21       1.45       47.5             0.10       3.4        
 
                                                               
 
  Measured + Indicated     2.91       1.50       46.8             0.14       4.4        
 
                                                               
 
  Inferred     2.21       4.06       146.7             0.29       10.4        
 
                                                               
Pueblo Viejo Project (16)
  Measured     0.50       2.67       7.0       0.04       0.04       0.1       1  
(Goldcorp’s 40%
  Indicated     16.64       2.40       6.8       0.04       1.28       3.6       15  
 
                                                               
interest)
  Measured + Indicated     17.14       2.40       6.8       0.04       1.32       3.7       16  
 
                                                               
 
  Inferred     32.57       2.46       3.4       0.02       2.58       3.6       16  
 
                                                               
Cerro Blanco Project (17)
  Measured                                          
 
  Indicated     2.52       15.64       72.0             1.27       5.8        
 
                                                               
 
  Measured + Indicated     2.52       15.64       72.0             1.27       5.8        
 
                                                               
 
  Inferred     1.35       15.31       59.6             0.67       2.6        
 
                                                               
Total
  Measured                                     3.92       74.8        
 
  Indicated                                     17.45       368.9       15  
 
                                                               
 
  Measured + Indicated                                     21.37       443.7       15  
 
                                                               
 
  Inferred                                     27.77       722.5       16  
 
(1)   All Mineral Resources have been calculated in accordance with the CIM Standards or the JORC Code. The JORC Code has been accepted for current disclosure rules in Canada under NI 43-101. All Mineral Resources have been reported as of December 31, 2007, with the following exceptions:
 
       •   Mineral Resources for the Imperial Project are reported as of January 1, 1997
 
 
     •   Mineral Resources for the Cerro Blanco Project are as reported by Glamis in its press release dated December 1, 2005
 
 
     •   Mineral Resources for the Pueblo Viejo Project have not been supported by a technical report prepared in accordance with NI 43-101. See note 16 below.
 
(2)   The Mineral Resources for Red Lake Gold Mines set out in the table above have been estimated by Dean Crick, M.Sc., P.Geo., Red Lake Gold Mines, who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Canada and the United States — Red Lake Gold Mines, Ontario — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(3)   The Mineral Resources for the Porcupine Mine set out in the table above have been estimated by Stephen Price, P.Geo., Patti Nakai-Lajoie, P.Geo. and Imola Götz, P.Eng., each at the Porcupine Mine, who are qualified persons under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.
 
(4)   The Mineral Resources for the Musselwhite Mine set out in the table above have been estimated by Andrew Cheatle, P.Geo. and Tim Sanford, P.Eng., each at the Musselwhite Mine, who are qualified persons under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.
 
(5)   The Mineral Resources for the Marigold Mine set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, and Patricia A. Maloney, P.Eng., Marigold Mining Co., who are qualified persons under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.
 
(6)   The Mineral Resources for the Wharf Mine set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, and Fred H. Brown, CPG, Independent Geological Consultant, who are qualified persons under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.
 
(7)   The Mineral Resources for the Éléonore Project set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, Jacques Simoneau, P.Geo., Les Mines Opinaca Ltée, and Nathalie Prud’homme, P.Geo., Les Mines Opinaca Ltée, who are qualified persons, who are qualified persons under NI 43-101. The Mineral Resources are classified as indicated and inferred, and are based on the CIM Standards.
 
(8)   The Mineral Resources for the South Arturo Project set out in the table above have been estimated by Barrick Gold Corporation and reviewed by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, who is a qualified person under NI 43-101. The Mineral Resources are classified as indicated and inferred, and are based on the CIM Standards.
 
(9)   The Mineral Resources for the Imperial Project set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.
 
(10)   The Mineral Resources for the Los Filos Mine set out in the table above have been estimated by Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Mexico — Los Filos Mine, Mexico — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(11)   The Mineral Resources for the El Sauzal Mine set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp and Steven Ristorcelli, P.Geo., Mine Development Associates, Inc., who are qualified persons under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.
 
(12)   The Mineral Resources for the San Dimas Mines set out in the table above have been estimated by Velasquez Spring, P.Eng., Senior Geologist, and Gordon Watts, P.Eng., Senior Associate Mineral Economist, both with Watts, Griffis and McOuat Limited, who are qualified persons under NI 43-101. The Mineral Resources are classified as inferred, and are based on the CIM Standards.
 
(13)   The Mineral Resources for the Nukay Mine set out in the table above have been estimated by Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.

- 19 -


 

(14)   The Mineral Resources for the Peñasquito Project set out in the table above have been estimated by Fred H. Brown, CPG, Independent Geological Consultant, who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Mexico — Peñasquito Project, Mexico — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(15)   The Mineral Resources for the Marlin Mine set out in the table above have been estimated by Michael G. Hester, FAusIMM, B.Sc., M.S., Independent Mining Consultants, Inc., who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Central and South America — Marlin Mine, Guatemala — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(16)   The Mineral Resources for the Pueblo Viejo Project set out in the table above have not been supported by a technical report prepared in accordance with NI 43-101. A technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed. See “Description of the Business — Mineral Properties — Central and South America — Pueblo Viejo Project, Dominican Republic — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(17)   The Mineral Resources for the Cerro Blanco Project set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, who is a qualified person under NI 43-101. The Mineral Resources are classified as indicated and inferred, and are based on the CIM Standards.
 
(18)   Mineral Resources are not known with the same degree of certainty as Mineral Reserves and do not have demonstrated economic viability.
 
(19)   Numbers may not add up due to rounding.
     The following table sets forth the estimated lead and zinc Mineral Resources for the Peñasquito Project and the Pueblo Viejo Project as of December 31, 2007:
Measured, Indicated and Inferred Lead and Zinc Mineral Resources (1)(4)
(excluding Proven and Probable Mineral Reserves)
                                                 
                    Grade   Contained Metal
Deposit   Category   Tonnes   Lead   Zinc   Lead   Zinc
            (millions)   (%)   (%)   (millions of   (millions of
                                    pounds)   pounds)
Peñasquito Project (2)
  Measured     107.02       0.23       0.62       536       1,453  
Mill
  Indicated     571.44       0.19       0.51       2,406       6,464  
 
                                               
 
  Measured + Indicated     678.46       0.20       0.53       2,942       7,917  
 
                                               
 
  Inferred     1,220.00       0.07       0.50       1,883       13,448  
 
                                               
Pueblo Viejo Project (3)
  Measured     5.00             0.78             85  
(Goldcorp’s 40%
  Indicated     94.43             0.55             1,149  
 
                                               
interest)
  Measured + Indicated     99.43             0.56             1,234  
 
                                               
 
  Inferred     32.57             0.02             13  
 
                                               
Total
  Measured                             536       1,538  
 
  Indicated                             2,406       7,613  
 
                                               
 
  Measured + Indicated                             2,942       9,151  
 
                                               
 
  Inferred                             1,883       13,461  
 
(1)   All Mineral Resources have been calculated in accordance with the CIM Standards.
 
(2)   The Mineral Resources for the Peñasquito Project set out in the table above have been estimated by Fred H. Brown, CPG, Independent Geological Consultant, who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Mexico — Peñasquito Project, Mexico — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(3)   The Mineral Resources for the Pueblo Viejo Project set out in the table above have not been supported by a technical report prepared in accordance with NI 43-101. A technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards. See “Description of the Business — Mineral Properties — Central and South America — Pueblo Viejo Project, Dominican Republic — Mineral Reserve and Mineral Resource Estimates” for further details.
 
(4)   Numbers may not add up due to rounding.

- 20 -


 

Mineral Properties
CANADA AND THE UNITED STATES
     The Corporation’s properties in Canada and the United States include Red Lake Gold Mines, the Porcupine Joint Venture, the Musselwhite Joint Venture, the Marigold Mine, the Wharf Mine, the Éléonore Project, the South Arturo Project and the Imperial Project.
RED LAKE GOLD MINES, CANADA
     Red Lake Gold Mines, an Ontario partnership, was formed on April 2, 2007 between Goldcorp Canada as to a 28% interest and Goldcorp Inc. as to a 72% interest for the principal purpose of operating and developing the combined operations of the Red Lake Complex and the Campbell Complex, each located at or about the town of Red Lake, in the province of Ontario, and to carry out all activities in connection with or ancillary thereto.
     At the request of the Corporation, Dean Crick, M.Sc., P.Geo., Stephane Blais, P.Eng. and Anthony Stechishen, P.Geo. prepared a technical report dated November 17, 2006 entitled “The Red Lake Gold Mines Property — Red Lake Mining Division” (the “Red Lake Gold Mines Report”). Dean Crick, Stephane Blais and Anthony Stechishen are each qualified persons under NI 43-101.
     The following description of the properties held by Red Lake Gold Mines has been summarized from the Red Lake Gold Mines Report and readers should consult the Red Lake Gold Mines Report to obtain further particulars regarding the properties held by the Red Lake Gold Mines. The Red Lake Gold Mines Report is available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile.
Property Description and Location
     The properties held by Red Lake Gold Mines cover approximately 2,335 hectares located in the Red Lake Mining Division within the District of Kenora in northwestern Ontario. The Red Lake Gold Mines’ properties are located in the Canadian Shield, approximately 180 kilometres north of Dryden. The Red Lake Complex consists of 89 patented claims covering 1,254 hectares and the Campbell Complex consists of 77 patented mineral claims covering 1,084 hectares. The Red Lake Gold Mines’ properties have been legally surveyed for all of the patented claims.
Accessibility, Climate, Local Resources, Infrastructure and Physiography
     The Red Lake Gold Mines’ properties are located in the Municipality of Red Lake in northwestern Ontario, Canada. The Municipality of Red Lake is comprised of the towns of Madsen and McKenzie Island, Red Lake, Cochenour, Balmerstown, Starratt Olsen and Flat Lake. The Red Lake area is accessible by Highway 105, which joins the Trans Canada Highway at Vermilion Bay, 175 kilometres south and 100 kilometres east of Kenora. Commercial air service from Thunder Bay and Winnipeg to the community is available several times a day.
     The climate in the Red Lake area is typical of a northern continental boreal climate with warm summers and cold winters.
     The Municipality of Red Lake has a population of approximately 5,500. Other industries in the Municipality of Red Lake include logging and tourism. Local infrastructure is well developed in the Red Lake area, with all the amenities needed for operations by Red Lake Gold Mines available locally. Potable water is supplied by the Municipality. Process water is taken from Balmer Lake and Sandy Bay. Ontario Hydro supplies power. Each Complex has 30 megawatts of transformer capability but is limited to 26 megawatts by the incoming line. There are multiple transformers throughout the Complexes, which step voltage down to 4,160, 2,300 and 575 volts.
     The Red Lake area has topography typical of the Canadian shield with irregular hummocky hills and discontinuous ridges created by glaciofluvial material and till. These are separated by depressions and hollows occupied by lakes, ponds and muskeg. Much of the Red Lake region is undeveloped and is accessible only by air or

- 21 -


 

canoe. The natural vegetation is predominantly black spruce, fir, tamarack and pine. In the better drained elevated areas the vegetation changes to poplar, birch, willow, alder and mountain ash with a variety of shrubs.
     Bedrock outcrops are scattered and consist of less than 5% of the surface area. Soil in the vicinity is characterized by a 30 to 50 centimetre layer of topsoil overlying compact sand with traces of clay, gravel, scattered cobbles and boulders. Low-lying areas contain silty-clay sediments that were deposited in glacial lakes.
History
     The first recorded prospecting in the Red Lake district was carried out by the Northwestern Ontario Exploration Company in 1887, but gold was not discovered in the district until 1922. A brief summary of the Red Lake and Campbell Complexes follows.
Red Lake Complex
     Red Lake was first staked during the Red Lake Gold Rush in 1926. In 1944, the property was re-staked and Dickenson Red Lake Mines Limited was incorporated. Production mining began in 1948 at a rate of 125 tons per day and increased to 500 tons per day in the 1970s, with grades varying between 0.45 and 0.61 ounces of gold per ton. In the early 1980s, the mill capacity was increased to 1,000 tons per day and long-hole stoping was introduced which resulted in a severe drop in production grade. Cut-and-fill mining was subsequently re-introduced and production was increased to about 1,000 tons per day by 1993/4 with the grade ranging from 0.25 and 0.34 ounces of gold per ton. The average recovery rate was 82%. An exploration diamond drilling program initiated in 1995 within the lower levels of the mine resulted in the discovery of a cluster of high grade gold veins between the 30 and 39 levels of the mine (the “High Grade Zone”).
     Between June 1996 and late 1999, operations were suspended due to a strike. Mine staff and outside contractors maintained essential services and supported the exploration program on the property. In September 1998, the feasibility of mining the High Grade Zone Mineral Reserves through a combination of existing mine infrastructure, new development and a new processing facility purchased from Cameco was studied. An operating plan was developed to mine the Mineral Reserves by the mechanized cut-and-fill stope method at a rate of 6,000 tons per day or 219,000 tons per year.
     Mining from the High Grade Zone began in early 2000 and test milling began in July. By year-end, full rated production was achieved with a small stockpile of several thousand tons of crushed ore remaining on surface. Since production restarted in 2000, the exploration to increase resources has focused on the High Grade Zone.
     Since the beginning of operations in 1948 until the end of 2006, 10.09 million tons of ore have been processed at an average head grade of 0.64 ounces per ton to produce 6.46 million ounces of gold. In 2007, 272,914 tons of ore at an average head grade of 1.88 ounces per ton were processed and 499,900 ounces of gold were poured.
Campbell Complex
     The Campbell claims were staked in 1926. Subsequently, there was a period of claim cancellations and restaking of the area. In, 1944, George and Colin Campbell restaked the area. In this period, Campbell Red Lake Mines was incorporated and Dome Mines purchased an option that eventually resulted in Dome Mines acquiring a 57% ownership interest in the company.
     In 1946, after further exploration had been carried out, a four-compartment shaft with four levels was sunk to a depth of 182 metres. Mill construction began in 1948 and the mill went into operation the following year reaching a capacity of 300 tons per day soon after the beginning of operations. By 1953, the shaft was further deepened to 655 metres and soon after a deeper higher grade zone was discovered at the 14th level. The next thirty years of production at Campbell remained consistent.
     A new phase of investment began following the merger between Campbell, Dome and Placer Development to form Placer Dome Inc. (“Placer Dome”). This led to autoclaving, replacing the roasting at the Campbell mill,

- 22 -


 

development of a decline from levels 27 to 30, a mill flotation circuit upgrade, construction of paste fill plant and the commissioning of the Reid Shaft in 1999, which enabled the discovery and development of the DC Zone.
     Since the beginning of operations in 1949 until the end of 2006, 19.74 million tons of ore have been processed at an average head grade of 0.58 ounces per ton to produce 11.35 million ounces of gold. In 2007, 521,872 tons of ore at an average head grade of 0.388 ounces per ton were processed and 200,700 ounces of gold were poured.
Geological Setting
Regional Geology
     The Red Lake greenstone belt is situated in the western portion of the Uchi Subprovince, a typical Achaean granite-greenstone terrain containing eastward trending belts of volcanic and sedimentary rocks and syn-volcanic intrusives. The rocks consist of volcanic and sedimentary assemblages representing magmatic and erosional events occurring over a period of approximately 300 million years.
     The Red Lake greenstone belt outcropping is defined by an east-northeast orientated bow tie shaped, anticline, roughly 40 kilometres long and 20 kilometres across. Two perpendicular axes of mirror symmetry trend east-northeast and southwest defining the bow tie and intersecting at the Dome Stock near Red Lake. The most prominent axis trends east-northeast defining a broad antiform with older rocks of the Balmer Assemblage occupying the hinge flanked by younger rocks of the Huston and Confederation assemblages on its northern and southern flanks. Between the oldest and youngest assemblages is a regional unconformity, overlain by the Huston conglomerate. At each end of the anticline, late-orogenic plutons stope up into the greenstone; the Killala-Baird batholith in the west, and the Walsh Lake pluton and Cat Island pluton in the east.
     The Balmer assemblage, predominantly tholeiitc and komatiitic mafic to ultramafic extrusive rocks, hosts the gold-bearing ore and constitutes over 50% of the Red Lake greenstone belt rocks. The sequence is disconformably overlain by a volcaniclastic/clastic sequence, the Bruce Channel assemblage prominent in the east and the Slate Bay assemblage in the southwest. The Trout Bay assemblage is characterized by predominantly mafic tholeiitic extrusive rocks. A laterally extensive polymict conglomerate belonging to the Huston assemblage marks an angular unconformity between Mesoarchean and Neoarchean strata and is overlain by dominantly calc-alkalic felsic volcanic rocks belonging to the Confederation assemblage.
     Large-scale folding and steep fault systems dominate the eastern part of the Red Lake greenstone belt. Northeast trending synclines and anticlines occur northeast of McKenzie Island west of East Bay. On the eastern side of East Bay, a major fold with a northwest trending fold axis occurs in Bateman and Balmer Townships. In Red Lake Gold Mines operations area, horizons of ultramafics within the basalt-dominated stratigraphy created complex geometries through competency contrast during the mechanical interaction of folding. High strain corridors characterized by pervasive foliation and cleavage development along mafic, ultramafic contacts are clearly distinguishable features using surface mapping and geophysics.
     Quartz-carbonate veining and alteration developed around mafic-ultramafic contacts, particularly fold hinges and in the damage zones of small and large displacement fault/shear zones. Continued shortening and foliation development caused rotation of conjugate shear zones towards parallelism with F2 fold axial surface orientations, producing strong deformation and strain partitioning. Further shortening resulted in strong near-vertical extension and locally the development of reverse faults.
     Auriferous, siliceous, sulphidic alteration and quartz veining, overprinting earlier quartz-carbonate veins, began to develop at this stage, apparently after the bulk of strain and displacements on major fault systems. Minor strike slip movements on fault systems, reflecting at least local changes in the orientation of stress axes, contributed to the dilation and replacement, particularly in ultramafic/mafic defined fold hinge zones abutting fault system.
Metamorphism
     Owing to the volume of late tectonic granitic plutons, a complex history of metamorphic events exists

- 23 -


 

which arises from episodes of burial, crustal thickening, thrusting, baking by felsic intrusions of all sizes and ages, and late hydrothermal alterations focussed along shear zones. Within the Red Lake greenstone belt the alteration is characterized by greenschist metamorphic mineral assemblages, but with amphibolite facies mineral assemblages in areas close to the major plutons.
Local Geology
     The gold bearing zones of the Red Lake and Campbell Complexes occur on the eastern flank of a D2, high strain corridor, known locally as the Cochenour-Gullrock Lake deformation zone or Red Lake Mines trend. These units are subparallel to a regional foliation that strikes from 100° to 120° azimuth, dipping southwest from 65° to 80°.
     At broad scales, the Red Lake Mines trend appears to be hosted by a steeply plunging reclined F2 fold system with south-southwest-dipping axial surface, outlined by the Bruce Channel contact to the north, south and east, and cored by the Balmer mafic-ultramafic assemblage. This fold system has undergone significant modification by a system of steeply-to-moderately southwest dipping fault zones which are interpreted to have developed during D2 deformation, a northeast-southwest oriented shortening.
     The D2 event, comprised of progressive northeast-southwest shortening, resulted in the dismemberment of the F2 folds along axial planar shear structures, displacing the steeply plunging parasitic mafic/ultramafic fold hinges into discrete litho-structural domains.
Site Geology
     The Red Lake Gold Mines’ properties are underlain mainly by tholeiitic basalt and locally by komatiitic basalt of the Balmer assemblage. The mine sequence is completed by peridotitic komatiite, rhyolite and associated mafic intrusions of the Balmer assemblage. The steeply plunging south-southwest folded package is unconformable overlain by felsic volcaniclastics, clastic and chemical sedimentary rocks of the Bruce Channel assemblage defining an enveloping syncline anticline couplet based on younging directions, with the synform hinge located on the northside of the Campbell Complex, east of the HG Young shaft underneath Balmer Lake and the anticlinal hinge in the south central portion of the former partywall boundary and east at the Red Lake Complex. The prominent fabric at the site is the S2 cleavage, trending northwest-southeast, axial planar of the F2 folding, plunging steeply to the south-southwest.
     The major mineralized zones, although hosted in basalt, are associated with a central ultramafic unit, which is a highly carbonatized and altered unit, believed to be either volcanic or plutonic in origin.
     Hydrothermal alteration at the Red Lake Gold Mines’ properties can be subdivided into three main phases: (1) an early alteration subdivided into (a) carbonatization and pervasive biotite (potassic) alteration and (b) early silicification and aluminosilicate-bearing alteration; (2) main-stage vein phase of barren dolomite to ankerite, cockade breccias and sheeted veinlet zones with chloritic alteration; and (3) a mineralization phase with quartz-sericite +/- cordierite alteration and a late episode of veinlet controlled biotite +/- tourmaline alteration.
     The mineralized system at the Red Lake Gold Mines’ properties is a wedge-shaped zone above roughly 27 level which widens upwards and is constrained by bounding fault structures on the northeast and southwest flanks. This wedge is defined by steeply south-dipping and south to south-southwestern plunging litho-structural packages of ultramafic and rhyolitic bodies, enveloped mainly by metabasalts. These bodies outline dismembered folds which also plunge steeply to the south to south-southwestern. Fold hinges are preserved between a series of steeply south-dipping and north-west to west-northwest-striking fault zones separating the detached folds, these major curviplanar fault/shear zones developed in fold limb positions and are approximately axial plane parallel.
Exploration
     Despite a prolific mining history since 1949, minimal exploration activity and development were focused in proximity to the former boundary between the Red Lake and Campbell Complexes which appears to transect the centroid of the ore body. Recently developed inter-mine connections provide operational flexibility and staging

- 24 -


 

platforms for exploration of the internal property boundary targets. Deep exploration depends heavily upon critical development away from the ore body for quality evaluation of highly sought after high grade vein structures to depth.
     The current high priority exploration targets include the High Grade Zone and associated footwall sulphides, the Party Wall Zone, the Deep Campbell Zone, the internal property boundary opportunities, the upper Red Lake sulphides, and surface, bulk mining opportunities. The exploration targets are characterized by relatively smaller high grade vein structures and laterally extensive footwall, lower grade, sulphide ore structures.
Mineralization
     In general, there are three types of mineralization zones encountered at the Red Lake Gold Mines’ properties, namely vein type ore, disseminated sulphide ore and replacement ore. Structures at the site exhibit three trends: conformable northwest, north-south and east-west. The conformable structures are most common and are sub-parallel to the foliation. The vein systems follow these structures. Complex vein arrays are those which also include the north-south and east-west components. The arrays are most common near high angle mafic-ultramafic contacts. The High Grade Zone occurs in such an environment where enhanced dilatency developed and was sustained over a long period of time. Its geometry will combine both conformable and complex vein arrays overprinted by replacement mineralization.
     The ore veins are normally structurally controlled; averaging 1.5 to 1.8 metres in width and extending over strike lengths ranging from 30 to 300 metres. Sulphide replacement zones vary from 3 to 12 metres in width and extend over a strike length of 120 to 180 metres. Gold mineralization zones in the Balmer assemblage of the Red Lake Mines trend can be broadly subdivided into two morphological groups: planar to curviplanar zones and plunging zones.
Drilling
     Diamond drilling has been carried out at the Red Lake Gold Mines’ properties since the beginning of operations. Over the years, various lithological descriptions have been developed for each of the complexes and these have continued to develop and change. Since the merger of the Campbell and Red Lake Complexes, the Corporation has developed a new lithological coding system that incorporates both the old systems.
     In 2007, 612,791 feet of definition, delineation and exploration diamond drilling was conducted by Red Lake Gold Mines.
Red Lake Complex
     The Mineral Resources and Mineral Reserves at and above the 30 level are based on over 21,000 surface and underground drill holes. Currently, the below 30 level database for the High Grade Zone and the sulphide zones contains about 5,700 diamond drill holes totalling more than 2.7 million feet of drilling.
     Exploration drill core is transported to the core facility in sealed boxes. Upon arrival it is marked up by a geologist and then geologically logged while wet. All drill core is logged using computer codes for the various rock types, mineralization, alteration characteristics and structural/geotechnical data. The shear structures containing the various mineralized zones are logged in detail to establish the zone width and sampling interval. Sections of core with high grade visible mineralization are transferred into safe locked storage to ensure that no core is lost or replaced, prior to shipping for assay.
Campbell Complex
     The Campbell drill hole database consists of a total of about 24,500 diamond drill holes, drilled from underground and surface. The channel sample database is comprised of over 81,000 channel cuts. Drill core sample security is maintained throughout the year with geological supervision of transport of the core from the underground/surface drill site, through to the logging facility and to the in-house assay laboratory.

- 25 -


 

     All drill hole collars are surveyed by mine surveyors, and down hole surveys are taken either with a Maxibore survey instrument at 5 foot intervals or an acid test/Tropari every 100 feet. Most of the drill holes greater than 1,000 feet are surveyed using the Maxibore method. All stopes will have channel sampling taken every 8-15 feet to fill in the gaps from diamond drill intercepts. More recently, Reflex and Ranger electronic compass single-shot survey tests are conducted every 100-150 feet down the hole, especially for drill holes exceeding 500 feet in length.
     Half of the core is kept for the majority of exploration and all grassroots exploration drill programs. All holes are logged for lithology, alteration, structure and veining/mineralization and RQD where applicable.
Sampling and Analysis
     Rigorous sampling is done during production for grade control and correlation with Mineral Reserves estimates and production at the Red Lake Gold Mines. At Red Lake, muck and chip sampling is performed on a blast by blast basis by the production geology team, while muck sampling at Campbell is done by the miner during the mucking process. Muck samples are used to provide a general guide and back-up information for day-to-day operations, while test holes are required to ascertain that no mineralization is missed in the walls of the stope.
     The reconciled grade on a stope-by-stope basis is variable between reserves and actual production, but shows reasonable correlation over a longer period of time through averaging of several cut and fill lifts or multiple long-hole blocks in the same ore lens.
Sample Preparation, Analyses and Security
     Drilling, sampling, analysis, data stewardship, ore body modeling and mine planning are carried out in accordance with NI 43-101 industry standards. Regular internal auditing of the Mineral Reserve and Mineral Resource estimation processes and procedures are conducted. The sampling and analytical methods are believed to be appropriate for the style and type of mineralization. Mine geological staff has verified all databases used to generate the geological models and Mineral Resource estimates.
     As a general rule, exploration drilling, especially in new areas of potential or Inferred Mineral Resources, is sampled by taking half core using a diamond saw. Geologists mark the core saw cut using a lumber crayon. The remaining half core is saved for future reference, part of which may be used for metallurgical testing. The remaining portion of the core is stored on site. However, delineation and definition drill holes are sent as whole core for assaying.
     Sample lengths are typically in the one to three foot range, and usually shorter in the higher grade sections. Low-grade rock and waste are typically sampled over two to three foot lengths, averaging 2.20 feet, while very high grade sections are sampled over 0.5 to 2.0 foot intervals with an average of 1.60 feet. The sampling strategy is conducted diligently striking a balance between approaching a consistent sampling interval for improved population statistics while maintaining respect for geologic boundaries.
     Standard fire assay procedures with a gravimetric or AA finish (depending on the anticipated grade of the sample) are carried out on all assays of production samples. Process, most definition, muck and chip data assays are generated using the in-house assay laboratory. A constant monitoring of quality assurance/quality control practices/procedures are conducted on a regular basis to ensure low assay contamination and consistent data accuracy. Overflow sampling and the majority of exploration and surface channel, blast hole and diamond drill hole assays are analyzed at the SGS Lab in Red Lake or the ALS Chemex Lab in Vancouver, British Columbia.
     Metallic screen assay methods are done at SGS in Red Lake for samples with visible gold or for samples where fire assay results reported more than 20 ounces of gold per ton. However, there appears to be no significant difference in results between metallic screen and regular assay methods.
     Exploration assay checks (duplicates and re-runs) are conducted regularly on the pulps and rejects and at the discretion of the geologist submitting the samples where assays did not match physical observations of mineralization.

- 26 -


 

     All samples have barcode tags and are scanned into the computer at sample receiving. Upload of assays is conducted by electronic transfer of certified assay data. Hard copy, official assay certificates are archived.
Mineral Resource and Mineral Reserve Estimates
     The following table sets forth the estimated Mineral Reserves for Red Lake Gold Mine as of December 31, 2007:
Proven and Probable Mineral Reserves (1)(2)(3)(4)(5)
                         
Category   Tonnes   Grade   Contained Metal
    (millions)   (grams per tonne)   (millions of ounces)
Proven
    0.96       36.12       1.12  
Probable
    5.90       17.86       3.39  
 
                       
Proven + Probable
    6.87       20.42       4.51  
 
                       
 
(1)   The Mineral Reserves for Red Lake Gold Mine set out in the table above have been estimated by Stephane Blais, P.Eng., Red Lake Gold Mines, who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(2)   Based on a gold price of $550 per ounce and an exchange rate of 1.15.
 
(3)   The estimated metallurgical recovery rate is 65% to 97%.
 
(4)   The average, diluted, cut-off grade for Mineral Reserves is 0.33 ounces per tonne (12.00 grams per tonne), but ranges from 0.20 ounces per tonne (6.85 grams per tonne) to 0.40 ounces per tonne (13.71 grams per tonne) depending on the zone and mining method. Resource models are diluted to minimum horizontal widths of 7 to 9 feet (2.12 to 2.74 metres) at a zero grade.
 
(5)   Numbers may not add up due to rounding.
     The following table sets forth the estimated Mineral Resources for Red Lake Gold Mine as of December 31, 2007:
Measured and Indicated Mineral Resources (1)(2)(3)(4)(5)
(excluding Proven and Probable Mineral Reserves)
                         
Category   Tonnes   Grade   Contained Metal
    (millions)   (grams per tonne)   (millions of ounces)
Measured
    0.73       24.03       0.56  
Indicated
    3.17       17.10       1.74  
 
                       
Measured + Indicated
    3.89       18.39       2.30  
 
                       
Inferred
    6.41       18.26       3.76  
 
(1)   The Mineral Resources for Red Lake Gold Mine set out in the table above have been estimated by Dean Crick, M.Sc., P.Geo., Red Lake Gold Mines, who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.
 
(2)   Based on a gold price of $650 per ounce and an exchange rate of 1.15.
 
(3)   The average, diluted, cut-off grade for Mineral Resources is 0.26 ounces per tonne (8.91 grams per tonne), but ranges from 0.20 ounces per tonne (6.85 grams per tonne) to 0.40 ounces per tonne (13.71 grams per tonne) depending on the zone. The in situ block model has been diluted to minimum horizontal widths of 4 to 6 feet (1.22 to 1.83 metres).
 
(4)   Mineral Resources are not known with the same degree of certainty as Mineral Reserves and do not have demonstrated economic viability.
 
(5)   Numbers may not add up due to rounding.
Mineral Processing and Metallurgical Testing
Red Lake Complex
     The original Red Lake mill was built in 1948 and was dismantled in early 2000. Construction of a new mill took place during 2000. The new process facilities consist of three separate plants: the crushing plant, the processing plant and the paste fill plant. Commissioning of the crushing plant began in February 2000, the processing plant’s commissioning phase commenced in early July 2000 with the first gold bar being poured on August 1, 2000 and commissioning of the paste fill plant began in August 2000. Commercial production began on

- 27 -


 

January 1, 2001. The mill throughput capacity is 1,250 tonnes per day.
     Unit operations in the processing plant include grinding, gravity concentrating, cyanidation, carbon-in-pulp, carbon elution and reactivation, electrowinning, bullion smelting/refining, cyanide destruction, flotation and concentrate handling. Three types of gold occur in the Red Lake Gold Mines ore requiring these various unit operations.
Campbell Complex
     The Campbell mill was designed in 1949 to treat free milling and refractory gold ore at a rate of 360 tonnes per day. The throughput has been gradually increased over the years to the current 1,850 tonnes per day.
     Conventional crushing and grinding is followed by gravity concentration to recover free milling gold. Refractory gold, finely disseminated in the arsenopyrite and pyrite matrix, is recovered by flotation followed by pressure oxidation, neutralization and CIL.
Mining Methods
     The mining methods currently in use at Red Lake Gold Mines are grouped into four categories: overhand cut and fill, underhand cut and fill, pillar recovery and longhole. The methods were chosen for, among other things, the following reasons: (a) to selectively mine highly variable and complex ore structures, allowing for full production geology control of each ore blast; (b) to reduce dilution in order to make the most of the limited available hoisting capacity by optimizing the grade of the ore hoisted; (c) to mitigate the potential for and damage from seismic events by controlling the open mining span, providing better control of the mining sequence and minimizing the creation of sill pillars; (d) to maximize ore recovery; and (e) to develop methods that could be applied to future mine expansion at depth.
Environmental Considerations and Permitting
     Red Lake Gold Mines operates under the Corporation’s environmental and sustainability policy which commits the operation to a defined standard of environmental stewardship. Red Lake Gold Mines has developed a series of management programs for environmental activities, tailings management and occupational health and safety that enable the Corporation to reach its commitments.
     All requisite material permits have been obtained for the mining and continued development of the site and are in good standing. Federal and provincial environmental legislation is recognized through policies and practices on the site that ensure compliance. The most comprehensive on-site environmental program covers the tailings effluent monitoring. A mine closure plan has been submitted to the Ministry of Northern Development and Mines and the technical portion of the document has been accepted. The tailing ponds are situated in Balmer Township.
     At the Campbell Complex, a nine hectare wetland was constructed to reduce the concentrations of copper, ammonia and low levels of other contaminants occurring in the discharge from waste rock and tailings pond facilities. The metals are removed through naturally occurring water treatment as the discharge water moves through the wetlands during the ice-free season. This process made the Campbell Complex one of the first gold mines in Ontario to use natural, microbial forces to produce a non-toxic discharge. This system is being introduced to the Red Lake Complex.
     The tailings management facility is currently undergoing modifications to address current mill and mine effluent characteristics to ensure discharge water meets all provincial and federal regulations.

- 28 -


 

PORCUPINE JOINT VENTURE, CANADA (non-material property)
     The Corporation acquired its original 51% interest in the Porcupine Joint Venture in connection with the Placer CLA Acquisition. Goldcorp Canada owns the 51% interest and is the operator of the Porcupine Joint Venture. Kinross Gold Corporation held the remaining 49% interest in the Porcupine Joint Venture until December 21, 2007, when the Corporation acquired Kinross Gold Corporation’s interest in the Porcupine Joint Venture. Goldcorp Canada will continue to operate the Porcupine Mine. The Porcupine Joint Venture operates the Hoyle Pond and Dome underground gold mines and the Pamour open pit gold mine. All of the ore produced from the three mines is milled and beneficiated at the Dome Mill, a central milling facility. The properties owned or controlled by the Porcupine Joint Venture have produced more than 64 million ounces of gold since 1910 and include the Dome Mine and Mill, North America’s longest continually operating gold mine/mill combination. The majority of the Porcupine Joint Venture property is located within the city limits of Timmins. The total property area, all of which is within 100 kilometres of the Dome Mill, is approximately 38,000 hectares of mine claims. In 2007, the Corporation’s 51% share of gold production from the Porcupine Mine amounted to 158,400 ounces of gold at a total cash cost of $489 per ounce. With existing mineral reserves, the Porcupine Mine has an expected mine life through to 2016.
MUSSELWHITE JOINT VENTURE, CANADA (non-material property)
     The Corporation acquired its original 68% interest in the Musselwhite Joint Venture in connection with the Placer CLA Acquisition. Goldcorp Canada owns the 68% interest and is the operator of the Musselwhite Joint Venture. Kinross Gold Corporation held the remaining 32% interest in the Musselwhite Joint Venture until December 21, 2007, when the Corporation acquired Kinross Gold Corporation’s interest in the Musselwhite Joint Venture. Goldcorp Canada will continue to operate the Musselwhite Joint Venture. The Musselwhite Joint Venture owns the Musselwhite Mine which is situated in north-western Ontario on the southern shore of Opapimiskan Lake, 480 kilometres by air north of Thunder Bay, on traditional First Nation land. The nearest town, Pickle Lake, is 103 kilometres by air to the south. The Musselwhite Mine is principally an underground gold mine with an associated processing plant that produces nearly a quarter of a million ounces of gold annually. The property held by the Musselwhite Joint Venture consists of a combination of leases and mining claim units covering a total of 17,548 hectares. The Musselwhite Mine commenced commercial production in 1997. In 2007, the Corporation’s 68% share of gold production from the Musselwhite Mine amounted to 155,700 ounces of gold at a total cash cost of $491 per ounce. With existing mineral reserves, the Musselwhite Mine has an expected mine life through to 2015.
MARIGOLD MINE, UNITED STATES (non-material property)
     The Corporation acquired its 662/3% interest in the Marigold Mine in connection with the Glamis Acquisition. Barrick holds the remaining 331/3% interest in the Marigold Mine. The Marigold Mine is situated in Humboldt County, Nevada at the north end of the Battle Mountain-Eureka Trend that extends through central Nevada. The property consists of 28.9 square miles, including 13 square miles of fee mineral interests. The remaining 15.9 square miles are unpatented mining claims, 6.1 square miles of which are not subject to royalties. Royalty rates on leased land range from 3% to 5% of net smelter returns, with rates rising to 7% or 8% on certain parcels depending on the price of gold. The rate for the remaining life of mine is anticipated to average 5.5%. Total royalty expense for 2007 was $5.2 million, of which the Corporation’s share was $3.5 million. The Marigold Mine is a run of mine heap leach operation that commenced production in 1988. The mine was transformed from a modest, conventional milling operation into a large and efficient heap leach mine. In 2007, the Corporation’s 662/3% share of gold production from the Marigold Mine amounted to 93,900 ounces of gold at a total cash cost of $575 per ounce. The Corporation expects production from the Marigold Mine through to 2017.
WHARF MINES, UNITED STATES (non-material property)
     The Wharf Mine property consists of title to, or leases held by Wharf Resources (U.S.A.) Inc. (“Wharf Resources”), which is an indirect wholly-owned subsidiary of the Corporation, on 449 patented and 98 unpatented mining claims, covering approximately 4,205 mineral acres and 3,626 surface acres. The Wharf Mine is situated four miles west of Lead in the Black Hills, a heavily forested, small mountain range located in western South Dakota. The property consists of several areas of adjoining gold mineralization amenable to open pit mining. Wharf Resources holds title to the surface and mineral rights of the claims. All of the Wharf Mine’s total proven and

- 29 -


 

probable mineral reserves are on patented claims. In 2007, gold production from the Wharf Mine amounted to 57,700 ounces of gold at a total cash cost of $369 per ounce. With existing mineral reserves, the Wharf Mine has an expected mine life through to mid 2010.
ÉLÉONORE PROJECT, QUÉBEC (non-material property)
     The Corporation acquired Virginia Gold Mines Ltd. and retained the Éléonore Project in March 2006. The Éléonore Project is located in the Ell Lake area in the north-eastern part of the Opinaca reservoir, approximately 320 kilometres north of the town of Matagami in the James Bay region of Québec, Canada. The Éléonore deposit is a major new gold discovery in a relatively unexplored area in the Province of Québec. It is a unique and significant property located in the core of what Goldcorp believes to be a promising new gold district in North America. The Corporation is continuing aggressive exploration and development on Éléonore, with resource and scoping studies continuing throughout 2007.
     Previous work on the property consisted mainly of surface geological interpretation and subsequently 56 kilometres of drill holes in exploration drilling. The priority on the property is to continue the drilling program while supporting the engineering scoping studies in progress. The ongoing exploration and drilling program is primarily concentrating on three themes:
  –    continuing with the “confirmatory” drilling already in progress,
 
  –    exploring the strike extent of the ore-body at both ends, and
 
  –    exploring the depth potential of the Roberto Zone.
     With the bulk of the infill drilling completed, a project scoping study has been completed to determine the best scale of operation which will mainly be an underground operation, with possibly a small pit. The milling operation will involve conventional gold processing techniques and a suitable tailing dam site has been identified. Regional infrastructure is excellent to support a future mining operation with available power, water and year round highway access nearby. These advantages, together with the Province of Québec being a regulatory friendly environment, further reinforce the quality of this asset.
     In June 2007, the first NI 43-101 compliant mineral resource was calculated on the Roberto Zone. The following table sets forth the estimated Mineral Resources for the Éléonore Project as of December 31, 2007:
Indicated and Inferred Mineral Resources (1)(2)(3)
                         
Category   Tonnes   Gold   Contained Gold
    (millions)   (grams per tonne)   (millions of
                    ounces)
Indicated
    10.78       7.23       2.51  
Inferred
    5.63       6.47       1.17  
 
(1)   The Mineral Resources for the Éléonore Project set out in the table above have been estimated by Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, Jacques Simoneau, P.Geo., Les Mines Opinaca Ltée, and Nathalie Prud’homme, P.Geo., Les Mines Opinaca Ltée, who are qualified persons under NI 43-101.
 
(2)   Cut-off grade was 3.5 grams of gold per tonne using $650 per ounce of gold.
 
(3)   Mineral Resources are not known with the same degree of certainty as Mineral Reserves and do not have demonstrated economic viability.
     Exploration efforts are focusing on defining gold mineralization at a vertical depth between 700 and 1,200 metres and testing the northern and southern extensions of the deposit.
     Significant progress has been made on project development at Éléonore, including completion of engineering work on an access road and airstrip. Additional data will support analysis of depth and breadth of deposit mineralization in order to properly scope shaft dimension, mill size and equipment selection. Geotechnical drilling in the outcrop area and condemnation drilling of key infrastructure sites is also continuing. The access road

- 30 -


 

and airstrip permit, which includes a full Environmental & Social Impact Assessment, has been submitted to regulatory authorities for approval.
     In 2007, extensive drilling continued, feasibility work was initiated, significant progress toward the development of a collaboration agreement with the Cree Nation of Wemindji was achieved and the Corporation initiated the main mine development permit process by submitting the Project Notice to regulatory authorities. A feasibility study is expected to be completed by 2008 with production expected by late 2011. Capital expenditures to December 31, 2007 amounted to $62 million.
SOUTH ARTURO PROJECT, UNITED STATES (non-material property)
     The Corporation holds a 40% interest in the South Arturo Project. Barrick Gold Corporation holds the remaining 60% interest in the project and is the manager of this project. The South Arturo Project is located 40 kilometres northwest of Carlin, Nevada and 8 miles northwest of Barrick’s Goldstrike operation in Elko County, Nevada. The South Arturo Project is located on the old Dee mine site on the northern Carlin trend. This trend is defined by a north-northwest alignment of gold deposits in upper plate windows exposing lower plate rocks. The project is located within the northern window. Most of the mineralization occurs in breccia-hosted Carlin-type deposits. The Dee mine was discovered in 1981, operated both open pit and underground from 1984 to 2000 and produced approximately 600,000 ounces of gold. In 1997, Barrick and the Corporation (doing business as Rayrock Mines) entered into an exploration earn-in agreement which Barrick eventually completed providing them with 60% of the property. In July 2005, surface drilling through at the Dee mine discovered the South Arturo mineral deposit. Drilling on the property has continued since such time with some 108 holes totaling 118,000 feet being drilled in 2007. An internal pre-feasibility study was completed in early 2007 which concluded further expenditures were warranted on the project. A feasibility study is scheduled to be completed in mid 2008.
IMPERIAL PROJECT, UNITED STATES (non-material property)
     The Imperial Project is a proposed open pit, heap leach project located in the southeastern corner of California, approximately 40 kilometres northwest of Yuma, Arizona. The property is located on public land (600 hectares) administered by the U.S. Bureau of Land Management. In 2002-2003, the California Legislature and State Mining and Geology Board adopted mandatory complete backfilling requirements for open pit gold mines. This legislation renders the Imperial Project uneconomic, practically infeasible and has prevented the Corporation from developing its mineral rights.
MEXICO
     The Corporation’s properties in Mexico include the Los Filos Mine, the El Sauzal Mine, the San Dimas Mines, the Nukay Mine and the Peñasquito Project. During 2007, construction and commissioning of the Los Filos project was completed and Los Filos achieved commercial production, as defined by Canadian generally accepted accounting principles, as of January 1, 2008.
     Corporate profits in Mexico are taxed only by the Federal Government. Through 2007, there were two federal taxes in Mexico that applied to Goldcorp’s operations in Mexico; an asset tax and a corporate income tax. For fiscal year 2007, corporations pay a federal tax on assets at the rate of 1.25% of the average value of assets. Corporate income tax is credited against this tax. Mexico has a general system for taxing corporate income, ensuring that all of a corporation’s earnings are taxed only once in the fiscal year in which profits are obtained. Mexican corporate income tax is calculated based on gross revenue less deductions for all refining and smelting charges, direct operating costs, all head office general and administrative costs, and depreciation deductions. The 2007 corporate income tax rate in Mexico was 28%.
     However, during 2007 the Government of Mexico adopted a Single Rate Business Tax (“SRBT”) which became effective as of January 1, 2008, and repealed the asset tax as of that date as well. The SRBT is a minimum tax that applies in addition to the corporate income tax. The tax is applicable to the taxpayer’s net income from the (i) sale of goods; (ii) performance of independent services; and (iii) lease of goods at the rate of 16.5% during 2008, 17% during 2009 and 17.5% as of 2010. The base to which the SRBT will be applied will be determined by deducting from gross income certain items, such as expenses associated to purchasing goods, rendering independent

- 31 -


 

services, and leasing goods, or expenses incurred in connection with the administration of such activities. Some expenses that are deductible in determining taxable income for income tax purposes, such as salaries, will not be deductible in determining the SRBT. However, certain tax credits are available to offset the SRBT, including income tax paid during the same fiscal year; a credit on certain salary-related expenses and social security contributions paid by an employer; a credit on losses; and monthly SRBT payments. The SRBT follows a cash flow system, which could distort the crediting of income tax against the SRBT. Finally, special rules apply to certain taxpayers, such as corporate groups like Goldcorp that file consolidated tax returns. In addition, the SRBT law provides special rules to deal with the transition from the asset tax to the SRBT, as well as with the deduction of investments acquired prior to the entering into force of the SRBT law.
LOS FILOS MINE, MEXICO
     The Los Filos Mine consists of two open pit mines (Los Filos and Bermejal) with common process and ancillary facilities, which is wholly-owned by Desarrollos Mineros San Luis, S.A. de C.V., a Mexican company indirectly wholly-owned by the Corporation, and is located in the Nukay mining district of central Guerrero State, Mexico.
     The first gold pour at Los Filos took place in June 2007 and commercial production was achieved on January 1, 2008. All mine equipment, as well as the heap leach pad, carbon plant, gold recovery and refinery areas performed according to expectations. Production at Los Filos will continue to ramp up through the second quarter of 2008.
Property Description and Location
     The Los Filos Mine is located in the Nukay mining district of central Guerrero State in southern Mexico, approximately 230 kilometres south of Mexico City. Both the mine and the adjacent Nukay mining operations lie within the southern part of the Morelos National Mineral Reserve (Morelos Sur) which covers a total of 47,600 hectares and was formally controlled by the Consejo Recursos Minerales, an agency of the government of Mexico. The Los Filos Mine consists of 20 different concessions totalling 4,962 hectares within the municipality of Eduardo Neri, Guerrero, Mexico.
     During the fourth quarter of 2007, engineering design work on modifications to the crushed ore bin as well as the construction of the second stage of the heap leach pad commenced. Both projects are progressing according to schedule and are expected to be completed during 2008.
     Negotiations with local communities following blockage of mine access, as reported in March 2007, resulted in the Corporation agreeing to a comprehensive community development program. Community relations improved significantly as the program began to be implemented.
Accessibility, Climate, Local Resources, Infrastructure and Physiography
     The Los Filos Mine is located in the Sierra Madre del Sur physiographic province of southern Mexico. The property is accessible from Highway 95, a major, paved route between Mexico City and Acapulco. At the village of Mezcala on Highway 95, a former 8.5 kilometre dirt road leading to Los Filos and Bermejal areas was broadened and paved as part of the Los Filos Mine development and is fully operational. Driving time from Mexico City is approximately three hours.
     The Los Filos Mine is located near established power and road infrastructure at Mezcala and near centers of supply for materials and workers at Chilpancingo, Iguala and Cuernavaca.
     Although topographic variations result in different climate types at the project, a very hot, semi-dry climate is the predominate climate at the site. The average annual temperature ranges between 22 degrees Celsius to a low of 18 degrees Celsius. The average annual precipitation is 590 millimetres. The months with the most rainfall are June through August. Very little precipitation (less than 5% of the average annual rainfall) occurs between November and April. However, the project area can be affected by tropical storms and hurricanes which can result in short term high precipitation events.

- 32 -


 

     The area is characterized by large limestone mountains divided by wide valleys. The slopes of the hills vary from very flat to strong slopes. The maximum elevation in the project area, 1,820 metres above mean sea level is the summit of Bermejal hill. The valley of Carrizalillo lies at an altitude of 1,000 to 1,100 metres above mean sea level. A total of 255 plant species were identified in the vicinity of the project area. Three of such plant species are protected; however, these protected species are all located outside of the proposed disturbance areas and will not be impacted by the project.
     The power supply for the Los Filos Mine is supplied through the local utility service, Comisión Federal de Electricidad. Power is supplied from the main feeder at Mezcala at 115 kV to a 25.0 MVA substation located on the Los Filos Mine property. The substation is designed to allow for expansion for future needs by an additional 12.5 MVA. An emergency power plant will be constructed during the first quarter of 2008 to provide back-up power for the leach pumps and the gold recovery plant.
     The Los Filos Mine is a heap leach operation utilizing multiple lift, single use leach pad. Leach grade ore will be processed by crushing, agglomeration and heap leaching once modifications to the crushing and ore handling system are completed (anticipated during 2008). Crushing includes a two-stage, closed circuit system. The crushing circuit will operate seven days per week, twenty hours per day. Until the modifications are successfully completed, low grade ore will be placed directly on the leach pad as run-of-mine (“ROM”).
History
Los Filos
     Much of the early exploration and mining activity in the area was focused on the neighbouring Nukay claim prior to the discovery of the Los Filos Mine in 1995. The Los Filos area was only subject to sporadic prospecting through the twentieth century until Teck Corporation (“Teck”) became interested in the Nukay property in 1993 and completed an agreement (the “Nukay Agreement”) with Minera Miral S.A. de C.V. which was in the process of buying out the owners of Minera Nukay, S.A. de C.V.
     Minera Nuteck S.A. de C.V. (“Minera Nuteck”) was formed by Teck and Miranda Mining Development Corporation and conducted regional exploration and a drilling campaign around the Nukay operations, focusing on the potential for mineralized skarns around the targets. The discovery hole for the Los Filos deposit was drilled in August 1995.
     Work in 1996 focused on the delineation of the Los Filos and Pedregal prospects which were subsequently found to be one continuous deposit. In 1997, delineation drilling at Los Filos continued. Scoping studies and metallurgical testwork were undertaken by Teck in the period between 1998 and 2002.
     In November 2003, Goldcorp gained 100% ownership of Los Filos through the purchase of Miranda Mining Development Corporation (“Miranda”) and agreements with Teck. In 2004, additional delineation, drilling, geotechnical and environmental studies and metallurgical testwork were conducted as an initial part of the feasibility study.
Bermejal
     The Bermejal deposit was overlooked due to low gold grades at surface and the negative results of diamond drilling by Draco and the Consejo de Recursos Minerales. Little attention was paid to this area until 1986 when geologists from Industrias Peñoles S.A. de C.V. (“Peñoles”) sampled jasperoids within an extensive oxidation zone on top of Cerro Bermejal. Anomalous values showed a zone of 1.2 grams of gold per tonne. In 1988, geophysicists recognized strong magnetic and induced polarization anomalies and in 1989, Peñoles started a detailed exploration program for bulk mineable gold deposits. Peñoles completed a prefeasibility study in 1994 with an estimated 1,000,000 ounces of recoverable gold to be mined by a 13,000 TPD open pit and heap leaching operation.
     During 2003, the Corporation (formerly Wheaton River Minerals Ltd.) evaluated the Bermejal deposit and conducted a due diligence review of the project. Subsequently a number of pits and adits were excavated to obtain

- 33 -


 

bulk samples for validation of the local grade estimates and to provide representative material for metallurgical testwork.
     On March 22, 2005, Luismin acquired the Bermejal gold deposit from Minera El Bermejal, S. de R.L. de C.V., a joint venture of Peñoles and Newmont Mining Corporation (“Newmont”). At the time of purchase the mineral resource estimate was 93.6 million tones at a grade of 0.79 grams of gold per tonne in the Indicated Mineral Resource category, as estimated by Peñoles. The Bermejal mineral resource reported in February 2005 used a 0.35 grams of gold per tonne cut-off and a $400 gold price.
     Due diligence metallurgical studies on the Bermejal mineralization for heap leach amenability were initiated and additional diamond core drilling has been conducted to delineate the mineral resources amenable to open pit mining. In 2005, further metallurgical, geotechnical, and engineering studies were undertaken resulting in the integration of Bermejal and Los Filos into one comprehensive mining operation.
Geological Setting
Regional Geology
     The Los Filos and Bermejal deposits are located in the Mezcala district in southern Mexico. This region of southern Mexico is underlain by a cratonic assemblage, approximately 2,000 metres thick of moderately to strongly folded Mesozoic platform carbonate and clastic rocks. The deposits lie near the centre of a large circular-shaped feature known as the Morelos-Guerrero Basin. The basinal sequence is composed of the Morelos, Cuautla and Mezcala Formations. The most important of these formations is the Morelos Formation, which is the thickest and most wide spread of the three. It is Cretaceous in age and predominantly a medium-bedded to massive fossilferous limestone and hosts most of the mineralization in the region including the Los Filos and Bermejal deposits. The Morelos Formation is up to 900 metres thick in places, and is overlain by share and thin-bedded limestone of the Cuautla and Mezcala Formations.
     The sedimentary formations were subsequently intruded by granodioritic plutons and related phases of dioritic stocks and dike intrusive bodies. The associated hydrothermal activities lead to the local development of alteration halos in the sediments surrounding the intrusives, including the formation of hornfels in argillaceous formations and, more importantly, marble within calcareous formations.
     The Cretaceous sediments and granitoid intrusions are unconformably overlain by a sequence of intermediate volcanic rocks and alluvial sediments (red sandstones and conglomerates) which partially cover the region.
     Regional structures in the Morelos-Guerrero Basin include sets of northeast-and-northwest-striking faults and fractures which cut both the carbonate sequence and the intrusives. The distribution of intrusive bodies in northwest-trending belts is thought to reflect the control on their emplacement by northwest trending faults.
Los Filos Deposit Geology
     In the Los Filos area, mineralization is associated with a diorite sill and granodiorite bodies that were emplaced in carbonate rocks of the upper Cretaceous Morelos Formation. The stocks comprise the area described as East Stock and are early Tertiary in age. Mineralization resulted from high temperature calc-silicate and oxide metasomatic alteration (skarn) assemblages that were followed by distinct meso-to epithermal alteration in the intrusives and the carbonates. Hemadite and magnetite are typical skarn minerals, but diopside which is more usually recognized in skarn assemblages, is not present. The Los Filos deposit formed along the north, east and southern margins of the East stock that geologic evidence and argon dating have indicated is slightly older than the West stock.
     The differing morphology of the East and West Nukay stocks is believed to reflect different structural controls during emplacement. The exposure of the West stock is roughly circular and about 1.3 kilometres in diameter. The East stock is elongated in a north-south direction and is about 1.4 kilometres long and 0.5 kilometres

- 34 -


 

to 0.7 kilometres wide in the south but in the north, a western lobe extends for 1 kilometre in a west-southwest to east-northeast direction.
     The deposit is hosted primarily by the diorite sill that dips between 20º and 50º to the east away from the East stock. The diorite was emplaced into a large, moderately-dipping, active structure that parallels bedding in the marble country rocks. The sill has a sigmoidal shape that starts out roughly flat at the stock, extends east at a moderate dip for about 200 metres, then thins and flattens out again at depth. Contained within the sill are thin, discontinuous slabs of marble that dip with the sill, interpreted to be structurally-bounded slivers of wall rock that were caught up in the diorite during emplacement. In the south-central portion of the deposit there is semi-circular gap in the sill, with holes drilled in the gap showing only marble to depths of 250 metres or more.
     On the western edge of the sill, the diorite grades into granodiorite of the main intrusive. The juncture where the sill meets the stock occurs at the point where the sill daylights and erosion has exposed the upper portions of the sill along with some of the contained marble xenoliths.
     Beneath the diorite sill, moderately east-dipping stubby bodies and fingers of granodiorite project into the carbonate wall rocks away from the East stock, forming a lower sill that generally parallels the dip of the upper diorite sill. A thin sliver of marble lies between the diorite sill and the lower granodiorite sill over much of the deposit. The lower-sill intrusive bodies extend, at most, halfway across the drilled cross-sections. These intrusive projections become less pronounced with depth, and the stock becomes essentially vertical a few hundred metres below the sill.
     In the north-central portion of the deposit, several of the eastern-most holes encountered thickness of several hundred metres or more of granodiorite beneath the diorite sill and above it.
Bermejal Deposit Geology
     Geology at the Bermejal deposit consists of calcareous and argillaceous rocks of Cretacerous age which are intruded by granodiorite stocks of Tertiary age, forming metasomatic halos at their contacts. Tertiary volcanics partly cover the area. Iron-gold mineralization is best developed at the granodiorite-limestone contacts and also within endoskarn. Endoskarn shows incipient garnetization and marmorization that decreases outward. Major pulses of gold and quartz mineralization occurred later, accompanied by strong retrograde alteration. The retrograde alteration stage destroyed the prograde calc-silicate mineral phases, resulting in chlorite, epidote and other hydrosilicate minerals. Second enrichment of gold and to a lesser extent copper, within the oxidation zone is common.
     The major mineralized bodies at Bermejal consist of iron-gold skarn with minor amounts of copper and silver at the intrusive-limestone contact. Mineralized bodies also occur with endoskarn and are disseminated within the hydrothermally altered intrusive rocks. Surface drilling defined four mineralized bodies around the Bermejal stocks: the Anomalia, BD-3, Tajo-Mez and Contacto Norte zones. With the exception of the Anomalia zone that dips to 30º to 40º SE, the other zones have almost vertical dips. Quartz-FeOx, high grade gold veins, stockwork and disseminated mineralization are locally important. The quartz-FeOx and high-grade gold veins are hosted by both limestones and intrusive rocks. Stockworks and disseminated mineralization are restricted to the intrusion. Examples of high grade veins can be found at the San Miguel and Guadalupe areas. At Bermejal, all zones are mostly oxide ores. At depths of more than 250 metres, oxidation is pervasive and continuous while minor sulphides occur locally. Sulphides are also found toward the core of Cerro El Bermejal. Although most gold is associated with massive iron oxide bodies at the intrusive-limestone contact, there is also gold within structures, quartz veins and the pyroxene skarn zone.
     At Bermejal, mineralization is distributed around the granodiorite stock, both at the limestone contact and within the intrusion. The extent of the limestone replacement is minor compared to that of endoskarn. Thickness of the zones varies from 10 to 150 metres with an average of 80 metres. Mineralization extends continuously all around the apophysis of the intrusion which is approximately 600 metres in diameter. The shape of the deposit mimics a shell around the domic shape of the intrusive. Important structural controls that strike north-south and east-west accounts for bends and widening of zones at the Tajo-Mez and Contacto Norte areas.

- 35 -


 

Exploration
     There is no documentation available to describe the exploration programs on the Bermejal gold deposit prior to 2005 which meets the requirement of NI 43-101. The information available for the Los Filos site provided below predates NI 43-101 and does not necessarily conform to the language set out therein.
     Subsequent to Wheaton River purchase of Miranda and of Luismin in November 2003, exploration continued at Los Filos with the drilling of 81 diamond core drill holes and at Bermejal with the drilling of 36 diamond core holes.
     Fully documented exploration on the Los Filos gold deposits dates back to the early 1990s. The discovery hole for the Los Filos deposit was drilled in 1995. The 1995 program undertaken by Minera Nuteck consisted of district-wide geologic mapping, grid lithogeochemical sampling, a time-domain electromagnetic survey, road-cut mapping and sampling and drilling of 19,128 metres in 90 holes. The program included part of the area that was eventually delineated as the Los Filos deposit.
     During 1996, work focused on the exploration and delineation of the Los Filos and Pedregal prospects that were found to be two portions of one continuous deposit. A total of 156 reverse circulation (“RC”) rotary and 44 core holes were completed at approximate spacing of 35 metres on a grid 1,200 metres long and 350 metres wide. Extensive mapping, sampling, density measurements, and metallurgical testing were also completed on the Los Filos deposit.
     In 1997, delineation drilling continued on the Los Filos deposit, for a total of 29,219 metres in 133 RC rotary holes. This drilling extended the area of known mineralization to the northwest and southwest. The 35 metre drilling grid covered an area of 1,400 metres by 400 metres. In 1997, metallurgical bottle-roll tests and column tests on low-and medium-grade core samples were carried out. Klohn-Crippen was retained to complete a preliminary geotechnical assessment of the project.
     The exploration phase of work on the Los Filos deposit was essentially completed in March 1998.
     In 1997, a scoping level study was completed on Los Filos by Teck, based on data available at the end of 1996. In 1998, Teck completed a prefeasibility level assessment using all of the drilling data for Los Filos available at the end of 1997. During the last quarter of 1998, Minera Nuteck initiated discussions with Peñoles/Newmont regarding the potential for a common processing arrangement for Los Filos and the Bermejal deposit.
     During 1999, Minera Nuteck continued metallurgical testwork, environmental studies, and a sediment control study and completed aerial photography over the Los Filos site in order to facilitate planning for site access and the potential location of a heap leach pad. In 2000, further work in preparation for a feasibility study on Los Filos was undertaken, including geological modeling, a 37-hole, 7,105 metre confirmatory drilling program, a study on the structural geology, further metallurgical testwork, environmental permitting studies, and a review of capital cost estimates.
     During 2007, a regional and local geophysical survey was performed to provide information that may be useful in identifying new drilling targets. The survey identified various magnetic anomalies related to iron-skarn bodies along the Guerrero Gold Belt. A 100 x 25 metre grid was used for local survey and geologic mapping.
Mineralization
     Approximately 75% of gold mineralization at Los Filos-Bermejal is hosted within the diorite sill and around the granodiorite stock. Mineralization is structurally controlled by breccias and quartz-hematite-gold (+calcite) veins.
Drilling
     An aggregate of 532 holes and 119,250 metres were drilled on the Los Filos site as of August 2005. At Los Filos, the majority of drilling, 86,350 metres, has been RC with the remaining 32,900 metres drilled as core over an

- 36 -


 

area measuring approximately 1.3 kilometres north-south by 400 metres east-west. Los Filos drilling sections were completed on approximately 35 metre spacing.
     An aggregate of 566 holes and 105,837 metres were drilled on the Bermejal site as of September 2005. As at Los Filos, the majority of drilling at Bermejal, 80,554 metres, has been RC with the remaining 25,283 metres drilled as core. As at Los Filos, Bermejal drill holes were completed on approximately 35 metre spacing.
     With regard to the pre-2003 drilling, the available documentation shows that Minera Nuteck used industry accepted drilling techniques to evaluate the Los Filos deposits. The Bermejal drill hole database and documentation acquired from Minera El Bermejal is being updated and it is understood that the required fields for drill, type, hole size, recovery and contractor for pre-2005 drilling will be included. Industry standard drilling techniques have been used at Los Filos and Bermejal for post-2003 drilling.
     Since mining operations at Los Filos and Bermejal began in 2005, exploration drilling has focused on targets outside the Los Filos and Bermejal deposits. During 2007, 40 diamond holes were drilled at the 4P project for a total of 7,918 metres. The 4P deposit is located along the ridge in the west part of the Los Filos intrusive. The target consists of four areas: Creston Rojo, Zona 70, Conchita and El Grande.
Sampling and Analysis
     Core logging and sampling procedures are in accordance with standard industry practice.
     Since 2003, diamond drilling and sampling protocols have been conducted as follows: geologists selected target areas of potential mineralization based on geological sections and interpretations. Identification codes were assigned to the drill holes. Drilling normally commenced with HQ hole size and was reduced to NQ and sometimes BQ in areas of bad ground. Initially the core for metallurgical testing was drilled with a UDR 650 rig with PQ rods to recover a large volume of core. Down hole surveys were taken every 50 metres with a Reflex EZ-Shot instrument which also reported magnetism and temperature. Initially, the core was transported 13 kilometres to a core shack in Mezcala, however, since construction of the core shack on site was completed in mid-2006, all core has been processed on site. All core boxes are numbered consecutively and marked with hole identification and drilling interval contained in the box. Core is photographed and video recorded from collar to toe, these digital files are stored on hard disc.
     Geological logging is completed in the following manner: core is measured and recoveries calculated; RQD measurements are taken by measuring the sections of core greater than 10 centimetres that were not fractured over lengths of 5 metres; and rock hardness measurements are recorded on a scale of 0-5 with O being very soft and 5 being very hard. All discontinuities are classified by type and thickness and discontinuity orientations were recorded as 0º-30º, 30º-60º 60º-90º.
Security of Samples
     Geological logging is completed in the following manner: the drilling commencement and completion dates, core diameter, overall length and collar coordinates are recorded. The geological log records lithology, percent of phenocrysts, feldspars, plagioclase, biotite, quartz, pyroxenes, garnets, calcite, hematite, limotite and clays. Sample intervals are recorded and numbered. Core samples are cut with 220 volt Rockman saws or split with Hydrasplit manual hydraulic splitters, taking lithological contacts into account, as determined by the geologist. PQ core are cut into sections: 75% for metallurgical testing, 12.5% for assaying and 12.5% were stored in the core box in the core shack, NQ core is also cut into three section but only 50% for metallurgical testing, 25% for assaying and 25% was stored. Cut samples are bagged and numbered in polyethylene bags. When approximately 400 samples have been accumulated they are transported to Chemex’s Guadalajara laboratory, which is located approximately 800 kilometres from Los Filos. At the laboratory, Chemex employees sign off for the specific samples bags received and assume responsibility of the sample. Samples undergo thirty-four element analyses and results are generally received within fifteen days. Assay results are compiled by company geologists.

- 37 -


 

Mineral Reserve and Mineral Resource Estimates
     The following table sets forth the estimated Mineral Reserves for the Los Filos Mine as of December 31, 2007:
Proven and Probable Mineral Reserves (1)(2)(3)(4)(5)
                                         
            Grade   Contained Metal
Category   Tonnes   Gold   Silver   Gold   Silver
    (millions)   (grams per tonne)   (grams per tonne)   (millions of   (millions of
                            ounces)   ounces)
Proven
    33.71       0.83       3.4       0.90       3.7  
Probable
    243.77       0.61       6.2       4.75       48.8  
 
                                       
Proven + Probable
    277.47       0.63       5.9       5.64       52.5  
 
                                       
 
(1)   The Mineral Reserves for the Los Filos Mine set out in the table above have been estimated by Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, who is a qualified person under NI 43-101.
 
(2)   Cut-off grade for the Los Filos deposit was 0.22 grams of gold per tonne wholly contained within a pit optimization shell defined by using $550 per ounce of gold.
 
(3)   Cut-off grade for the Bermejal deposit was 0.20 grams of gold per tonne wholly contained within a pit optimization shell defined by using $550 per ounce of gold.
 
(4)   The estimated metallurgical recovery rate is 55% to 72% for gold and 5% for silver.
 
(5)   Numbers may not add up due to rounding
     The following table sets forth the estimated Mineral Resources for the Los Filos Mine as of December 31, 2007:
Measured, Indicated and Inferred Mineral Resources (1)(2)(3)(4)(5)(6)
                                         
            Grade   Contained Metal
Category   Tonnes   Gold   Silver   Gold   Silver
    (millions)   (grams per tonne)   (grams per tonne)   (millions of   (millions of
                            ounces)   ounces)
Measured
    6.26       0.69       3.4       0.14       0.7  
Indicated
    78.11       0.53       5.3       1.33       13.3  
 
                                       
Measured + Indicated
    84.37       0.54       5.1       1.47       14.0  
 
                                       
Inferred
    73.49       0.56       5.5       1.33       13.0  
 
(1)   The Mineral Resources for the Los Filos Mine set out in the table above have been estimated by Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, who is a qualified person under NI 43-101.
 
(2)   Cut-off grade for the Los Filos deposit was 0.22 grams of gold per tonne wholly contained within a pit optimization shell defined by using $650 per ounce of gold.
 
(3)   Cut-off grade for the Bermejal deposit was 0.20 grams of gold per tonne wholly contained within a pit optimization shell defined by using $650 per ounce of gold.
 
(4)   Cut-off grade for the 4P deposit was 0.22 grams of gold per tonne.
 
(5)   Mineral Resources are not known with the same degree of certainty as Mineral Reserves and do not have demonstrated economic viability.
 
(6)   Numbers may not add up due to rounding.
Mining Operations
     During 2007, a total of 5.1 million tonnes of ore with an average grade of 0.773 grams of gold per tonne and 18 million tonnes of waste were mined from the Los Filos pit. The Bermejal pit produced 3.3 million tonnes of ore with an average grade of 0.423 grams of gold per tonne and 8.9 million tonnes of waste. The combined mine production from the Los Filos site was 8.4 million tonnes of ore with an average grade of 0.636 grams of gold per tonne for a total of 171,356 contained ounces of gold mined.
     An average of 1,000 ounces of gold per day was placed on the leach pad during the fourth quarter of 2007.

- 38 -


 

     Production is scheduled in two ten-hour shifts per day; seven days per week. Mining equipment includes three front-end loaders, five hydraulic shovels, 13 90-tonne haul trucks, 14 140-tonne haul trucks and other auxiliary equipment. Drilling is performed with seven rotary drills. Maintenance of mine equipment is covered by two MARC contracts.
     Since November 2007, bagged ANFO was replaced by mixing ammonium nitrate and fuel oil on site and placing it directly into drill holes which improved safety and reduced blasting costs. Preparations are in progress to use recycled oil for the ANFO mix in order to further reduce costs.
     Tri-cone bits are being tested and preliminary results indicate better performance compared to hammer bits. A final evaluation will require additional testing.
Mineral Processing and Metallurgical Testing
     Ore placement on the heap leach pad began on January 1, 2007. On May 25, 2007, ore leaching was initiated and the first gold pour occurred on June 15, 2007. As of December 31, 2007, 8.8 million tonnes of ore (including 0.4 million tonnes from stockpiles) with an average grade of 0.629 grams of gold per tonne were placed on the leach pad.
     Flow rate to the ADR plant carbon columns began at a daily rate of 9,000 cubic metres in June 2007 and ended the year at a rate of 43,000 cubic metres per day. As of December 31, 2007, an average of 430 ounces was adsorbed per day in the carbon columns.
     The second stage of the heap leach pad is currently under construction and is expected to be completed by the end of May 2008. This stage provides the required capacity to support the 2008 ore placement.
     A total of 43,853 ounces of gold were produced at Los Filos in 2007 which represents an average recovery of 25% of the total ounces placed on the leach pad. The average recovery rate is expected to reach 45% of the total gold ounces placed on the leach pad by the end of 2008.
Environmental Considerations and Permitting
     Environmental permits are required from various Mexican Federal, State and Municipal agencies. The most important and complex environmental permit required for the project is the environmental license of Licencia Ambiental Unica (“LAU”). The authorization of the LAU is based on the approval of an environmental impact assessment, an environmental risk study and land use change authorization. All of these environmental permits have been obtained.
     Other important permits include the Concession Title for Groundwater Extraction and a Wastewater Discharge Permit. The extraction of water from mines is regulated by Mexican law and no permit is required to extract mine water. However, the use of mine water requires an agreement with the National Water Commission (“CNA”) and payment of the corresponding water right. The use of surface water or groundwater from a source other than a mine is regulated under Mexican law and a water concession must be obtained from the CNA. Application to the CNA for water usage rights has been filed and approvals received during 2006. The discharge of wastewater to national water bodies is regulated by CNA. A permit is required for most industrial discharges. A detailed water balance prepared for the project indicates that the ponds have the capacity to contain all process solutions, and no discharges from the process facilities will be required. Four sewage discharge permits for employee housing and office facilities were solicited and are pending authorization.
     The following additional permits were granted to the Los Filos Mine: an explosive usage permit was granted by Mexican Military authorities early in 2005, approval of the 115 kilovolt transmission line and Los Filos main substation, and a franchise for diesel auto-consumption station granted by Pemex.
     The environmental management system and environmental and social management plans are being developed and implemented to meet Mexican and international environmental guidelines. During 2007, compliance

- 39 -


 

reports on Land Usage and Environmental Impact Assessment were prepared and delivered to the Federal Environmental Agency (SEMARNAT) as required.
     Lease agreements for all land required for the Los Filos-Bermejal projects were obtained from the nearby communities in 2004 and 2005. Public consultation and community assistance and development programs have been developed and will be ongoing throughout the project. A needs assessment was performed for the Carrizalillo, Mezcala and Mazapa communities in order to define and implement sustainable development strategies in the surrounding area. Implementation of such strategies started during the last quarter of 2007.
EL SAUZAL MINE, MEXICO (non-material property)
     The Corporation acquired its 100% interest in the El Sauzal Mine in connection with the Glamis Acquisition. El Sauzal is located 447 kilometres from Chihuahua, Mexico. Exploration activities began at El Sauzal in 1995. Construction of the mine began in 2003 and production commenced in December 2004. The El Sauzal property covers approximately 10,250 hectares of land. Road access to the site is via the cities and towns of Chihuahua, Creel, San Rafael, Bahuichivo, Cerocahui, and Mesa de Arturo. The total road distance from Chihuahua to the site is approximately 447 kilometres. The climate in the El Sauzal area is classified as temperate sub-humid, with distinct wet and dry seasons. The rainy season is short, generally from June to August. Annual rainfall averages 800 millimetres and annual average evaporation is 2,400 millimetres. Average monthly evaporation exceeds average monthly precipitation in every month of the year.
     Due to the remote location and steep, rugged terrain surrounding the El Sauzal site, extensive site development was required prior to the commencement of operations. An on-site camp provides housing and services for the 250 employees who rotate in and out on varying shifts. The El Sauzal Mine is a conventional open pit operation moving nearly 7.0 million tonnes per year of material. Ore is mined at an annual rate of 2.0 million tonnes. Ore is fed through a primary jaw crusher prior to being introduced into a semi-autogeneous grinding mill/ball mill circuit. Gold recovery is a modified CIL(P) circuit. Gold production in 2007 was 306,900 ounces at a total cash cost of $120 per ounce. Gold production of approximately 530,000 ounces are expected for the remaining mine life through to 2010.
SAN DIMAS MINES, MEXICO (non-material property)
     The San Dimas Mines are located on the border of Durango and Sinaloa States approximately 125 kilometres northeast from Mazatlan, Sinaloa or approximately 150 kilometres west of the city of Durango. These properties are surveyed and contained in a contiguous block that covers an area of 22,468 hectares. Since late 2003, the three mining units, Tayoltita, Santa Rita and the Central Block (which includes the San Antonio mine) (hereinafter referred to as “San Antonio/Central Block”), were placed under common management. All mine production is now processed through the Tayoltita mill. These operations are now referred to as the San Dimas Mines and are owned by Desarrollos Mineros San Luis, S.A. de C.V., a Mexican company indirectly wholly-owned by Goldcorp.
     The Tayoltita mine is the oldest operating mine in the San Dimas area. The main access is a 4.4 kilometre tunnel from a portal approximately 400 metres northeast of the Tayoltita mill. The Santa Rita mine main access is by adit approximately three kilometres to the northeast of the Tayoltita mill site. The mining method employs cut-and-fill mining on vein mineralization. The San Antonio/Central Block mine is located northwest of Tayoltita and is accessible by 20 kilometres of winding dirt road over the mountains. In 2001, the San Luis tunnel was completed which provides for easier access between San Antonio/Central Block and Tayoltita as well as integration of support services of the two locations. The San Antonio/Central Block site includes a mill and some limited accommodation for the workforce. The mill operation was shutdown in November 2003 and all milling consolidated at the expanded Tayoltita mill facility.
     The San Dimas district now has one milling facility at Tayoltita to process the production from the three active mining areas in San Dimas. The Tayoltita mill has a conventional process flowsheet that employs cyanidation and zinc precipitation for recovery of the gold and silver. The mill currently has an installed leaching capacity of 2,100 tonnes per day. A project to increase the crushing and grinding capacity of the Tayoltita mill to 3,200 tonnes per day is currently underway and is expected to be completed at the end of 2009. In 2007, the mill

- 40 -


 

averaged 1,986 tonnes per day. Gold production during 2007 was 132,900 ounces of gold at a total cash cost of $336 per ounce (co-product) and $238 per ounce (by-product).
NUKAY MINE, MEXICO (non-material property)
     On November 3, 2003, the Nukay Mine was acquired through the acquisition of Miranda Mining Corporation (“Miranda”), along with the Los Filos Mine (then the Los Filos project) and the 21.2% interest in the El Limón joint venture with Teck Cominco Ltd. The Nukay operations include the Nukay mill, the Nukay and La Aguita open pit mines and an underground mine that produces ore from two zones (La Subida and San Andres). The mining operations are located in the Nukay Mining District of central Guerrero State, immediately northwest of the Los Filos Mine. The properties cover an area of 597 hectares and are held by Desarrollos Mineros San Luis S.A. de C.V., an indirect wholly-owned subsidiary of the Corporation. Currently, all of Nukay’s production comes from underground operations. Gold production during 2007 was 28,100 ounces of gold at a total cash cost of $317 per ounce. Gold production of approximately 281,000 ounces is expected for the remaining mine life through to 2017.
PEÑASQUITO PROJECT, MEXICO
     Robert H. Bryson, MMSA, Fred H. Brown, CPG, Reynaldo Rivera, MAusIMM and Steven Ristorcelli, P.Geo. prepared a report dated August 9, 2007 entitled “Peñasquito Project Technical Report Concepción del Oro District, Zacatecas State, México” (the “Peñasquito Report”) for Goldcorp. Messrs. Bryson, Brown, Rivera and Ristorcelli are each qualified persons within the meaning of NI 43-101.
     The following description of the Peñasquito Project has been summarized from the Peñasquito Report and readers should consult the Peñasquito Report to obtain further particulars regarding the Peñasquito Project. The Peñasquito Report is available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile.
Property Description and, Location
     Goldcorp owns, through its wholly-owned Mexican subsidiary, Minera Peñasquito, S.A. de C.V. (“Minera Peñasquito”), 100% of the mineral rights to a large area covering approximately 39,000 hectares located in the north-eastern portion of the State of Zacatecas in north-central Mexico (the “Peñasquito Property”). The closest major town is Concepción del Oro which lies approximately 27 kilometres east of the Peñasquito Property on Mexican highway 54, a well maintained, paved highway which links the major cities of Zacatecas (in the state of Zacatecas), approximately 250 kilometres to the southwest with Saltillo (in the state of Coahuila) approximately 125 kilometres to the northeast.
     Investigations on the Peñasquito Property have identified several major sulphide mineralization zones with significant values of silver, gold, zinc and lead. The Peñasquito Report considers the economic development of three zones, the Peñasco (the “Peñasco Zone”), the Azul (the “Azul Zone”) and the Chile Colorado (the “Chile Colorado Zone”), which have been the subject of most of the geological and metallurgical investigations to date (collectively the “Peñasquito Project”). In addition to the sulphide mineralization, the three zones also have substantial oxide ore caps which contain recoverable gold and silver. The gold and silver recovered from the oxide ores have been included in the Peñasquito Project economic evaluation.

- 41 -


 

     The following table lists the mineral claims associated with the development of the Peñasquito Project. This table is not a complete list of Minera Peñasquito’s mineral claims in the area.
List of Pertinent Claims — Peñasquito Project
                                                 
Claim   Type   Title   File No.   Area (Hectares)   Date Issued   Expiry Date
EL PEÑASQUITO
  Exploitation     196289       43/885       2.000       1993-07-16       2011-07-11  
LA PEÑA
  Exploitation     203264       07/1.3/547       58.000       1996-06-28       2046-06-27  
LAS PEÑAS
  Exploitation     212290       8/1.3/00983       40.000       2000-09-29       2050-09-28  
ALFA
  Exploitation     201997       7/1.3/485       1100.000       1995-10-11       2045-10-10  
BETA
  Exploitation     211970       8/1.3/01137       2054.761       2000-08-18       2050-08-17  
SEGUNDA RED. CONCHA
  Exploration     218920       8/2/00018       23304.691       2006-11-22       2050-11-06  
MAZAPIL 3 F. I
  Exploration     217001       007/13852       1950.702       2002-06-14       2008-06-13  
MAZAPIL 10
  Exploration     223327       93/26975       1073.555       2004-10-02       2010-10-01  
     A 2% net smelter return royalty is owed to Royal Gold, Inc. (as a result of its acquisition of Kennecott Canada Explorations Inc. (“Kennecott”) in 2006) on production from both the Peñasco Zone and the Chile Colorado Zone.
     There is no previous mine development of any form in the immediate area of the Peñasco Zone or the Chile Colorado Zone and as such no environmental liabilities are attached to the Peñasquito Project. All drilling pads are cleaned and rehabilitated on an ongoing basis.
Accessibility, Climate, Local Resources, Infrastructure and Physiography
Accessibility and Infrastructure
     An adequate network of road and rail services exists in the region to support the Peñasquito Project. Road access to the Peñasquito Project is presently gained west out of Concepción del Oro approximately 15 kilometres to the town of Mazapil and then a further 12 kilometres west from Mazapil. The road is very steep immediately west of Concepción del Oro with numerous tight switchbacks. It is either paved or cobbled and maintained to approximately 6 kilometres west of Mazapil, and after that, the road becomes a well-maintained gravel road. The Chile Colorado Zone is within two kilometres of this main road and the Peñasco Zone lies directly beneath the road. A system of gravel roads to the east connects to Cedros and eventually to Torreon and the Torreon/Fresnillo highway.
     Goldcorp has completed construction of 2 kilometres of a new road east from Mazapil to join Highway 54 approximately 25 kilometres south of Concepción del Oro. This road will provide superior grade and alignment to the old road from Concepción del Oro. Use of this new road has eliminated the rather steep switchback sections of the current cobblestone road just west of Concepción del Oro and reduces the impact to the town of Concepción del Oro itself. There is one railhead approximately 100 kilometres to the west.
     Negotiations for a high voltage power line right-of-way are complete and the towers to the property have been installed.
     Given the mining experience in the area and the high unemployment rate, there is expected to be an adequate pool of mining personnel available.
     There is adequate space for development of the process facilities and the tailings and waste areas. The tailings disposal will be constructed as a four-sided containment area using alluvial material for a starter dam and tailings for raising the embankment. In general, this is a very favourable site for development.
Water
     The National Water Law and its regulations control all water use in Mexico. Comisión Nacional del Agua (“CNA”) is the responsible agency. Applications are submitted to this agency indicating the annual water needs for

- 42 -


 

the mine operation and the source of water to be used. The CNA grants water concessions according to the availability in the source area.
     The Peñasquito Project will apply for permits to pump up to 40 million m3 per year. The required hydro-geological studies are currently being conducted that will prove to authorities that the aquifers in the region have enough available water to provide this amount.
     The first two phases of hydro-geological studies have been completed (ending in December 2006). A third phase is in progress for Cedros Basin which is anticipated will be completed during the second quarter of 2008. Based on the completed studies, a 4.6 million m3 per year concession was obtained on August 26, 2006. Using existing studies, another application for an additional water concession of 9.1 million m3 per year has been submitted. An application for the remaining water requirements will be submitted following completion of the third phase of the hydro-geological study.
Surface Rights
     Surface rights in the vicinity of the Peñasco Zone and the Chile Colorado Zone are held by private individuals and three Ejidos. Signatures indicating agreement to the granting of access to Minera Peñasquito have been obtained from all three of the Ejidos and nearly all the private owners. Goldcorp is currently in negotiations to finalize surface rights to the land required for the project.
     An Ejido is a communal ownership of land recognized by the federal laws in Mexico. While mineral rights are administered by the federal government through federally issued mining concessions, an Ejido controls surface rights over communal property through a board of directors which is headed by a president. An Ejido may also allow individual members of the Ejido to obtain title to specific parcels of land and thus the right to rent or sell the land. Relations with the Ejidos remain positive.
Climate
     The climate in the area of the Peñasquito Project is generally dry with precipitation being limited for the most part to a rainy season of June and July. Annual precipitation for the area is approximately 700 millimetres, most of which falls in the rainy season. Temperatures range between 20 degrees Celsius and 30 degrees Celsius in the summer and 0 degrees Celsius and 15 degrees Celsius in the winter.
Physiography
     The Peñasquito Project area lies within a wide valley bounded to the north by the Sierra El Mascaron and the south by the Sierra Las Bocas. Except for one small outcrop, the area is covered by up to 30 metres of alluvium. The terrain is generally flat, rolling hills. Vegetation is mostly scrub, with cactus and coarse grasses. The prevailing elevation of the Peñasquito Property is approximately 1,900 metres above sea level.
History
     The region in which the Peñasquito Property is located has a strong tradition of mining going back to the mid 1500s when silver mining first started in the region and the city of Zacatecas was founded. Up until the 19th century, 20% of all silver mined in the world was reportedly mined from the region surrounding the city of Zacatecas. Mining remains active in the State of Zacatecas.
     Some limited exploration of the Peñasquito Project area was carried out during the 1950s, however, it was not until 1994 when Kennecott initiated a comprehensive exploration program in the project area that the size and potential of the mineralized system were recognized.
     Western Copper Holdings Ltd. (“Western Copper”) acquired 100% of the Peñasquito Project from Kennecott in March 1998. On August 24, 2000, Western Copper optioned the Peñasquito Property to Mauricio Hochschild & Cia Ltda. (“Hochschild”), a Peruvian company. During the fourth quarter of 2000, Hochschild completed a 14 hole, 4,601 metre drill program, with 11 holes drilled in the Chile Colorado Zone. However,

- 43 -


 

Hochschild returned the property to Western Copper after spending more than $1 million on drilling and land payments.
     In 2002, Western Copper resumed active drilling of the Peñasquito Property. Western Copper changed its name to Western Silver Corporation (“Western Silver”) in 2003 and continued drilling into April 2006. Western Copper and Western Silver drilled a total of 443 holes (220,880 metres) in the period from 1998 to 2006. Glamis acquired Western Silver on May 3, 2006. Glamis continued drilling from May 2006 through its merger with Goldcorp in November 2006. Goldcorp continued aggressive drilling of the Peñasquito Property through the end of 2007. From May 2006 to December 2007, Glamis and Goldcorp drilled a total of 324 diamond core holes (213,988 metres).
Geological Setting
     The regional geology is dominated by Mesozoic sedimentary rocks intruded by Tertiary stocks of intermediate composition (granodiorite and quartz monzonite). The sedimentary rocks formed in the Mexico Geosyncline, a 2.5-kilometre thick series of marine sediments deposited during the Jurassic and Cretaceous Periods consisting of a 2,000-metre thick sequence of carbonaceous and calcareous turbidic siltstones and interbedded sandstones underlain by a 1,200 to 2,000-metre thick limestone sequence.
     The Mesozoic sedimentary units of the Mazapil area were folded into east-west arcuate folds, cut by northeast- and north-striking faults, and intruded by Tertiary granodiorite, quartz monzonite, and quartz-feldspar porphyry. Tertiary stocks are exposed in the ranges, but not in the valley at Peñasquito. Two diatremes breccia pipes, believed to be related to quartz-feldspar porphyry stocks beneath the Peñasquito area, explosively penetrated Caracol sedimentary units, and probably breached the surface and erupted. These two diatremes, Peñasco and Brecha Azul, are the principal hosts for gold-silver-zinc-lead mineralization at Peñasquito. There is a single outcrop of altered breccia near the center of the Peñasco pipe. Weak sulphide mineralization outcrops on the west side of the outcrop, representing the uppermost expression of much larger mineralized zones below.
     Both breccia pipes are believed to have erupted and breached the surface. Their eruption craters and ejecta aprons have since been eroded away, and the current bedrock surface at the Peñasquito Property is estimated to be on the order of 50 to 100 metres below the original paleo surface. Both of the breccia pipes sit within a hydrothermal alteration shell consisting of a central sericite-pyrite-quartz (phyllic) alteration assemblage, surrounding sericite-pyrite-quartz-calcite assemblage, and peripheral chlorite-epidote-pyrite (propylitic) alteration halo.
Mineralization
     Sulphide mineralization in the Chile Colorado Zone and the Peñasco Zone is hosted by breccias within the diatreme pipes (Brecha Azul and Peñasco) and by surrounding siltstone and sandstone (Cretaceous Caracol Formation) outside of the pipes.
     The Peñasco Zone is comprised of disseminated sulfides in crudely stratified breccias within the diatreme, cut by closely related quartz-felspar porphyry and felsite dikes, and by sulphide disseminations in siltstone and sandstone horizons of the surrounding sedimentary units (Caracol Formation). Breccia units consist of sediment-clast breccias high in the sequence, mixed-clast breccias (sediment and intrusion clasts) at intermediate-depths, and underlying intrusion-clast breccias. All breccias have a matrix of milled, fine-grained intrusion clasts. All of these units may be mineralized, including the cross-cutting dikes. The Chile Colorado Zone is very similar to the Peñasco Zone, with sphalerite-galena-gold-silver hosted by breccias within the Brecha Azul diatreme pipe and by Caracol siltstone and sandstone surrounding the pipe. The Peñasco diatreme is about 900 meters east-west by 800 meters north-south immediately below the alluvial cover; the Brecha Azul diatreme is about 500 meters in diameter at its uppermost extent. Crackle breccias along the inner margins of the diatremes host some of the highest grade mineralization. Sulfide mineralization consists of disseminations and less common veinlets of medium to coarse-grained sphalerite-galena-argentite, various silver sulfosalts, including minor tetrahedrite-polybasite, and common gangue of calcite-rhodochrosite-quartz-fluorite.

- 44 -


 

     At Chile Colorado, the highest grade mineralization outside of the diatremes pipes occurs as stockwork veins and disseminations hosted by weakly silicified sandstone, siltstone or shale of the Caracol Formation. This mineralization is localized by north-south trending fracture zones. At Peñasco, the most prominent mineralization outside of the diatreme is at SW Peñasco where it occurs as disseminations and veinlet stockworks in weakly silicified Caracol siltstone and sandtone, and as garnet-sulfide skarns and shalerite-galena mantos in the limestone units of the underlying Indidura and Cuesta del Cura formations (Cretaceous).
     Sphalerite and galena associated with carbonate and pyrite occur locally as massive veins. Pyrite, sphalerite and galena often occur as discrete crystals and disseminations within sandstone and siltstone units surrounding the diatremes. Late-stage carbonates and pyrite fracture fillings occur throughout the Caracol sedimentary sequence distal to the primary mineralized zones at Peñasquito.
Exploration
     Kennecott completed numerous air and ground based geophysical surveys on the Peñasquito concessions between 1994 and 1997. The aeromagnetic survey of the region defined an 8 kilometres by 4 kilometres, north-south trending magnetic high centered roughly on the Peñasco Breccia. These surveys provided an understanding of the relationship of Peñasquito mineralization to underlying intrusions (magnetometer surveys), located sulphide stockworks (IP surveys), and discovered the Brecha Azul diatremes (gravity survey). The successful identification and location of sulphide stockworks led directly to the initial “ore-grade” discovery at Chile Colorado.
     In 2004, Western Silver initiated additional CSAMT and IP surveys that extended coverage on the older lines, and extended coverage to the east of the pre-existing coverage. The geophysical database for the Peñasquito Project area now provides a detailed geophysical database that images changes in geology and has identified other targets of interest.
     Kennecott completed an extensive rapid air blast (“RAB”) drilling campaign across much of the Peñasquito Project area after the discovery of the Chile Colorado Zone. This program, designed to systematically test the entire project area, consisted of 250 holes. The holes penetrated the extensive overburden cover and collected chip samples from the top few metres of bedrock. Twenty-eight of the RAB holes in this campaign by Kennecott were drilled within and immediately adjacent to the Peñasco Zone. The geochemical survey results identified broad zinc, lead, gold and silver anomolies that warranted further exploration. Exploration drilling results have subsequently confirmed significant mineralization in the Peñasco and Chile Colorado zones.
     Exploration has continued uninterrupted since 2002. Between one and nine exploration drill rigs have been on site at any given time since then. To the date of the resource estimate set out below under “Mineral Resource and Mineral Reserve Estimates”, 782 drillholes totalling 396,000 metres had been drilled.
Drilling
     The Peñasquito Project has been drilled by five mining and exploration companies, beginning with Kennecott in 1995 and extending through Western Copper/Western Silver, Mauricio Hochschield, Glamis and Goldcorp. Drilling has focused on the exploration of three principal areas: the original Chile Colorado Zone, the Brecha Azul Zone (Azul Breccia, Azul NE and Luna Azul) and the Peñasco Zone (including El Sotol). Work for the latest resource and reserve update concentrated on in-fill exploration drilling of the Peñasco Zone and the Brecha Azul Zone.
     The following table summarizes exploration drilling performed and assayed to date on the Peñasquito Property. This data has been used in the preparation of the resource estimates used in the Peñasquito Report. Additional exploration drilling is ongoing.

- 45 -


 

                 
CATEGORY   TOTAL DRILL HOLES
    Number   Meters
Holes in Database (1)
    782       396,426  
Hochschild Holds Excluded for Resource Estimate
    14       4,601  
PP (water wells) Series Excluded for Resource Estimate
    7       2,064  
Holes Used for Resource Estimate including condemnation
    761       389,761  
 
(1)   15,135 metres are reverse circulation drilling; the balance are core.
Sampling, Analysis, Security and Data Verification
     Due to the alluvial cover, the vast majority of resource sampling at the Peñasquito Project has been done using diamond core drilling or, less commonly, reverse-circulation drilling. Most diamond drilling is HQ size core, but narrowing to NQ diameter at depth in the longer holes. Drillhole spacing is generally on 50 metre centres in the main deposits spreading out to 400 metre spaced holes in the condemnation zones. Drilling covers an area approximately 8,000 metres east-west by 4,500 metres north-south with the majority of holes concentrated in an area 2,100 metres east-west by 2,800 metres north-south.
     Minera Peñasquito has sampled drill holes from bedrock to final depth. The standard sample interval is 2.0 metres. Some samples are limited to geological boundaries and are less than 2.0 metres in length. A senior geologist examines the core, defines the primary sample contacts, and designates the axis along which to cut the core. Special attention in veined areas was taken to ensure representative splits were made perpendicular and not parallel to veins.
     Geological logging is very detailed and follows the geological legend on a regional scale. Once the core has been measured, marked, photographed, and logged geotechnically and geologically, the core boxes are brought to the diamond saw cutting stations located at the project site. The core is sawed in half. One-half of every sample is placed into a heavy plastic bag that the splitter’s helper has previously marked with the drill hole and sample number and the sample tag has been inserted into the plastic bag. Standard reference material samples and blanks are inserted into the sample stream going to the assay laboratory in a documented sequence on a frequency of one standard reference sample every 40 samples and a blank every 50 samples. The analytical laboratory also inserts its own standard reference samples.
     The plastic bags are placed into large sacks and picked up by an ALS Chemex transport truck which delivers them directly to ALS Chemex Laboratories (“ALS”) in Guadalajara, Mexico approximately twice per week, where the samples are prepped and pulped. Pulps are then sent to ALS in Vancouver, British Columbia where they are assayed and checked. At present ALS is Minera Peñasquito’s primary assay lab. Check samples are sent to Acme Laboratories (“Acme”) of Vancouver, British Columbia. Both ALS and Acme are ISO9002-certified laboratories and both use industry standard sample preparation procedures.
     The sample preparation procedures on site before shipment to the laboratory have been independently reviewed and deemed secure and adequate. The quality assurance and quality control (the “QA/QC”) procedures employed by Minera Peñasquito have been independently audited by MDA (Mine Development Associates, Reno, Nevada).
     Based on a review of Minera Peñasquito’s sample preparation, analysis, security, and QA/QC procedures to date with respect to database verification, the database used for the resource estimates is deemed to be accurately compiled and maintained, and is suitable for use in mineral resource estimation.
     The Peñasquito Report states that no significant problems were identified during reviews of the drilling data, that the holes appear to have been properly located and downhole-surveyed and to have recovered an adequate sample (core recovery during the later Minera Peñasquito campaigns averaged 97.8%).
     The check assay data was supplemented by performing numerous paired comparisons of grades from different drilling and assaying campaigns, including those for which no check assays are available. The results show

- 46 -


 

no evidence to indicate that any of the Minera Peñasquito and Kennecott database assays are affected by large analytical or sample preparation biases. However, they do suggest that the Hochschild grades are quite heavily high-biased relative to the Minera Peñasquito and Kennecott grades for gold, silver and zinc. No Hochschild samples were available for re-assay, so the precautionary decision was taken not to use the Hochschild assays when estimating grades in the resource model.
     The paired-comparison reviews did not detect any biases between core and reverse circulation drilling (about 10% of the exploration drilling is reverse circulation).
Mineral Reserve and Mineral Resource Estimates
     The following table sets forth the estimated Mineral Reserves for the Peñasquito Project as of December 31, 2007:
Proven and Probable Mineral Reserves (1)(2)(5)(6)(7)
                                                                                 
                    Grade   Contained Metal
Deposit   Category   Tonnes   Gold   Silver   Lead   Zinc   Gold   Silver   Lead   Zinc
            (millions)   (grams   (grams   (%)   (%)   (millions   (millions   (millions   (millions
                                    of ounces)   of ounces)   of pounds)   of pounds)
                    tonne)   tonne)                                                
Peñasquito Project
  Proven     426.80       0.57       34.0       0.36       0.78       7.85       466.9       3,432       7,365  
Mill (3)
  Probable     380.30       0.37       27.2       0.29       0.65       4.55       332.6       2,444       5,442  
 
                                                                               
 
  Proven + Probable     807.10       0.48       30.8       0.33       0.72       12.40       799.5       5,876       12,806  
 
                                                                               
 
                                                                               
Peñasquito Project
  Proven     42.20       0.21       20.9                   0.28       28.3              
Heap Leach (4)
  Probable     68.30       0.17       16.4                   0.37       36.1              
 
                                                                               
 
  Proven + Probable     110.50       0.18       18.1                   0.65       64.4              
 
                                                                               
 
(1)   The Mineral Reserve estimates for the Peñasquito Project set out in the table above have been prepared under the supervision of Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, who is a qualified person under NI 43-101. The Mineral Reserves are classified as proven and probable, and are based on the CIM Standards.
 
(2)   Based on a gold price of $525 per ounce, a silver price of $10.00 per ounce, a lead price of $0.40 per pound and a zinc price of $0.80 per pound.
 
(3)   The estimated metallurgical recovery rate for the Peñasquito Project (Mill) is 5% to 64% for gold, 5% to 65% for silver, 63% to 72% for lead and 60% to 75% for zinc.
 
(4)   The estimated metallurgical recovery rate the Peñasquito Project (Heap Leach) is 50% for gold and 22% for silver.
 
(5)   The Proven and Probable Mineral Reserves have been calculated using NSR (Net Smelter Return) cut-off grades and assuming the Mineral Reserves metals prices set forth above. These cut-off grades are: $4.55 NSR for Peñasco-Azul sulphide feed and $5.18 NSR for Chile Colorado sulphide feed. A run-of-mine , heap leach process for gold and silver has been defined for the oxide materials at an NSR cut-off of $1.18 for Peñasco-Azul and $1.30 for Chile Colorado.
 
(6)   Proven and Probable Mineral Reserves are a subset of Measured and Indicated Mineral Resources.
 
(7)   Numbers may not add up due to rounding.

- 47 -


 

     The following table sets forth the estimated Mineral Resources for the Peñasquito Project as of December 31, 2007:
Measured, Indicated and Inferred Mineral Resources (1)(2)(3)(4)
(excluding Proven and Probable Mineral Reserves)
                                                                         
            Grade   Contained Metal
Category   Tonnes   Gold   Silver   Lead   Zinc   Gold   Silver   Lead   Zinc
    (millions)   (grams   (grams   (%)   (%)   (millions   (millions   (millions   (millions
            per   per                   of ounces)   of ounces)   of pounds)   of pounds)
            tonne)   tonne)                                                
Measured
    107.02       0.25       21.2       0.23       0.62       0.86       73.0       536       1,453  
Indicated
    571.44       0.21       18.5       0.19       0.51       3.87       340.3       2,406       6,464  
 
                                                                       
Measured + Indicated
    678.46       0.22       18.9       0.20       0.53       4.73       413.3       2,942       7,917  
 
                                                                       
Inferred
    1,220.00       0.23       13.0       0.07       0.50       9.02       509.9       1,883       13,448  
 
(1)   The Mineral Resource estimates for the Peñasquito Project set out in the table above have been prepared by Fred H. Brown, CPG, Independent Geological Consultant, who is a qualified person under NI 43-101. The Mineral Resources are classified as measured, indicated and inferred, and are based on the CIM Standards.
 
(2)   Mineral Resources are based on a gold price of $650 per ounce, a silver price of $13.00 per ounce, a lead price of $0.50 per pound and a zinc price of $1.00 per pound.
 
(3)   Mineral Resources are not known with the same degree of certainty as Mineral Reserves and do not have demonstrated economic viability.
 
(4)   Numbers may not add up due to rounding.
Proposed Mining Operations
Mine Plan
     The mine plan will provide sulphide ore to a mill flotation plant that will produce two concentrates for sale: a lead concentrate and a zinc concentrate. Both concentrates will have gold and silver credits. Likewise, the mine plan will provide oxide and mixed ores to a heap leach operation that will produce a silver and gold doré.
     The mine plan provides for a combined production schedule for both sulphide and oxide ores from both the Peñasco and Chile Colorado zones. The calendar year 2007, the start of mining operations, is taken as Year 1 in the mining schedule. Half-way through Year 3, sufficient sulphide ore is available such that the mill operation can begin under a 15-month start-up and commissioning mode. Commercial mill production is scheduled to begin in Year 4 and is planned to continue through Year 20 at an annual mining rate of 46.8 million tonnes of sulphide ore per year. The total material mined per year increases over the first four years to peak at 216.0 million tonnes (592,000 tonnes per day). The production rate increases correspond to significant increases in the equipment quantities of the mining fleet. Commercial sulphide production is scheduled for 20 years.
     Mining begins in the Peñasco pit, which provides the only sulphide mill feed through Year 11, and continues to provide mill feed through Year 20. Waste stripping begins in the Chile Colorado Zone in Year 10 and sulphide ore is mined during Year 12 through Year 20.
Environmental Permitting
     A large number of permits are in the process of being obtained in order to bring the Peñasquito Project into production. For the most part, federal laws regulate mining in Mexico, but there are some project components subject to state or local approval. The Secretary of Environment and Natural Resources (“SEMARNET”) is the chief agency regulating environmental matters in Mexico. Three SEMARNAT permits needed to begin mine construction have been obtained: the Environmental Impact Assessment (“EIA”), the Risk Study and the Land Use Change. A land use license from the municipality of Mazapil and an archaeological release letter from the National Institute of Anthropology and History have also been obtained. An explosives permit from the National Secretary of Defence have been obtained.

- 48 -


 

Taxes
     The Peñasquito Report calculates taxes on a project basis in accordance with published Mexican taxation legislation effective in 2007. In the Peñasquito Report, income tax was calculated at a rate of 28% of taxable income after 2007 and an allowance for employee profit sharing was been included. Based on this analysis, total estimated federal income tax paid over the life of the mine is $2.3 billion. However, as discussed under the heading “Mexico” above, during 2007 the Government of Mexico adopted a Single Rate Business Tax (“SRBT”) which became effective as of January 1, 2008, and repealed the asset tax as of that date. The Peñasquito Report does not include an assessment of the effect of the SRBT on the Peñasquito Project.
     Optimization and detailed design for the Peñasquito Project is continuing and certain of the project parameters may change as such work progresses. No smelting, refining or transportation contracts have yet been entered into.
Mine Life and Payback
     Based on the current estimates of Proven and Probable Mineral Reserves, together with the selected production rate, result in a mine life of 20 years. Based on the cash flow schedule in the Peñasquito Report, the payback of the initial capital investment will be realized in 5.7 years for the base case.
CENTRAL AND SOUTH AMERICA
     The Corporation’s properties in Central and South America include the Alumbrera Mine, the Marlin Mine, the San Martin Mine and the Cerro Blanco Project. During 2007, mining was completed at the San Martin Mine; production from residual leaching of the heap leach pads will continue during 2008.
ALUMBRERA MINE, ARGENTINA
Property Description and Location
     The Alumbrera Mine, 37.5% owned by the Corporation, consists of the following five facilities, with support offices located in Tucumán, Catamarca City, Rosario and Buenos Aires:
    an open pit mine, processing facilities and central administration offices at Alumbrera, Catamarca;
 
    a 316-kilometre concentrate slurry pipeline through Catamarca and Tucumán Provinces;
 
    a 202-kilometre, 220 kilovolt power line from the project’s substation at El Bracho, Tucumán;
 
    a filter plant and rail loading facilities at Cruz del Norte, Tucumán; and
 
    a port, handling facilities and train maintenance facilities at San Martìn near Rosario, Santa Fé.
     The open pit mine is located on a 600 hectare mining lease at Alumbrera, near Belen in northwestern Argentina, 1,100 kilometres northwest of Buenos Aires. The mining lease encompasses all mineralized areas of the deposit. Immediate mine infrastructure and other mine facilities cover an additional permitted surface area of 5,200 hectares. The mine is located in a valley west of the easternmost range of the Andes at an elevation of 2,600 metres above sea level.
     The Alumbrera Mine processes ore through conventional crushing, grinding, sulphide flotation and gravity gold circuits. Concentrate slurry from the processing facilities is pumped 316 kilometres to a filter plant at Cruz del Norte. Concentrates from the filter plant are shipped 830 kilometres by rail from Cruz del Norte, Tucumán to Puerto Alumbrera. The port is located in San Martín, Rosario in the Province of Santa Fé. The port operation and maintenance facilities are contained within a 12 hectare lease which includes a rail-switching yard with approximately 8,200 metres of rail. Port facilities include a rail car unloading building and 50,000 tonne storage shed.

- 49 -


 

     All mining prospects in the Farallón Negro district, the region including Alumbrera, are enclosed within a 344 square kilometre national mineral reserve and are owned and administrated by Yacimientos Mineros de Agua de Dionisio (“YMAD”), a quasi-government mining company. In April 1994, MAA and YMAD entered into an agreement, since amended, to form a Unión Transitoria de Empresas (“UTE”) for the purpose of exploiting the Alumbrera Mine (the “UTE Agreement”). A UTE is a legal construct recognized by the law of Argentina that is similar to a joint venture. The UTE Agreement defines the working relationship between the parties, including royalty obligations, and requires that ownership of certain of the infrastructure revert to YMAD after completion of operations. The assets subject to the UTE Agreement are jointly owned by MAA and YMAD, the participants in the UTE. The UTE Agreement provides that the UTE is managed by a Management Committee comprised of eight members; five appointed by MAA and three appointed by YMAD. Each of the Management Committee members has one vote and decisions are adopted by a majority of the votes. The UTE Agreement designates MAA as the operator of the Alumbrera Mine and grants to MAA all the rights to explore and exploit the Alumbrera Mine, including the power to extract, treat, beneficiate, transport and market the minerals from the Alumbrera Mine, as well as the other rights vested by the Mining Code of Argentina in YMAD as the owner of the Alumbrera Mine. As of December 31, 2007, Xstrata indirectly holds a 50% interest in MAA, Goldcorp indirectly holds a 37.5% interest in MAA, and Yamana Gold Inc. (“Yamana”) indirectly holds a 12.5% interest in MAA (Goldcorp and Yamana hold their respective interests in MAA through Musto Explorations (Bermuda) Limited) (“Musto”). MAA has a four-member board of directors comprised of two representatives from Xstrata and two from Musto.
Royalties
     Minera Alumbrera Limited, the operator of the Alumbrera Mine (“MAA”), is required to pay a 3% royalty (the “Boca Mina Royalty”) to the provincial government of Catamarca. The royalty is calculated on the value of mineral substances at the mine mouth after certain allowable deductions. Allowable deductions include all processing and transportation costs, but exclude mining costs and all depreciation. MAA commenced payments of the Boca Mina Royalty in 1998.
     Under the terms of the UTE Agreement, beginning in the fiscal year following the one in which positive net proceeds are realized, MAA is also obliged to pay a royalty to YMAD equal to 20% of net proceeds after capital recovery and other adjustments related to working capital. In 2006, positive net proceeds, as defined in the UTE Agreement, were realized, triggering the requirement to pay YMAD the 20% net proceeds royalty. MAA calculates and accrues the royalty payable to YMAD on a monthly basis according to the formula set forth in the UTE Agreement. Prior to the realization of positive net proceeds, MAA was obligated to pay YMAD in each fiscal year, beginning after the second full fiscal year following the commencement of commercial production and ending the year in which MAA began to pay the net proceeds royalty, an advance royalty equal to (i) if net income was less than $1 million, 5% of net income; or (ii) if net income was more than $1 million, the greater of 5% of net income and $1 million only after the capital recovery and certain other adjustments. During 2007, the Corporation recorded YMAD royalty expenses of $111 million (2006 - $35 million).
Accessibility, Climate, Local Resources, Infrastructure and Physiography
     Alumbrera is about 1,100 kilometres northwest of Buenos Aires and six hours by paved and dirt roads from the airport at San Miguel de Tucumán. Located in Hualfin District, Belen Department, Catamarca Province, the deposit is 95 kilometres northeast of the town of Belen and approximately 50 road-kilometres northwest of Andalgalà. The project is served by air and all-weather roads. Alumbrera has scheduled flights and road transport to and from Tucumán and Catamarca and the mine site. On average, more than 2,100 people are transported by road and more than 2,500 people are transported by air every month.
     The climate is arid to semi-arid with topography and vegetation similar to the Arizona-Sonora desert. The Alumbrera Mine is near the boundary between the Sierras Pampeanas and Puna physiographic provinces and the area is sparsely populated. Average mean temperature is 17 to 18 degrees Celsius and average minimum and maximum temperatures range between 8 and 10 degrees Celsius and 22 and 27 degrees Celsius. Temperatures can be as low as minus 10 degrees Celsius in the winter and as high as 40 degrees Celsius in the summer. Average mean rainfall is 160 millimetres, occurring predominantly during the months of December through March. Light snows can occur in the winter.
     Mine site infrastructure includes offices, a warehouse, a laboratory, a medical centre, a permanent camp and workshops. Site facilities include two accommodation camps, catering, medical and indoor and open-air recreation facilities. The mine’s main water supply originates from a bore field, Campo Arenal, and is delivered to the mine site through a 30-kilometre pipeline. The mine maintains a 1.7 million cubic metre water reservoir. A 202-kilometre long 220-kilovolt power line provides electrical power to the mine site from a substation at El Bracho, Tucumán. The power line, with 530 transmission towers, was constructed to provide access to the national power grid.
     Topographically, (prior to commencement of mining) the deposit at the Alumbrera Mine was a bowl-shaped, ellipsoidal depression oriented northeast-southwest surrounded by ridges formed mostly by andesitic breccia of the Farallón Negro volcanics. The floor of the bowl covers an area of 2.5 square kilometres. It is characterized by altered yellowish and reddish rocks that are the oxidized and weathered “surface rind” of hydrothermally altered and mineralized zones that were easily weathered in the recent geologic past, thereby forming the bowl.

- 50 -


 

History
     The Alumbrera area has been known for its veins of copper and gold deposits and alum since at least the 19th century. Small-scale mining activity took place at the end of the 19th century and during the early 20th century at the southern edges of the present mine area. In 1950, the Alto de la Alumbrera veins were sampled by the government for copper and gold. In 1963, a mapping and geochemical survey defining a deposit of disseminated/scattered copper was conducted. In 1969, YMAD carried out a thorough geological geochemical prospecting program and completed four short drill holes.
     From 1973 to 1976, the government carried out a geophysical study (induced polarization and magnetism) and commenced a drilling program. Drilling was completed over several years with 6,000 metres drilled from 1974 to 1976. YMAD carried out resource mapping and evaluation from available drill holes. From 1975 to 1982, there was intermittent drilling to complete a total of 18,970 metres and 71 drill holes for the period 1968 to 1981.
     From 1985 to 1988, YMAD investigated open pit mining and heap leaching of ore from the central gold-rich oxidized zone. An additional 1,283 metres of drilling, averaging 50 metres per hole, was completed. Feasibility studies were prepared in 1986 and 1988.
     From 1992 to 1993, another feasibility study was conducted. Geological exploration activity included geotechnical investigations, a core relogging program and a diamond drilling program, mineralogical assessments and a complete reinterpretation of the deposit geology. A geology and metal grade block model of the deposit was generated.
     In October 1994, Alumbrera completed a 20-hole, 8,000-metre diamond drillhole program. Drilling was concentrated in the southern flank of the ore body and within the area to be mined during the first five years of the open pit life. In 1995, Alumbrera commenced mining activities in the mine area. In August 1997, project commissioning commenced with the processing of the first ore from the mine. In December 1999, the mine achieved production and performance tests under terms of project financing.
     Musto Explorations (Bermuda) Limited (“MEB”) acquired an interest in the Alumbrera project from YMAD in 1990, and established MAA as the entity to exploit the deposit in 1993. M.I.M. Holdings Limited (“MIM”) purchased a 50% interest in MAA in 1994. MEB, with a 50% remaining interest in MAA, was subsequently acquired by Rio Algom Ltd. and North Ltd. in 1995. Rio Tinto Limited acquired North Ltd. in August 2000. Billiton acquired Rio Algom Ltd. in October 2000. BHP and Billiton merged during 2001 to form BHP Billiton. In 2003, Goldcorp acquired Rio Tinto Limited’s 25% indirect interest in MAA together with 50% of BHP Billiton’s indirect interest in MAA. The remaining 50% of BHP Billiton’s indirect interest in MAA was acquired by a subsidiary of Northern Orion Resources Inc. (“NNO”). Also in 2003, MIM was acquired by Xstrata. In 2007, a subsidiary of Yamana Gold Inc. acquired NNO. As a result, as of December 31, 2007, Xstrata indirectly holds a 50% interest in MAA, Goldcorp indirectly holds a 37.5% interest in MAA, and Yamana Gold Inc. indirectly holds a 12.5% interest in MAA.

- 51 -


 

Geological Setting
Regional Geology
     The Alumbrera deposit was emplaced in the late Miocene Farallón Negro — Capillitas volcanic flow and breccia complex, situated in the Sierra de Capillitas. This high-potassium calc-alkaline shoshonitic to banakitic volcanism is the easternmost expression of subduction related volcanism which appears to have developed in block-faulted areas on Palaeozoic crystalline basement along the Andean Cordillera in the late Miocene. The Farallón Negro complex lies near the boundary of nearly flat and 30-degree east dipping segments of the subducting Nazca Plate, a discontinuity expressed by the east-west boundary between the Puna and Sierras Pampeanas provinces, by a 50-kilometre right-lateral offset in the Andes crest and by the east-west trend of Neogene volcanoes of the Ojos de Salado chain west of Alumbrera and the Farallón Negro centre.
     The Alumbrera deposit and its host stratovolcano lie between two northeast-trending lineaments, the Hualfin and Aconquija, which may have localized volcanism and mineralization in tension fractures between them. The volcanism was controlled by sinistral pull-apart tectonics along a major northwest trending lineament. The Farallón Negro volcanic and intrusive complex was a stratovolcano formerly up to 6 kilometres high and approximately 16 kilometres in diameter, which evolved from more mafic pyroxene andesites to more hornblende and biotite bearing andesites and dacites. Volcanism was followed by the emplacement of the mineralization-related dacite porphyries. The location of the dacite porphyries coincides with the eruptive centres of the former andesite-dacite stratovolcano, whose roots they intruded.
Deposit Geology
     The Alumbrera alkalic dacite porphyries were intruded about 8 million years ago into the roots of the Farallón Negro volcano. The intrusion-generated large-scale hydrothermal circulation resulted in alteration and mineralization of the porphyry itself and its volcanic host rocks. Subsequent erosion has exposed the upper part of the volcano and its porphyry system to a level that is favourable for mining.
     The Farallón Negro host rocks are about 90% autobrecciated flows in a thick-bedded sequence of fragment-poor to fragment-crowded weakly to strongly porphyritic potassic andesite. The remaining 10% is comprised of lithic and non-porphyritic flow units.
     The primary mineralized rocks of the Alumbrera deposit consist of a series of porphyritic intrusions. A total of seven distinctive porphyritic intrusions have been recognised, which form stocks (earliest units) and dyke-like bodies (youngest units) that extend to the outer edge of the deposit with some of the dykes forming a radial pattern around the central stocks. Geochemically the dacites are typical for subduction-related potassic igneous rocks (shoshonites) from mature continental arc settings.
Exploration
     The mining rights to the Alumbrera Mine are limited to a 2,000 metre by 3,000 metre rectangle (600 hectares in size) approximately centred on the open pit mine. This area, referred to as the contract area, is slightly larger than the ultimate pit rim dimensions. No exploration is conducted by MAA outside of the contract area.
     Because of the very limited area of mineral rights involved and the dominance of the area by the open pit mine, further exploration work will be limited.
Mineralization
     The mineralogy of the primary (unweathered) ore consists of chalcopyrite (± bornite), native gold and pyrite. Gold occurs mainly in chalcopyrite. Gold values correlate closely with copper values in primary mineralization and ratios are very consistent through the deposit.
     Ore grades correlate with lithology. The highest copper-gold grades are associated with intense potassic (quartz-magnetite) alteration of two of the earliest mineralized porphyritic intrusions and in adjacent biotized

- 52 -


 

or potassium feldspar altered andesites. Younger porphyries are less mineralized or barren. The majority of the copper is primary and occurs as chalcopyrite in disseminated grains and in veinlets. Copper and gold are positively correlated with gold occurring in association with early pyrite-chalcopyrite-magnetite as free gold grains in the 10 to 50 micron range. The economic-grade sulphide mineralization extends upward almost to surface.
     The upper portion of the ore body has been subject to weathering and can be sub-divided into two distinct zones, an upper, thin, leached zone, and a lower sulphide enriched zone. The leached zone contains oxide and carbonate copper minerals, including soluble species. Gold values appear largely unaffected by leaching. The sulphide-enriched zone is complex and contains chalcocite, covellite, native copper and chalcopyrite in varying proportions. The intensity of chalcocite decreases with depth and is absent in fresh (primary) ore. Leaching and oxidation near the surface generally does not extend to deeper than 30 metres.
Drilling
     The Alumbrera Mine has been worked on by at least four different companies with numerous drilling campaigns since YMAD commenced work in 1969. Both reverse circulation and diamond drilling has been performed, however, the database is composed predominantly of diamond core data. The diamond drill programs were completed using both N-sized core (“NQ”) and H-sized core (“HQ”) long-year Q-series drilling systems (47.6 millimetres and 63.5 millimetres core diameter, respectively).
     270 holes were drilled on a nominal 50 metre by 50 metre pattern over the entire deposit. However, due to shorter lengths on some holes, this density decreases somewhat at the deepest pit elevations. All holes were drilled on N75o/N255o oriented sections, with dips varying between vertical and minus 60o. This orientation was chosen so as to best outline faults in the dominant fault strike direction, many of which have material post-mineralization movement or control the intrusion of the host porphyry and mineralizing fluids.
     After the 1998-99 resource definition drilling program it became apparent that it was necessary to drill a few more holes to increase data density at the deeper elevations of the pit. This was required in order to improve geological controls on the model and upgrade some of the indicated resources to the measured category based on the models used to estimate mineral resources and Kriging variances seen during grade interpolation. An additional 14 holes were drilled to fill in areas of low confidence. This drilling highlighted that the economic mineralization was open at depth and that it could be potentially exploited by an expansion of the existing open pit.
     A significant drilling program was conducted during 2004, resulting in the addition of more than two years of operating life to the Alumbrera Mine. Additional drilling following up on favourable results received in 2004 was conducted in 2005. Because of the very limited area of mineral rights involved and the dominance of the area by the open pit mine, further exploration work will be limited.
Sampling and Analysis
     Exploration samples were sawn (core) or split (reverse circulation) and sent to ALS Chemex (“ALS”) in Mendoza for further preparation and analysis, following which the assay results were reported by ALS.
     Exploration samples were analysed for gold using a 50 gram fire assay with a flame AAS finish after nitric acid/aqua regia digestion of the bead. This method has a detection limit of 0.01 parts per million and is suitable for the low gold grades seen at Alumbrera. Samples were analysed for copper and silver using an aqua regia mixed-acid digestion and elemental determination by flame AAS. The detection limit for copper and silver by this method are 100 parts per million and 1.0 parts per million, respectively.
     Minor element analyses have been routinely carried out on approximately 10% of samples to determine base line quantities of potentially toxic metals available to be released into the environment. Samples were randomly selected and analyzed for antimony, arsenic, bismuth, cadmium, lead, mercury, molybdenum, selenium, tellurium and zinc. Additional sampling was conducted in areas identified to have lead and zinc bearing veins.
     Sulphur and sulphate analyses were also conducted in order to estimate the amount of pyrite within the deposit.

- 53 -


 

Drill Core Samples
     During logging, the Alumbrera geologist selects the portions of each hole to be sampled based primarily on mineralization. Using visual inspection, the location of the 0.15% copper boundary would be estimated and sampling would commence approximately 50 metres before this estimated position. Samples were selected on three-metre intervals regardless of lithologic contacts and geological variation in the core. Once selected, the core to be sampled was sawn in half with a diamond saw and one half of the core retained. All sampling and core storage took place at the core logging facility.
Reverse Circulation Samples
     Reverse circulation samples were collected in the field at the drill rig over 3-metre intervals after being split in the ratio 3:1 at the sampler. The smaller sample was sent for analysis and the larger fraction retained on site for the duration of the drill program and then discarded.
Sample Quality
     The program set up to monitor the quality of the assay database consisted of the following procedures:
    the use of internal standards by the laboratory;
 
    the use of Alumbrera submitted standard samples with each sample batch;
 
    regular re-analysis of pulps by the laboratory;
 
    re-analysis of pulps as requested by Alumbrera;
 
    check analysis of randomly selected pulps by a second laboratory; and
 
    1/4 core re-sampling of selected sample intervals mixed with each batch.
     Data validation protocols are built into the date-entry system used by Alumbrera to prevent hole-depth, over-lapping logging/sampling intervals or hole-name validation errors.
Security of Samples
     MAA’s core logging and storage facility is located in the administration and warehouse building cluster beside the concentrator. These facilities are secure from entry by non-MAA personnel. Exploration samples are shipped from this location using scheduled mine delivery trucks.
Ore Reserve and Mineral Resource Estimates
     The following table sets forth the estimated Ore Reserves for Goldcorp’s 37.5% interest in the Alumbrera Mine as of June 30, 2007:
Proved and Probable Ore Reserves (1)(2)(3)(4)(5)
                                         
            Grade   Contained Metal
Category   Tonnes   Gold   Copper   Gold   Copper
    (millions)   (grams per tonne)   (%)   (millions of   (millions of
                            ounces)   pounds)
Proved
    138.75       0.45       0.43       2.00       1,317  
Probable
    3.75       0.35       0.38       0.04       31  
 
                                       
Proved + Probable
    142.50       0.45       0.43       2.04       1,348  
 
                                       

- 54 -


 

 
(1)   The Ore Reserves for the Alumbrera Mine set out in the table above have been estimated by Luis Rivera, MAusIMM at MAA, who is a qualified person under NI 43-101 and a competent person under the JORC Code. The Ore Reserves are classified as proved and probable, and are based on the JORC Code.
 
(2)   Based on a gold price of $500 per ounce and a copper price of $1.25 per pound.
 
(3)   The estimated metallurgical recovery rate is 75% for gold and 89% for copper.
 
(4)   Ore Reserves are based on a life-of-mine production schedule generated from pit optimization studies on the new resource block model and are reported on the basis of a recoverable payable copper equivalent cut-off grade of 0.26%, with the equivalent grade taking into account copper and gold grades, prices, metallurgical recoveries and realisation costs.
 
(5)   Numbers may not add up due to rounding.
     As of June 30, 2007, there are no Mineral Resources for the Alumbrera Mine.
Mineral Processing and Metallurgical Testing
     The economic mineralogy of the primary, unweathered ore consists of chalcopyrite, native gold and pyrite in a simple textural relationship. Chalcopyrite occurs in disseminated grains and in veinlets; copper and gold are positively correlated, with the gold occurring as free grains or, more usually, as inclusions within the chalcopyrite. As a classic porphyry copper-gold deposit, it is expected that the ore should respond to conventional sulphide flotation for recovery of gold bearing copper concentrate.
     There is a wide range of metallurgical testing and operating experience available and planned in support of strategic planning and development.
     The feasibility study metallurgical testing confirmed the amenability of the ore body to conventional copper porphyry processing. Although the programme was possibly not as systematic in establishing the metallurgical response of the ore body as has been the case on other similar projects, the feasibility study concluded that the testing adequately addressed all the expected issues and generated appropriate criteria for process design. These criteria have been generally confirmed by operating experience to date.
     MAA decided in 2001 to install a third grinding line and a pebble crushing circuit in order to meet the objective of maintaining concentrate production at lower ore grades over the life-of-mine. MAA has increased the capacity of the rougher flotation circuit which was successfully commissioned in 2004. During 2005, approval was obtained for the construction and installation of an additional ball mill which was commissioned in 2006. In 2007, operation of the additional mill line ramped up to expected production levels rapidly. To augment recovery, expansion of the flotation cleaner circuit began in 2007 and is expected to be operational in 2008.
Mining Operations
     Standard truck and shovel mining techniques operations are employed in the open pit mine, utilizing 42 cubic metre shovels and 220 tonne haul trucks to move both ore and waste. Mining is carried out on 17-metre benches, with 2-metre sub-drill, which suit the size of the equipment necessary for the production rate.
     Current mineral reserves have a low waste to ore ratio of an average of 2:1 for the 2007 life-of-mine plan. Operation of the mine is carried out at an elevated cut-off grade, which is reduced over the mine life to the economic cut-off grade. This practice requires that some ore be stockpiled for later processing.
     The mining rate in 2007 was slightly under 300,000 tonnes per day for a total of approximately 109 million tonnes of material mined, comprised of approximately 26 million tonnes of ore and 84 million tonnes of waste. The total material mined is planned to average 312,000 tonnes per day, approximately 114 million tonnes per annum for 2008 to 2010.
     MAA employs approximately 1,145 permanent staff and 630 operational and service contractors. Argentina is a highly unionized country with industry-based unions and very prescriptive labour agreements. The current labour agreement was renegotiated in 2007 and is in effect for a four year period.

- 55 -


 

Milling Operations
     The original plant uses a conventional porphyry copper flotation circuit with proven, large scale equipment. The plant produces two products, a copper flotation concentrate containing the major gold credit and doré bullion from gravity recovery of coarser free gold. The original design capacity was 80,000 tonnes per day with a utilisation of 94%. Provision was made for expansion to 100,000 tonnes per day by the addition of a third grinding line, in order to maintain metal production as the ore grade decreases.
     MAA has increased the capacity of the original plant to approximately 100,000 tonnes per day by the addition of the third grinding circuit, albeit using smaller equipment than that already installed. The expansion also included a pebble crushing circuit to handle critical size material from the semi-autogenous grinding (“SAG”) mills, of which about 1 to 1.5 million tonnes, at 0.4% copper, already had been accumulated. MAA identified that the ball mill capacity was the limiting factor to additional throughput in the expanded plant and that a low capital option to increase throughput by approximately 10% to 110,000 tonnes per day was the installation of an additional 6.1 metre diameter, 9.34 long ball mill.
     The project design included a modification of the cyclone feed flow to grinding lines 1 and 2. By extracting a portion of the cyclone feed flow and redirecting it to the new ball mill, extra capacity has been achieved in lines 1 and 2. This optimizes the operation by reducing the recirculation of pulp into the existing ball mills, increasing throughput and achieving a lower average grind size. As a result of these improvements, this circuit is no longer a bottle-neck and SAG mill throughput has increased.
     The new mill configuration has the flexibility to operate with a variable number of cyclones in each battery diverting flow to the new circuit and directing the crushed pebbles flow to SAG 1, 2, 3, or new ball mill. This allows the plant to operate more efficiently under any plant restriction, whether the restriction is in the SAG or ball mills.
     Although the cleaner flotation circuit is a constraint to feed metal, this will not be a problem except on the softest, high grade ore, as lower ore grade will compensate for the increased throughput. MAA has not identified any other areas that require expansion, although it acknowledges that increased utilisation in most areas is required. Work is underway, however, to expand the capacity and the efficiency of the cleaner circuit. This should be completed in 2008.
     The mined ore is crushed in a 1,540 millimetre by 2,770 millimetre gyratory crusher. The crushed ore is conveyed 1.7 kilometres to an 80,000 tonne live capacity stockpile. The ore is drawn from the stockpile by apron feeders to conveyors feeding three parallel grinding circuits. The two original grinding lines each consist of an 11 metre diameter, 5.14 metre long SAG mill and two 6.1 metre diameter, 9.34 metre long ball mills operating in closed circuit with hydrocyclones. The third grinding line, which was commissioned in August 2002, consists of a 8.53 metre diameter, 4.27 metre long SAG mill and a 5.03 metre diameter 8.84 metre long ball mill, both of which are reconditioned second-hand units. It has been the practice to remove and stockpile the minus 35 millimetre critical size pebbles from the SAG mill discharge when processing harder ores with lower throughput rate. A circuit was commissioned in August 2002 for crushing the stockpiled pebbles and the newly generated pebbles, as required. The pebbles are conveyed via a surge bin to a crusher operating in open circuit and the crushed pebbles will be conveyed via a surge bin to each of the three SAG mill feed conveyors.
     SAG and ball mill discharge is pumped to a cluster of hydrocyclones, one cluster for each ball mill. Hydrocyclone underflow discharges to the ball mill feed, with a minor proportion diverted via two centrifugal gravity concentrators for each cluster, for removal of coarser free gold. Hydrocyclone overflow at 80% passing 150 microns gravitates to the flotation circuit. The gravity concentrate is transferred to the secure gold room for further cleaning and smelting with fluxes to bullion.
     After conditioning with reagents, the hydrocyclone overflow passes to the rougher flotation circuit consisting of 32 100 cubic metre mechanical flotation cells. MAA has expanded the flotation capacity to allow further ore residence time, thus improving recoveries in difficult ore types. This expansion was successfully commissioned in mid-2004. Rougher concentrate is reground in one or two 5.0 metre diameter, 7.32 metre long ball mills operating in closed circuit with hydrocyclones, and centrifugal gravity concentrators for further free gold

- 56 -


 

recovery. The reground rougher concentrate passes to the cleaner flotation section, consisting of 14 pneumatic flotation cells arranged for two stages of cleaning and a cleaner scavenger, all in closed circuit. The concentrate from the second stage cleaner is the final product and the tailings from the cleaner scavenger are now recirculated to the rougher circuit, although as commissioned these cells operated in open circuit producing final tailings.
     Final concentrate is thickened to 63% solids in two 30 metre diameter thickeners and for storage in surge tanks before being pumped via a 316 kilometre long, 175 millimetre diameter pipeline to MAA’s filter plant near Tucumán. Positive displacement pumps at the mine site and two booster stations elevate the concentrate to a high point from where it flows by gravity 150 kilometres to the filter plant. At the filter plant, the concentrate is stored in surge tanks and thickened prior to being fed into three 120 cubic metre continuous belt filter presses, which reduce the moisture content to 7.5%. The filters discharge to a storage building, where a front-end loader reclaims the filter cake for rail transport 830 kilometres to the port near Rosario.
     Tailings from the process plant flow by gravity pipeline for 8.5 kilometres to an engineered, centreline dam constructed across the Vis Vis canyon. Distribution is effected by spigotting along the upstream face of the dam. Supernatant water is pumped back to the process plant and seepage is collected downstream of the dam and pumped back. The dam is raised using waste rock with a core of selected material and remains a significant capital cost throughout the life of the mine. MAA retains Knight Piesold as its consultant for tailings dam management and construction quality control.
Markets and Contracts
     MAA’s objective has been to sell 90% to 95% of its concentrate production through frame contracts, with the balance for sale into the spot market. This has reduced the annual average treatment and refining charges and provided short-term flexibility of production, sales and revenue. In this way, the project is able to utilize the market conditions to their optimum advantage. Marketing is managed by MAA and Xstrata copper marketing personnel.
Environmental Considerations
     MAA, in its capacity as the operator of the Alumbrera Mine, is responsible for compliance with the commitments made in the main environmental permit for the Alumbrera Mine and the cost of reclamation and closure. MAA is committed to stabilizing tailings and waste rock against potential acid generation and water pollution and, to this end, is conducting studies to verify that closure plans will successfully achieve these requirements. Other activities include contaminated land remediation, removal and stabilization of potentially acid generating road base material, securing pit safety and closure of infrastructure. Ongoing environmental management is recognized as part of routine operations and associated costs are included in the project’s financial plan. Studies are ongoing to verify measures for controlling acid generation from waste rock and tailings materials at closure, including cover modeling studies, vegetation assessments, and groundwater modeling studies. MAA makes provisions for reclamation and closure in its life-of-mine plans and financial statements, however, MAA is not required to post a bond in connection with its reclamation and closure obligations and no cash provisions are being made. MAA’s closure planning is an ongoing process that is refined as the operations plans are revised and operational and monitoring data are evaluated. Closure costs for the Alumbrera Mine are revised on an annual basis.
Permitting
     The main environmental permit is the original EIR, which was prepared to World Bank guidelines and was approved in 1997 as part of the project approval process. The EIR must be updated bi-annually as two separate reports for approval by the Tucumán and Catamarca provincial authorities. The Catamarca EIR was submitted in early 2007 and approved by mid-year. The Tucumán EIR is to be submitted before the end of 2008. The prior Tucumán EIR was never officially approved by the provincial authorities, though by law it became automatically approved 60 days after submission. Under the terms of the UTE Agreement, MAA is responsible for compliance with the commitments made in the EIR and the cost of reclamation and closure. There are currently no significant areas of non-compliance. Other statutory environmental controls are the water license associated with the fresh water supply from Campo Arenal (Catamarca) and the filter plant discharge license (Tucumán).

- 57 -


 

     In addition to the direct statutory controls, the UTE Agreement contains requirement for consultation with YMAD on strategic environmental management issues, including closure options.
     Third party auditors are utilized to review key environment areas such as tailings storage facility design, construction and management. Through Xstrata and the other shareholders, MAA conducts regular audits of its environment programs to ensure that corporate, community and statutory standards have been adequately identified and are being adhered to.
Compliance
     Under the terms of the UTE Agreement, commitments made in the EIR reside with MAA. In response to these commitments, MAA has revised its environmental management system to comply with the International Standard ISO14001. Various initiatives have been taken and are ongoing to ensure compliance, which is demonstrated by routine monitoring of air and water quality against background levels. Certification was accredited at the end of 2005 for the Concentrate Pipeline, the Filter Plant, Train Transportation and the Rosario Port areas. The implementation of the Standard in all the other areas commenced in 2006 and continued in 2007, with a focus on the Mine Operations and Process Plant areas.
     Of particular significance is the commitment to minimize impacts to the quality of groundwater and surface water, which is implemented by intercepting and pumping back surface and near surface groundwater downstream of the tailings storage facility. Despite design considerations, a seepage plume, containing elevated concentrations of calcium and sulphate, has developed in the natural groundwater downstream of the facility, albeit currently well within the Alumbrera concession, due to the area’s complex structural geology. A series of pump back wells have been established to capture the seepage. The pump back wells will be augmented over the life of the mine in order to contain the plume within the concession and monitoring wells will be provided for the Vis Vis River. A groundwater flow and solute transport model completed in 2002 for the Vis Vis River was recalibrated in 2005 to include the latest results of all environmental studies and monitoring data. The results of the recalibration confirmed the need to operate the pump back system for several years after mine closure. Recalibration will be conducted periodically to help MAA ascertain the efficiency of its pumpback system and monitoring program over the life of the project.
     The other potentially significant environmental risk lies with the concentrate pipeline. This pipeline crosses areas of mountainous terrain, significant rivers, high rainfall and active agriculture. Any rupture of the pipeline poses an environmental risk from spillage of concentrate. Subsequently, control structures and river crossing protection have been, and continue to be, installed in order to minimize the risk of breakage and spillage, a program of geotechnical inspection has been implemented to monitor landslide risk areas, and routine physical surveillance of the pipeline route is carried out.
Reclamation and Closure
     Although YMAD has the right to retain certain project infrastructure, the UTE Agreement and 1997 Mining Lease Agreement between MAA and YMAD state that, on final termination of commercial production, MAA is legally responsible for reclamation and closure costs in its capacity as operator of the Alumbrera Mine. MAA is committed to stabilizing tailings and waste rock against potential acid generation and water pollution and, to this end, is conducting studies to verify that closure plans will successfully achieve these requirements. Other activities include contaminated land remediation, removal and stabilization of potentially acid generating road base material, securing pit safety and closure of infrastructure. The ultimate requirement is to achieve final landforms that do not require Alumbrera’s presence post closure.
     MAA has prepared an Interim Mine Closure Plan in response both to commitments in the EIR and to meet the requirements of those existing shareholders who are signatories to the Australian Minerals Council Code for Environmental Management. MAA’s closure planning is an ongoing process that is refined as the operations plans are revised and operational and monitoring data are evaluated. Closure costs are revised on an annual basis.
     Studies are ongoing to verify measures for controlling acid generation from waste rock and tailings materials at closure. Preliminary modelling of potential capping designs for the top surface of the waste rock dump

- 58 -


 

and the tailings dam was completed in January 2003. Field trials were then established to ascertain the actual standards for the final model. In addition, a local vegetation assessment program was initiated in 2004 to ascertain the feasibility of revegetation using native species on the final capping system. A re-calibration of the cover modelling was completed in 2006 based on the field information collected between October 2003 and October 2005. No major changes to previous conclusions were indicated by the results of the field studies. Sources of suitable capping material within the mining lease have been identified in the Tampa Tampa area; studies to confirm material properties and volumes were carried out in 2007.
Bond-Posting
     MAA makes provisions for reclamation and closure in its life-of-mine plan and financial statements, however, MAA is not required to post a bond in connection with its reclamation and closure obligations and no cash provisions are being made.
Capital Costs
     The Alumbrera Mine was commissioned in 1998 after the expenditure of approximately $1.233 billion of project development capital. After additional capital expenditure of approximately $79 million in 1999, on-going annual sustaining and project capital has been expended since that time at a rate of approximately $26 million per fiscal year. Approximately $17.6 million was expended in fiscal 2005. Capital expenditures in 2005, 2006 and 2007 were approximately $17.6 million, $46.8 million and $66.6 million, including sustaining and expansion capital. Budgeted capital for 2008 is estimated at $73.5 million.
Taxes
     MAA is subject to taxation in the form of income tax and IVA tax, the latter of which is applicable to purchases of goods and services at a rate of 21%. Full reimbursements for IVA tax are available to exporting mining companies.
     The statutory tax rate of MAA is 30% as compared to the statutory tax rate of 35% for non-mining companies. This rate is protected under a fiscal stability regime which also provides for favoured treatment in terms of special deductions for interest paid on foreign loans.
     In December 2007, the Argentinean Government unilaterally decided to levy export duties on mining companies operating in the country, including MAA, contrary to a 1993 fiscal stability agreement guaranteeing no change to the tax regime for 30 years. In order to continue shipping concentrate produced at Alumbrera to foreign smelters, MAA has paid the 10 percent export retentions under protest. MAA has initiated appropriate legal actions seeking to have the imposition of the export duties reversed. Xstrata and Goldcorp have communicated their objections to the Government’s action to President Fernandez de Kirchner and other Government officials.
Production Estimates
     The Alumbrera operation is expected to draw the majority of its economic value from the sale of copper and gold in concentrate. In addition, a doré containing gold and silver is produced on-site. Production is derived from ore mined at the Alumbrera Mine. The total remaining scheduled ore to be mined and processed, and the gold and copper output, are approximately 355 million tonnes, approximately 3.7 million ounces of gold and approximately 1.25 million tonnes of copper, respectively, over a period of approximately 10 years (100% basis). Production in 2008 is expected to be 527,000 ounces of payable gold and 171,000 tonnes of payable copper in concentrate (100% basis).
MARLIN MINE, GUATEMALA
     James S. Voorhees, P.Eng., formerly at Glamis, prepared an amended technical report dated November 11, 2003 entitled “Marlin Project Technical Report” (the “Marlin Report”). The following description of the Marlin Mine has been summarized, in part, from the Marlin Report and readers should consult the Marlin Report to obtain

- 59 -


 

further particulars regarding the Marlin Mine. The Marlin Report is available for review on the SEDAR website located at www.sedar.com under Glamis’ profile.
Project Description and Location
     The Marlin Mine is 100% owned by Montana Exploradora de Guatemala, S.A., a wholly-owned subsidiary of the Corporation. It is located in the northern section of the province of San Marcos in the municipality of San Miguel Ixtahuacan in western Guatemala, approximately 140 kilometres northwest of the capital, Guatemala City.
     The project consists of one 200 hectare exploitation concession and 10,000 hectares of exploration concession. Approximately 550 small properties have been purchased by the Corporation and steps are being taken to have title to surface rights registered in the Corporation’s name. All of the surface rights in the vicinity of the project area are believed to be privately controlled, but few of the owners possess written title to their land.
     Guatemalan mining law provides three types of licenses. The licenses are reconnaissance, exploration and exploitation. A reconnaissance license has a six month period of duration with the possibility of renewal for an additional six month period. This license can cover an area from 500 to 3,000 square kilometres and upon application it can be converted to an exploitation license. An exploration license covers an area of up to 100 square kilometres and has a term of three years with the possibility of extension for two additional two year terms. With each extension the surface area should be reduced by 50 percent. An exploitation license follows from the exploration license and has a 25 year term with an extension for a second 25 year term upon application. It covers a maximum of 20 square kilometres. Surface rights fees are payable with all types of licenses and a royalty of one percent is payable at the exploitation stage. The one percent royalty is shared equally between the state and the municipality where the project is situated.
     All environmental regulatory permits, licenses and authorizations required to carry out planned operations at the Marlin Mine have been obtained and are in good standing.
Accessibility, Climate, Local Resources, Infrastructure and Physiography
     The Marlin Mine is 25 kilometres by air west-southwest of the town of Huehuetenango or 300 kilometres by paved and gravel roads from Guatemala City. The Corporation has completed substantial improvements on roads leading into and roads within the project area.
     The climate is predominantly warm and dry with well defined wet and dry seasons. The majority of the 1,088 millimetres of annual rainfall occurs from April to October. The average yearly temperature in the area is approximately 25 degrees Celsius. Typically high temperatures are estimated to reach 40 degrees Celsius with low temperatures falling to 3 degrees Celsius.
     Power for the mine is obtained from a local power broker and is provided via a 27 kilometre power line built by the Corporation and dedicated to the Marlin Mine.
     Water is pumped from the Rio Tzala which flows from east to west in the valley adjacent to the site. Raw water for the project is pumped from two wells drilled directly in the river bed to a small containment pond and then distributed throughout the project as required. Potable water requirements are met by filtering and treating water.
     Topography at the project site is characterized by moderate to steep terrain with elevations ranging from 1,800 to 2,300 meters above sea level.
History
     The Marlin deposit was discovered in western Guatemala through regional grass-roots exploration in 1998 by Montana Exploradora, S.A. and was later purchased by Francisco Gold Corporation (“Francisco”) in 2000. In June 2002, Francisco shareholders approved a Plan of Arrangement between Glamis and Francisco that merged Francisco into Glamis and effectively transferred control of the Marlin Mine to Glamis. With the Guatamalan government’s issuance of environmental permits and the key exploitation license, construction on the project commenced early in 2004. In the second quarter of 2004, the Glamis board increased the original development budget from $120 million to $140 million to

- 60 -


 

incorporate additional capacity and reflect the increased costs of construction materials. Mill capacity expanded by more than 20 percent to 5,000 tonnes per day.
Geological Setting
     The Marlin district is located 15 to 20 kilometres south of the Cuilco-Chixoy-Polichic Fault, a major sinistral transform fault that separates the North American and Central American cratons. Tertiary movement is documented to be over 150 kilometres. The Marlin deposit is on a projection of a southern splay off of the Polochic fault system. The northern side of the Polochic fault system contains Mesozoic sediments. The south side of the Polochic fault contains Paleozoic schist, gneiss and granite and a series of Tertiary mafic volcanic eruptive events composed mostly of dacitic to andesitic tuff, lahar and andesitic to basaltic flows. These eruptive units are separated by thin beds of waterlain sediments composed mostly of shale and tuffaceous shale. These older volcanics are covered by thick eruptive units of Quaternary and recent dacitic volcanic ash. The Marlin deposit is located within the Tertiary mafic eruptive unit. The deposit trends in the same direction as the Polochic fault system.
     There are four major lithologic units present at the Marlin site: quaternary pyroclastic deposits, marlin andesites, tertiary voclaniclastic sequence and porphyric dykes.
Mineralization
     The mineralization lies on the eastern portion of a two kilometre east-west trending vein system, which is one of several parallel vein systems identified in the Marlin district. Most of the mineralization is in quartz veins and quartz vein stockwork within a Tertiary-age, dacitic, lithic tuff of the Marlin formation or within south-dipping tectonic breccia zones within the Tertiary Volcaniclastic Sequence. A small part of the mineralization is in calcite veins. Drilling to date has confirmed geological continuity along strike to include the Cochis and the Main Zone.
     The mineralization is consistent over an east-west distance of 1,500 metres and is up to 300 metres wide. A 150 by 75 metre on surface layer of weathered vein “rubble” overlies the main zone of Marlin. Clay alteration consisting of illite and kaolinite forms adjacent to the veins although not abundant. Post mineralization faults have produced sheer zones within the mineralization. Approximately 9 percent of the mineralization and 30 percent of the reserves found to date are oxide. The remaining is non-oxide. The non-oxide mineralization contains pyrite at concentrations of one to three percent.
Exploration
     In 2005, exploration activities concentrated on drilling two of the several veins which have been identified in the area of the Marlin Mine. A total of 27 holes were completed during the year at the West Vero zone located 0.7 kilometres south of the main Marlin zone. The Rosa vein was also drilled from the underground mine. Additionally, in-fill drilling at the La Hamaca deposit located 3 kilometres north of Marlin allowed for the conversion of 152,000 ounces of gold resources to reserves. In 2006, $5 million is budgeted for exploration at Marlin and other regional sites and is expected to include continued drilling at West Vero and Rosa, as well as initial testing of other vein targets on the property.
     In 2006, exploration activities concentrated on continued drilling of the West Vero and Agel areas adjacent to the Marlin Mine. A total of 37 holes were completed during the year at the West Vero and Agel zones. Some infill drilling was also carried out at the La Hamaca deposit.
     In 2007, exploration focused on definition of additional reserves in the Marlin West exention zone, conversion of West Vero zone resources to reserves and advancement of the exploration drift towards the Cora; zone, a satellite occurrence located one kilometre north of Marlin. During the year, a total of 24 holes were drilled for a total of 11,410 metres at West Marlin, 21 holes were drilled for a total of 7,647 metres at West Vero and 187 metres of underground drift development towards Coral was completed.
Drilling
     The Marlin Mine has been drilled nearly continuously since Francisco discovered the property and began drilling in 2001. Francisco completed 72 core holes totalling 7,606 metres. The drilling was concentrated around the outcrop of gold mineralization and its extension into the subsurface. The average drill-hole depth is 106 metres. After purchasing the

- 61 -


 

property from Francisco in 2002, Glamis concentrated on expanding the mineralization down dip and along strike with a combination of 150 rotary, 119 rotary/core holes (rotary pre-collared) and 97 shallow holes drilled in the rubble zone.
     Rotary drilling was the primary source of sample collection in 2002. Shallow RZG holes were drilled evaluating the surficial “rubble zone” a regolith which contains higher than average grade mineralization. The average depth of these holes is 14 metres. Sample intervals of the RC drilling is 1.5 metres. During 2003, rotary drilling was primarily used to pre-collar core holes. The rotary holes were drilled to a point above the lower grade domain. Sample interval of the RC drilling is 1.5 metres.
     Glamis used core drilling predominantly to determine the geometry and grade of the high grade quartz vein. Holes are collared using H size core and reduce to N as drilling conditions dictate. Sample interval of the core drilling averages 1.56 metres and varies from a minimum of 0.01 metres to 6.09 metres.
     As of December 31, 2007, the Corporation had drilled and received analytical assay data on 742 drill holes (reverse circulation and core) totalling 165,043 metres.
Sampling and Analysis
     Rotary samples collected from 4 3/4 inch, face-sampling, hammer-drilled reverse circulation holes are initially collected in a five-gallon bucket. The weight is then recorded and the sample placed into the hopper of a Gilson splitter. The process is repeated until the entire 1.5 metre sample is collected. The total weight is recorded on the sample sheet along with the sample identification and the time of day collected. Weights are only recorded for the dry portion of the drill hole. The Gilson splitter is set to split the sample into two halves, one half is retained and the other half is wasted. The remaining 50 percent is placed into the hopper again and another 50 percent split is made. The two samples are placed into pre-labeled plastic sample bags, one for assay and the other is stored. An air hose and nozzle is provided for blowing out the Gilson splitter, pan and buckets. A geologist is assigned to the rotary rig to supervise sample collection and log geology.
     The diamond drill core is collected and placed in wooden core boxes made locally on site. The core is washed to obtain a clean surface for geologic and geotechnical logging and placed in a covered logging facility. All core is photographed on print film. Core is sawn longitudinally with a diamond saw and half the core, on a nominal 1.5 metre interval broken at lithologic boundaries, is placed in a pre-labeled plastic bag. The other core holes are shipped to Chemex’s Hermosillo, Mexico laboratory for preparation. After preparation, the samples were shipped for assaying to either Rocky Mountain Geochemical’s laboratory in Reno, Nevada or Chemex Labs in Vancouver, British Columbia. Since June 2002, when Glamis began the second drilling program, splits from the core holes are shipped to a facility operated by Inspectorate’s laboratory in Sparks, Nevada for assay. Unused core from both drilling campaigns is available for inspection on site.
     Inspectorate uses their rock sample preparation on the Marlin samples. Thoroughly dried samples are reduced to greater than 80 percent passing 10 mesh using a two stage crushing procedure, jaw and roll mill. After homogenization, a 300 gram split is obtained using a Jones riffle splitter. The spit is further reduced to greater than 90 percent passing 150 mesh. Clean sand is employed in pulverization between all samples. The sand then is inserted into the sample stream one per batch where it is reported as a blank sample.
     Gold and silver is estimated for each sample using fire assay. Samples that exceed three grams per tonne of gold and 200 grams per tonne of silver are automatically submitted for fire assay-gravimetric finish. If geologists identify visible gold in the core, the sample is submitted for 5 assay tonne analysis.
     Bulk density determination was performed on 92 core samples. The distribution density samples within the mineralized area is sufficient for resource estimation.
     Although the number of quartz determinations appears low, the confidence interval at 95 percent is an acceptable 3 percent. The number of determinations in the rubble zone is also low but the zone only contains 300,000 tonnes.

- 62 -


 

Security of Samples
     Both independent laboratories used in the Marlin Mine exercise quality control in the form of duplicates, standard reference materials and blanks.
     Glamis established a limited QA/QC program focused on coarse reject and pulp reject checks. A frequency of 1 in 20 pulps is systematically submitted to the check lab (Chemex Labs, Nevada) for gold and silver analysis. Coarse rejects are also submitted to the check lab.
     Samples analyzed at Inspectorate and Chemex were paired and examined on scatterplots. In general, the check and primary labs agree within an overall average of less than 5 percent.
Mineral Reserve and Mineral Resource Estimates
     The following table sets forth the estimated Mineral Reserves for the Marlin Mine as of December 31, 2007:
Proven and Probable Mineral Reserves (1)(2)(3)(4)
                                         
    Grade   Contained Metal
Category   Tonnes   Gold   Silver   Gold   Silver
    (millions)   (grams per tonne)   (grams per tonne)   (millions of   (millions of
                            ounces)   ounces)
Proven
    4.10       5.61       152.8       0.74       20.1  
Probable
    11.46       4.11       98.1       1.51       36.1  
 
                                       
Proven + Probable
    15.56       4.50       112.5       2.25       56.3  
 
                                       
 
(1)   The Mineral Reserves for the Marlin Mine set out in the table above have been estimated by Michael G. Hester, FAusIMM, B.Sc., M.S., Independent Mining Consultants, Inc., who is a qualified person under NI 43-101.
 
(2)   Based on a gold price of $550 per ounce and a silver price of $10.00 per ounce.
 
(3)   The estimated metallurgical recovery rate is 92% for gold and 65% for silver.
 
(4)   Numbers may not add up due to rounding
     The following table sets forth the estimated Mineral Resources for the Marlin Mine as of December 31, 2007:
Measured, Indicated and Inferred Mineral Resources (1)(2)(3)
                                         
            Grade   Contained Metal
Category   Tonnes   Gold   Silver   Gold   Silver
    (millions)   (grams per tonne)   (grams per tonne)   (millions of   (millions of
                            ounces)   ounces)
Measured
    0.70       1.67       44.4       0.04       1.0  
Indicated
    2.21       1.45       47.5       0.10       3.4  
 
                                       
Measured + Indicated
    2.91       1.50       46.8       0.14       4.4  
 
                                       
Inferred
    2.21       4.06       146.7       0.29       10.4  
 
(1)   The Mineral Resources for the Marlin Mine set out in the table above have been estimated by Michael G. Hester, FAusIMM, B.Sc., M.S., Independent Mining Consultants, Inc., who is a qualified person under NI 43-101.
 
(2)   Based on a gold price of $650 per ounce and a silver price of $13.00 per ounce.
 
(3)   Numbers may not add up due to rounding.
Operations
     The Marlin Mine has both conventional open pit mining operations will 11 cubic metre loaders and 90 tonne trucks for moving the ore, and underground mining operations which employ five cubic metre loaders and 30 tonne trucks for ore haulage. Support equipment includes blasthole drills, drilling/bolting machines, track dozers, motor graders and water trucks to maintain the road surfaces, dumps and operating benches.

- 63 -


 

     The mill is designed to treat a nominal 1.82 million tonnes per year of ore. Ore is fed through a crusher prior to being introduced into the grinding circuit. Milling is conducted in a semi-autogenous grinding mill/ball mill circuit. The pulp produced by the milling is subjected to tank leaching with cyanide. After leaching the ores in the large tanks, the pulp is “washed” in a series of settling units (counter-current decantation). This effectively produces two products: a clear gold and silver bearing solution and also a pulp without precious metal values. The gold and silver solution is sent to the refinery where the metals are precipitated out of solution through the addition of zinc. This precipitate is filtered and smelted to produce doré bars.
     The Marlin Mine commenced production in December 2005. In 2006, the first year of production, the Marlin Mine produced 160,900 ounces of gold and 1,598,400 ounces of silver. In 2007, the Marlin Mine produced 227,200 ounces of gold and 2,837,300 ounces of silver at a total cash cost of $144 per ounce (by-product) and $253 per ounce (co-product). The Corporation expects production from the Marlin Mine through to 2015.
SAN MARTIN MINE, HONDURAS (non-material property)
     The Corporation acquired the San Martin Mine in connection with the Glamis Acquisition. The San Martin Mine is situated in Central Honduras, approximately 90 kilometres north of the capital city of Tegucigalpa, Honduras. The property consists of 14,100 hectares of land around the Rosa and Palo Alto deposits. The San Martin Mine is a conventional open pit, heap leach operation, designed for low-cost production. Two separate mineralized zones make up the San Martin deposit. The San Martin Mine commenced commercial production in 2001. In 2007, gold production from the San Martin Mine amounted to 45,300 ounces of gold at a total cash cost of $479 per ounce. Mining was completed at San Martin in late 2007 and reclamation and closure operations began. Releaching and rinsing of the heaps, recontouring and revegetation will be carried out over the next few years to comply with closure requirements and restore the property to commercial agricultural use.
PUEBLO VIEJO PROJECT, DOMINICAN REPUBLIC
     The following description of the Pueblo Viejo Project has largely been summarized from the Pueblo Viejo Feasibility Study Update dated December 2007 (the “Pueblo Viejo Feasibility Study”) which was prepared by Pueblo Viejo Dominicana Corporation (“PVDC”) and its consultants: Fluor (general plant site and infrastructure); Hatch (pressure oxidation and oxygen plant); SNC-Lavalin (power and transmission lines); NCL S.A. (mining studies); and BGC Engineering (geotechnical). The Pueblo Viejo Feasibility Study is an update to a feasibility study prepared for Place Dome Inc. in 2005. The technical disclosure in this annual information form with respect to the Pueblo Viejo Project has not been supported by a technical report prepared in accordance with NI 43-101. The technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed.
Property Description and Location
     The Pueblo Viejo Project is located in the central part of the Dominican Republic on the Caribbean island of Hispaniola in the province of Sanchez Ramirez. The project is 15 kilometres west of the provincial capital of Cotui and approximately 100 kilometres northwest of the national capital of Santo Domingo. The Pueblo Viejo Project is situated on the Montenegro Fiscal Reserve which covers an area of 4,880 hectares.
     The central region of the Dominican Republic is dominated by the Cordillera Central mountain range, which runs from the Haitian border in the east to the Caribbean Sea in the south. The Pueblo Viejo Project is located at the head of the Arroyo Margajita Valley in the eastern portion of the Cordillera Central where local topography ranges from 565 metres at Loma Cuaba to approximately 65 metres at the Hatillo Reservoir. The Arroyo Margajita Valley is orientated east-west, approximately 1 kilometre in width, and confined by a series of hills with an average elevation of 300 metres above sea level. The site is characterized by rugged and hilly terrain covered with subtropical wet forest and scrub cover. Forest capacity is limited by slope, topography, and soil movement.
     Access to the Pueblo Viejo Project from Santo Domingo is by a four lane, paved highway (Autopista

- 64 -


 

Duarte) that is the main route between Santo Domingo and the second largest city, Santiago. This highway connects to a single lane, secondary Highway #17 at the town of Piedra Blanca, approximately 78 kilometres from Santo Domingo. This secondary highway is a two lane, paved highway that passes through the towns of Piedra Blanca and Maimón on the way to Cotui. The gatehouse for the mine is 22 kilometres from Piedra Blanca.
     The main port facility in the Dominican Republic is Haina in Santo Domingo. Other port facilities are located at Puerto Plata, Boca Chica and San Pedro de Macoris.
     The Pueblo Viejo Project site has been a non-operating gold mine since June 1999. It currently consists of several mine site components including two old tailings impoundments (Las Lagunas and Mejita), two main pit areas (Monte Negro and Moore), and several smaller pit areas and mine rock piles. There are no deep depressions or large lakes associated with the pits. Small stockpiles are distributed irregularly throughout the pit areas, and larger piles are found on the periphery of the larger pits. Infrastructure still in operation includes water supply, power station, housing, recreational facilities, and two acid drainage treatment plants (only one is working, as of December 2007). There are also a significant number of abandoned structures.
History
     The earliest mining records at Pueblo Viejo date from 1505, although Spanish explorers encountered Arawak Indians actively mining the deposits in the late 1400s. The Spanish exploited the deposits until 1525, when the mine was abandoned in favour of newly discovered deposits on the American mainland.
     During the 1960s, several companies inspected the property but no serious exploration was conducted until Rosario Resources Corporation of New York became interested in 1969. Although exploration was at first focused on sulphides, exploration discovered an oxide deposit of significant tonnage and gold grade.
     In 1972, Rosario Dominicana S.A. (40% Rosario resources, 40% Simplot Industries, and 20% Dominican Republic Central Bank) was incorporated. Construction started in 1973 and open pit mining of the oxide deposits started in the Moore area in 1975. In 1979, the Central Bank purchased all foreign-held shares in the mine.
     Gold and silver production from oxide, transitional, and sulphide ores occurred from 1975 to 1999. Production over that period totalled 5.5 million ounces of gold and 25.2 million ounces of silver. The oxide ore was effectively mined out in 1992 and a carbon-in-leach (“CIL”) plant was installed to treat the transitional ore. Depletion of the transitional ore occurred in 1997 and sulphide ore was processed with low recoveries until closure in June 1999.
     Lacking funds and technology to process the sulphide ore, Rosario attempted two bidding processes (in 1992 and 1996) to joint venture the property. Both attempts (1992 and 1996) to privatize/joint venture the property failed.
     In November 1996, Rosario Dominicana selected Salomon Brothers (Salomon Smith Barney) to coordinate a process to find a strategic partner to rehabilitate the operation and to determine the best technology to economically exploit the sulphide resource. Three companies were involved in the privatization process: GENEL JV, Mount Isa Mines (“MIM”), and Newmont. The privatization process was never completed but each of the three companies conducted work on the property for their evaluations.
     The GENEL JV was formed in 1996 as a 50:50 joint venture between El Dorado Gold Corporation and Gencor Inc. (later Gold Fields Inc.) to pursue their common interest in Pueblo Viejo. The GENEL JV expended $6 million between 1996 and 1999 in studying the project and advancing the privatization process. Studies included diamond drilling, developing a new geological model, mining studies, evaluation of refractory ore milling technologies, socioeconomic evaluation and financial analysis.
     MIM also conducted a due diligence program in conjunction with their evaluation of Pueblo Viejo in the privatization process. MIM proposed to carry out a pilot plant and use ultra-fine grinding/ferric sulphate leaching.
     Newmont had proposed to carry out a pilot plant for ore roasting/bioheap oxidation. Newmont collected

- 65 -


 

samples for analysis, but no results are available.
     During the year 2000, the Dominican Republic invited international bids for the leasing and mineral exploitation of the Pueblo Viejo sulphide deposits. Placer Dome Inc. participated in the bid process and on July 2, 2001, its subsidiary Placer Dome America Holding Corporation presented a Technical and Financial Offer to the Dominican Republic committee. PVDC (then known as Placer Dome Dominicana Corporation), an affiliate of Placer Dome America Holding Corporation, was awarded the bid and the parties signed a Letter of Intent on August 4, 2001, pursuant to which the parties negotiated a special lease agreement (the “SLA”) for the Montenegro Fiscal Reserve. The SLA was subsequently ratified by the Dominican National Congress, was published in the Official Gazette of the Dominican Republic on May 21, 2003, and became effective on July 29, 2003 (the “Approval Date”). PVDC is a Barbados corporation that is legally registered in the Dominican Republic with Dirección General de Impuestos Internos.
     In September 2005, PVDC completed a Feasibility Study on the Pueblo Viejo Project. An Environmental Impact Assessment (the “EIA”) for the mine was completed in late 2005 and presented to the Dominican State in November 2005. Approval of the EIA was received in December 2006 from the Ministry of Environment.
     However, in February 2006, Barrick Gold Corporation acquired Placer Dome Inc. and in May 2006 completed the process of merging the companies. At the same time, Barrick sold a 40% stake in the Pueblo Viejo Project to Goldcorp Inc. Following the acquisition of Placer by Barrick, Barrick decided to engage Fluor, Hatch and SNC-Lavalin to review and update the 2005 Feasibility Study for Pueblo Viejo Project. Fluor was given the responsibility to review the process plant and infrastructure as well as compile the entire updated Capital Expenditure estimate. Hatch was awarded the pressure oxidation and oxygen plant review. SNC-Lavalin was charged with the power plant and transmission line review and update. The combined review and update of the 2005 Feasibility Study for the Pueblo Viejo Project continued through 2007 and resulted in the Pueblo Viejo Feasibility Study. In conjunction with the preparation of the Pueblo Viejo Feasibility Study, the Pueblo Viejo Project EIA was updated in September 2007. PVDC anticipates that a second update will be filed by the end of October 2008.
     On February 26, 2008, PVDC gave Project Notice to the Government of the Dominican Republic pursuant to the SLA and delivered the Pueblo Viejo Feasibility Study to the Government.
Special Lease Agreement
     The SLA between the Dominican State and PVDC governs the development and operation of the Pueblo Viejo Project. This agreement was approved by the Congress of the Dominican Republic on July 29, 2003. The SLA provides PVDC with the right to operate the Pueblo Viejo Project for a 25 year period commencing when PVDC gives Project Notice. PVDC has the right to automatically renew the term of the lease for an additional 25 years at its sole option (50 years in total). The agreement provides for another 25 year extension with mutual agreement between both parties (75 years in total).
Under the SLA, PVDC is obligated to make the following payments to the Dominican Republic: certain fixed payments due upon achieving certain milestones; a Net Smelter Return Royalty; a Net Profits Interest; a tax on income, and a withholding tax on interest paid on loans. In addition, an Environmental Reserve Fund to be held in an offshore escrow account is to be funded during operations until the escrowed funds are adequate to discharge PVDC’s closure reclamation obligations.
     Excluding exchange commissions, PVDC is to be exempt from all forms of taxes, permits, licenses, fees and duties, sales taxes, gross revenue taxes, value-added taxes (Impuesto a la Transferencia de Bienes Industrializados y Servicios), customs export duties and excise taxes, on all goods, services and rights produced, sold or leased that relate to the activities in connection with the construction, operations, and closure of the Leased Properties.
     The Dominican State will, at its sole cost and expense, remediate and rehabilitate, or otherwise mitigate all historic environmental matters. However, upon PVDC giving the Dominican State a Project Notice, PVDC shall

- 66 -


 

assume the responsibilities for all historic environmental matters within the boundaries of the “Development Areas” designated in the Project Feasibility Study. In addition, the Dominican State shall, in compliance with the applicable Environmental and Social Guidelines and Policies, and at its sole cost and expense, relocate and pay all indemnification and other compensation due to certain persons with valid claims to land within the Montenegro Fiscal Reserve.
Geological Setting and Mineralization
     The Pueblo Viejo precious and base metal deposit consists of high sulphidation or acid sulphate epithermal gold, silver, copper, and zinc mineralization that was formed during the Cretaceous Age island arc volcanism. The two main areas of alteration and mineralization are the Monte Negro and Moore deposits.
     Pueblo Viejo is situated in the Los Ranchos Formation, a series of volcanic and volcaniclastic rocks that extend across the eastern half of the Dominican Republic, generally striking northwest and dipping southwest. The Pueblo Viejo Member of the Los Ranchos is a restricted sedimentary basin approximately 3 kilometres north-south by 2 kilometres east-west. The basin is filled with lacustrine deposits that range from coarse conglomerate deposited at the edge of the basin, to thinly bedded, carbonaceous sandstone, siltstone, and mudstone deposited further from the paleo-shoreline. To the south, the Pueblo Viejo Member is unconformably overlain by the Hatillo Limestone Formation by means of a low angle, southwest dipping thrust fault.
     The Moore deposit is located at the eastern margin of the Pueblo Viejo member sedimentary basin. Stratigraphy consists of finely bedded carbonaceous siltstone and mudstone (PV sediments) overlying horizons of spilite (basaltic-andesite flows), volcanic sandstone, and fragmental volcaniclastics. The Monte Negro deposit is located at the northwestern margin of the sedimentary basin. Stratigraphy consists of interbedded carbonaceous sediments ranging from siltstone to conglomerate that are interlayered with volcaniclastic flows. Metallic mineralization in the deposit areas is primarily pyrite with lesser amounts of sphalerite and enargite. Pyrite mineralization occurs as disseminations, layers, replacements, and veins. Sphalerite and enargite mineralization is primarily in veins, but disseminated sphalerite has been noted in core.
     Studies have determined that there were two stages of advanced argillic alteration, both associated with precious metal mineralization. A third stage of mineralization occurred when hydro-fracturing of the silica cap produced pyrite-sphalerite-enargite (Stage III) veins with silicified haloes. Individual Stage III veins have a mean width of 4 centimetres and are typically less than 10 centimetres wide. Stage III veins contain the highest precious and base metal values and are more widely distributed in the upper portions of the deposits. The most common vein minerals are pyrite, sphalerite, and quartz with lesser amounts of enargite, barite, and pyrophyllite.
     Gold is intimately associated with pyrite veins, disseminations, replacements, and layers within the zones of advanced argillic alteration. Gold values generally are the highest in zones of silicification or strong quartz-pyrophyllite alteration. These gold-bearing alteration zones are widely distributed in the upper parts of the deposits and tend to funnel into narrow feeder zones. Stage III sulphide veins also have higher gold values than replacement-style mineralization. The most common form of gold is sub-microscopic gold within pyrite, where it is present as both solid solution within the crystal structure of the pyrite and as colloidal-size microinclusions (<0.5 microns). The proportions of the different forms and carriers of gold vary significantly throughout the Moore and Monte Negro deposits. Generally, the majority of gold is found as sub-microscopic gold in microcrystalline, disseminated, or porous pyrite.
     Of all the elements, assays for silver consistently have the strongest correlation with gold. Silver has a strong association with Stage III sulphide veins where it occurs as the minerals Ag, Sb-sulphides (pyrargyrite), Ag-tellurides (hessite), Au, Ag-tellurides (sylvanite, petzite), and Ag-bearing tetrahedrite. The majority of the zinc occurs as sphalerite; primarily in Stage III sulphide veins and secondary as disseminations. The majority of copper occurs as enargite hosted in Stage III sulphide veins. Only trace amounts of chalcocite and chalcopyrite have been recorded.
     Many rock types based on both lithological and structural domain boundaries were used in the geological block model. However, rock types were divided into five different categories based on metallurgical properties.

- 67 -


 

Drilling and Verification of Data
     Drilling campaigns have been conducted by most of the participating companies in the Pueblo Viejo Project over the years, including Rosario, GENEL JV, MIM, PDDC and PVDC.
Prior Drilling Campaigns
     Rosario employed several drilling methods during the exploration and development phases at Pueblo Viejo. Geological information was recorded on paper log-forms or graphic logs for all core, RC, and percussion drill holes. Detailed geology logs are available for only the RS-series rotary holes. Assay intervals and results were handwritten onto separate paper forms. The combination of drill hole name and from-to assay intervals was used to identify the samples. Unique sample numbers were not used. No photos of the core were taken. These practices were common for the period in which the drilling was undertaken. The majority of the Rosario drill holes were vertical. Drill hole spacing ranges from 20 metres to 80 metres, with a nominal overall spacing of 50 metres. No down-hole surveys were performed. The type of instrumentation used for surveying collar locations is not documented. Core recoveries were reported to be approximately 50% in areas of mineralization and within silicified material. Poor drill core recovery in gold deposits is a common source of recovery-induced grade biases.
     In 1996, the GENEL JV drilled 20 holes at the Pueblo Viejo Project site, 11 in the Moore deposit and 9 in the Monte Negro deposit. Swiss-Boring was contracted to do the drilling using HQ core size. All holes were drilled at an angle. Down-hole surveys were performed but there is no record of the type of instruments used for the surveys. The GENEL JV used a GPS system to locate drill holes and to survey the existing pits.
     In late 1996 and into 1997, MIM drilled 31 holes at the Pueblo Viejo Project site, 15 at the Moore deposit and 16 at the Monte Negro deposit. Geocivil was contracted to do the drilling. Core size was HQ with occasional reductions to NQ as necessary to complete the holes. Five holes were vertical and 26 were drilled at an angle. Apparently no down-hole surveys were performed on these holes. There is no record of instrumentation used to survey collar locations. Original data documentation is not available from this drilling campaign for database confirmation, thus, the laboratory that analyzed the samples or the methodology used cannot be confirmed. Source certificates for confirmation of the database results are not available. Drill logs were entered into Excel, and assays presented as printouts.
     Surveying methods for the GENEL JV holes are considered by PVDC to be of an accuracy suitable to support resource estimates. The accuracy of collar and down-hole surveys for Rosario and MIM drill holes cannot be confirmed but is assumed by PVDC to be accurate enough to support resource estimates.
     Placer Dome Dominicana Corporation (“PDDC”) completed 3,039 m of core drilling in 18 holes during 2002 and 15,424 metres of core drilling in 111 holes during 2004. The drilling was a part of the resource confirmation program conducted by the PDDC geological team. The drilling was completed using thin-walled NQ rods that produce NTW (57 millimetres) core. All but one of the core holes drilled by PDDC were angle-holes, allowing for a better representation of the vertical sulphide veining. PDDC drilled with oriented core to calculate the true orientations of bedding, veining, and faulting in the deposit areas. A down-hole crayon-marking system was used to mark the bottom of the core. The system proved to be successful, and down-hole structures showed similar orientations to those measured at the surface. PDDC was the only company to attempt oriented core drilling at Pueblo Viejo. All core samples were sawn in half, with half sent for analysis and the other half kept as a record at the site. Samples were normally collected at 2 metre intervals. Sample intervals were shortened at lithological, structural, or alteration contacts.
PVDC Drilling Campaign
     PVDC completed 10,015 metres of core drilling in 53 holes during 2006 as part of a resource confirmation program. The following criteria were set for selecting drill targets:
    Six holes for 1,506 metres to identify mineralization along high-grade trends and potential mineralization with high priority targets near the pits.
 
    Forty-two holes for 7,293 metres to test open mineralization along pit edges and to define inferred

- 68 -


 

      resources along the pit edges.
 
    Five holes for 1,216 metres were drilled to test the pit bottom.
 
    All drill holes were angle holes to optimize the information cut.
     The drilling was completed using thin-walled NQ rods that produce NTW (57 millimetres) core. Some holes were started on PQ and some holes were reduced to 42 millimetres. All the core holes drilled by PVDC were angle holes, allowing for a better representation of the vertical sulphide veining. All core samples were sawn in half, with half sent for analysis and the other half kept as a record at the site. Samples were normally collected at 2 metre intervals. Sample intervals were shortened at lithological, structural, or alteration contacts. Drill pads were marked with wooden pegs after using GPS to find the pre-selected locations. In areas where the GPS signal was weak, the Rosario bench map and IKONOS satellite images were used. Holes were aligned using foresite and backsite pegs.
     Two or three down-hole surveys were completed in all PVDC drill holes using a Sperry-Sun single-shot survey camera. Surveys were spaced every 60 metres to 75 metres and deviation of the drill holes was minimal. Azimuth readings were corrected to true north by subtracting 10 degrees. After completion, a wooden post marked with the drill hole number was placed in the collar of every hole. Final drill hole locations were then surveyed in UTM coordinates by a professional surveyor, translated into the mine coordinate system (truncated UTM), and entered into the drill hole database.
     Geologic information generated by the PVDC 2006 drill program was imported directly into the Project database and imported into Vulcan to generate sections for resources modelling. Assays were incorporated in the database electronically. The following geological data were recorded on the geology log with reference to assay intervals:
    Lithology – type, interval in metres.
 
    Assay – interval, sample number (interval normally 2 metres but intervals were also cut at lithology changes or major structures).
 
    Oxidation – oxide, transitional, or sulphide facies.
 
    Alteration – type, intensity.
 
    Veining – type, estimated percentage.
 
    Disseminated Sulphides – type, percentage.
     Geotechnical collection was done using the same software to capture directly the information. Most of the geotechnical information generated by the program was collected and recorded by technicians under the supervision of a geologist. The data were recorded on custom-made forms and later entered into Excel spreadsheets. The following geotechnical data were recorded with reference to drill intervals:
    Drill interval – From-To, and length in metres of block-to-block intervals; 1.5 metres under normal drilling conditions.
 
    Core recovery.
 
    Sum of core pieces greater than 10 centimetres – RQD calculated by Excel.
 
    Fracture count – number of natural fractures per interval.
 
    Oriented – whether or not drill interval was successfully marked with orienting crayon.
Validation of Historic Drilling Information
     Validation of the historical drilling information was addressed as part of the 2005 Pueblo Viejo Technical Report. To evaluate the possible biases between drill types, and to validate the historical Rosario and MIM drilling information, two tests were performed at that time. Those tests were performed before the 2006 PVDC drilling. The pseudo-twin assay pair test compared assays from PVDC and previous drilling programs. The second test was a cross section review.
     The pseudo-twin assay pair test compared results from nearby holes by searching for Rosario samples near the PVDC holes. Search radii were selected by PVDC to pair assays of different drilling campaigns to assess the similarity of assay grade distributions of the pairs. After examination, PVDC concluded the QQ plots indicate that

- 69 -


 

the Rosario and PVDC drilling campaigns reflect similar assay distributions.
     Declustered QQ plots were constructed and the conclusions made by PVDC were confirmed by a contractor. In grade ranges below 2 grams per tonne, Rosario drilling appears to be biased slightly high compared to PVDC drilling; however, above 2 grams per tonne and below 6 grams per tonne, the assays fit a line x = y reasonably well. Above 6 grams per tonne, Rosario drilling appears generally biased high, relative to PVDC drilling.
     The assays on cross sections were reviewed and the similarity of the MIM, GENEL JV, Rosario and PVDC drilling was assessed. In general, there is close agreement of the orientation, tenor, and thickness of mineralization between drilling campaigns. PVDC drill holes with prefix PD and GT were drilled preferentially across mineralization. Six Rosario drill holes are crossed by seven PVDC drill holes and indicate similar gold grade and thickness of mineralization. Collectively, the drill holes indicate a sharply inclined top of mineralization. The Rosario drill hole indicates similar grade and mineralization thickness when compared to the MIM and PVDC drill holes.
     Approximately 2.5% of the Rosario data have been verified against original documents. Extensive evaluations of the possible bias introduced by various drilling procedures have been undertaken by Fluor, PAH, PVDC, and AMEC. After reviewing the drill data, AMEC was of the opinion that the Rosario core, RC and some Rosario conventional rotary data (pre-1975 and some Rosario RS-series) are generally reliable. There may be some bias in the RC data but those holes have been individually evaluated and obvious problems have been eliminated. The risk involved in using those data is judged to be acceptable. Drilling types that have produced questionable results have been excluded from the database and were not used by PVDC in preparing the resource estimate.
     GENEL JV data have been verified against original documents and are believed to be reliable. MIM data have not been verified against original documents and there is some risk involved with using those data. AMEC compared those data to nearby PDDC data and found that the MIM holes indicated mineralized zones with very similar tenors and thicknesses as the PDDC and Rosario data. The risk involved with using the MIM data is considered acceptable. PDDC data have been verified against original documents and are believed to be reliable.
Sampling Method and Approach
     No information is available concerning the sampling strategies used by Rosario during their drilling programs. The record suggests that Rosario generally sampled core on 2 metre intervals with some samples based on lithology. RC holes were generally sampled on 2 metre intervals. This approach is appropriate for the style of mineralization and mining methods that will probably be used.
     GENEL JV sampled on 2 metre intervals. The core was split into thirds and one-third was used for the analytical sample. The remainder could be archived or split again for metallurgical test work. This approach is appropriate for the style of mineralization and mining methods that will probably be used.
     From the record, it appears that MIM samples were collected on 2 metre intervals with adjustments for lithological boundaries. There is no documentation of the approach.
     Core sampling procedures were described by PDDC in 2004. Sample intervals were normally 2 metre long but were shortened at lithological, structural, or major alteration contacts. Prior to marking the sample intervals, geotechnicians photographed and geotechnically logged the core, then a geologist quick-logged the core, marking all the geological contacts. Geotechnicians then marked the sample intervals and assigned sample numbers. After the sample intervals were marked, the geologist logged the core in detail and the core was sent for sampling where it was split into two halves using a core saw. PDDC procedures are consistent with the type of mineralization and the type of mining envisioned for the Pueblo Viejo Project.
     The 2006 PVDC diamond drilling core-sampling procedures were comparable to the procedure used by PDDC in their last drilling campaign. Geotechnical and geological descriptions were performed using comparable sets of data collection. The core was photographed. Sample intervals were normally 2 metre long but shortened according to the geology and mineralization when needed. Three-metre samples were used in the waste area.

- 70 -


 

Sample Preparation, Analyses and Security
Rosario
     The fire assay and other analytical procedures in use up to the time of the Stone & Webster (1992) study were reported to be of industry standard. No details are available regarding the sample preparation and analytical procedures used. It is only known that the samples were analyzed using the fire assaying technique for gold and silver, the LECO combustion furnace method for carbon and sulphur, and AA (atomic absorption) for copper and zinc. No details are available on crush sizes, sub-sample sizes, or final pulp sample weights used during sample preparation.
     For the sulphide drilling program which started in 1984, two assay labs were present at site, a mainline lab responsible for gold, silver, copper, zinc, and iron analyses, and a sulphide lab responsible for carbon and sulphur analyses. Sample preparation methods are not documented for this period of sample analysis.
     Security of the samples after removal from the hole is not documented.
GENEL JV
     GENEL JV samples were apparently prepared on site by GENEL JV personnel. This is not explicitly stated in the GENEL JV report but is inferred from the discussion in the report. A one-third split of the core was crushed to -10 mesh, homogenized by passing the sample through a Gilson splitter three times. The sample was then down-sized to about 400 grams using a Gilson splitter. This sample was then packaged and sent to Chemex Labs Ltd. in Vancouver, BC, Canada (Chemex) where presumably, the final pulverization was completed. In the GENEL JV report, the final pulp grain size is not stated.
     The samples were then assayed at Chemex for Au, Ag, Zn, Cu, S, and C. The procedures are not stated in the report. A 32 element ICP analysis (G-32 ICP) was performed on each sample.
     Security measures utilized by GENEL JV are not documented.
MIM
     No details are available on the sample preparation, analytical procedures, or security measures for the MIM samples.
     Core from Rosario, MIM, and GENEL JV drilling was previously stored in inadequate storage facilities where severe oxidation of the remaining core has rendered the core relatively useless.
PDDC
     During the 2002 and 2004 program, drill core was sawn in half with a diamond blade saw at site. All of the second half of the 2002 core was consumed in metallurgical testwork. The archived half of 2004 core was stored on site for future reference in suitable storage conditions. The other half was placed in plastic sample bags marked with the appropriate sample number and sealed with a numbered security tag (zap-strap). The manager of the drilling company drove the samples from the site to the airport unaccompanied by any PDDC employee. The core samples were sent to Vancouver using airfreight and were received by ALS. No record was kept of the state of the security tags when logged into ALS.
     Initial splitting of the core on site was the only aspect of sample preparation performed by employees of PDDC. The split samples were then sent to commercial laboratories for sample preparation and analysis.

- 71 -


 

PVDC
     The 2006 PVDC drill core was sawn in half with a diamond blade saw at site. The entire second half of core was kept for records and future metallurgical test work. The archived half of the core was stored on site for future reference in suitable storage conditions. The other half was placed in plastic sample bags marked with the appropriate sample number and sealed with a numbered security tag (zap-strap). The core samples were sent to Vancouver using airfreight and were received by ALS. Initial splitting of core on site was the only aspect of sample preparation performed by employees of PVDC. The split samples were then sent to commercial laboratories for sample preparation and analysis.
     The core samples were assayed for gold, silver, copper, and zinc. In addition to these elements, multi-element analysis was performed. Sulphur and carbon assays are in the process of being completed using LECO furnaces.
     Sampling by PVDC has been performed appropriately for the style of mineralization present at Pueblo Viejo. Sampling of the pre-PVDC samples may have been adequate but there is little in the way of documentation to confirm this. Sample preparation for the Rosario and MIM samples has not been documented.
     Preparation of samples from the PVDC drill programs used initial crush specifications less than that generally used for gold deposits. The 90th percentile relative error for 21 duplicate samples assayed is about 23% which is higher than is generally expected (15%) for pulp duplicates. This is a very small data set from which to draw conclusions but if it is representative of the whole, much of the relative error is probably related to sample preparation procedures. A similar review of duplicate samples analyzed by GENEL JV indicates that that program had a 90th percentile relative error of about 14% which is within the expected range.
QA/QC Procedures
     QA/QC procedures have varied significantly during the history of work at Pueblo Viejo. During the time of Rosario’s operation, QA/QC consisted of two batches of check assays sent to a second laboratory without duplicate, blank, or standard samples. Although the QA/QC was substandard relative to current industry practice, it must be viewed in its historical context and check assaying was the industry standard for QA/QC at that time.
     MIM sample data lack any QA/QC validation. The quality of those data is indeterminate. There is no reason to believe that there are any problems with those data but the quality cannot be directly evaluated. Comparison of the tenor and thickness of mineralized zones defined by the MIM data with tenor and thickness of mineralized zones defined by the PVDC and GENEL JV indicate that the grades are similar.
     PDDC relied on two standards and check assaying for QA/QC. No duplicate samples were analyzed, and the check analysis program included no certified reference materials or blank samples.
     The QA/QC procedure used for the 2006 PVDC drilling program consisted of the introduction of blanks, commercial standards for gold, and core duplicates into the sampling process.
    Each batch was submitted with 75 samples, of which 6 were QC control (2 blanks, 2 standards, and 2 core duplicates).
 
    The blanks were a local limestone, the same used during the Placer campaign.
 
    The standards were purchased from Rocklab of New Zealand and correspond to the gold range of the deposit. These standards were used for most of the year.
 
    Five custom, reference materials were prepared by PVDC using the mineralization from Pueblo Viejo. The gold grade range corresponds to the range of the Project.
 
    The core duplicates were also inserted approximately every thirtieth sample.
Mineral Processing and Metallurgical Testing
     The metallurgical history of the Pueblo Viejo Project has been summarized by Pincock, Allen & Holt (PAH). Defining an economic processing method for the sulphide phase of this Project has been challenged by the

- 72 -


 

high sulphur to gold ratio in mineralization and by the wide distribution of gold in various mineralogical facies, not easily concentrated with one metallurgical process. PAH identified 15 different metallurgical processes that were evaluated by various companies between 1973 and 2001.
     Following the award of the SLA, PVDC selected a fairly straightforward process based on pressure oxidation of the whole ore followed by CIL cyanidation for recovery of the gold and silver. One innovation, a hot cure on the slurry from the autoclave, is designed to reduce lime consumption by solid basic ferric sulphate in the cyanide leaching circuit, in favour of the neutralization of dissolved ferric sulphate in the liquid phase by limestone in the HDS circuit. Autoclaving of the whole ore entails greater capital and operating costs than treating a concentrate but the increment in operating cost is limited because of its dependence more on sulphur throughput rather than total solid throughput. The increment in gold recovery with whole ore pressure oxidation is significant, gold recoveries are projected to vary with ore type from 89.4% to 95.5%. These projections are supported by an extensive test program completed at SGS Lakefield in Peterborough. The SGS Lakefield program included a 10-day continuous autoclave and cyanidation pilot plant campaign. Further confirmation of the process design parameters was achieved with another continuous pressure oxidation pilot plant campaign conducted at the Barrick Technology Centre in Vancouver in July 2006.
Mineral Reserve and Resource Estimates
     The Mineral Reserve and Mineral Resource estimates disclosure in this annual information form with respect to the Pueblo Viejo Project are based on the Pueblo Viejo Feasibility Study Update dated December 2007 (the “Pueblo Viejo Feasibility Study”) which was prepared by Pueblo Viejo Dominicana Corporation (“PVDC”) and its consultants: Fluor (general plant site and infrastructure); Hatch (pressure oxidation and oxygen plant); SNC-Lavalin (power and transmission lines); NCL S.A. (mining studies); and BGC Engineering (geotechnical). The Pueblo Viejo Feasibility Study is an update to a feasibility study prepared for Place Dome Inc. in 2005. The technical disclosure, including the Mineral Reserve and Mineral Resource estimates, in this annual information form with respect to the Pueblo Viejo Project have not been supported by a technical report prepared in accordance with NI 43-101. A technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed.
     The following table sets forth the estimated Mineral Reserves for Goldcorp’s 40% interest in the Pueblo Viejo Project as of December 31, 2007:
Proven and Probable Mineral Reserves (1)(2)(3)(4)
                                                         
            Grade   Contained Metal
Category   Tonnes   Gold   Silver   Copper   Gold   Silver   Copper
    (millions)   (grams per   (grams per   (%)   (millions of   (millions of   (millions of
            tonne)   tonne)           ounces)   ounces)   pounds)
Proven
    4.50       3.39       18.9       0.10       0.49       2.7       10  
Probable
    81.16       2.88       14.6       0.09       7.53       36.4       145  
 
                                                       
Proven + Probable
    85.65       2.91       14.8       0.09       8.02       39.2       155  
 
                                                       
 
(1)   The Mineral Reserves for the Pueblo Viejo Project set out in the table above have not been supported by a technical report prepared in accordance with NI 43-101. A technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed.
 
(2)   Based on a gold price of $575 per ounce, a silver price of $10.75 per ounce, and a copper price of $2.00 per pound.
 
(3)   The estimated metallurgical recovery rate is 88% to 95% for gold and 86% to 89% for silver.
 
(4)   Numbers may not add up due to rounding.

- 73 -


 

     The following table sets forth the estimated gold, silver and copper Mineral Resources for Goldcorp’s 40% interest in the Pueblo Viejo Project as of December 31, 2007:
Measured, Indicated and Inferred Gold, Silver and Copper Mineral Resources (1)(2)(3)(4)
(excluding Proven and Probable Mineral Reserves)
                                                         
            Grade   Contained Metal
Category   Tonnes   Gold   Silver   Copper   Gold   Silver   Copper
    (millions)   (grams per   (grams per   (%)   (millions of   (millions of   (millions of
            tonne)   tonne)           ounces)   ounces)   pounds)
Measured
    0.50       2.67       7.0       0.04       0.04       0.1       1  
Indicated
    16.64       2.40       6.8       0.04       1.28       3.6       15  
 
                                                       
Measured + Indicated
    17.14       2.40       6.8       0.04       1.32       3.7       16  
 
                                                       
Inferred
    32.57       2.46       3.4       0.02       2.58       3.6       16  
 
(1)   The Mineral Resources for the Pueblo Viejo Project set out in the table above have not been supported by a technical report prepared in accordance with NI 43-101. A technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed.
 
(2)   Mineral Resources are not known with the same degree of certainty as Mineral Reserves and do not have demonstrated economic viability.
 
(3)   Based on a gold price of $650 per ounce, a silver price of $11.50 per ounce and a copper price of $2.25 per pound.
 
(4)   Numbers may not add up due to rounding
Measured, Indicated and Inferred Zinc Mineral Resources (1)(2)(3)(4)
(excluding Proven and Probable Mineral Reserves)
                         
            Grade   Contained Metal
Category   Tonnes   Zinc   Zinc
    (millions)   (%)   (millions of pounds)
Measured
    5.00       0.78       85  
Indicated
    94.43       0.55       1,149  
 
                       
Measured + Indicated
    99.43       0.56       1,234  
 
                       
Inferred
    32.57       0.02       13  
 
(1)   The Mineral Resources for the Pueblo Viejo Project set out in the table above have not been supported by a technical report prepared in accordance with NI 43-101. A technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed.
 
(2)   Mineral Resources are not known with the same degree of certainty as Mineral Reserves and do not have demonstrated economic viability.
 
(3)   Based on a 1.4 grams per tonne of gold cut-off grade.
 
(4)   Numbers may not add up due to rounding.
Mining Operations
     The Pueblo Viejo deposits are located in two major areas, the Monte Negro pit and the Moore pit. The process chosen to treat the Pueblo Viejo ore requires a significant amount of limestone slurry and lime. Three areas have been identified for limestone, the plant limestone deposit, the Los Quemados limestone deposit, and the Las Lagunas deposit. All limestone deposits are within 2 kilometres of the Moore pit.
     The first stage pit is located in the existing Monte Negro pit. There is no need for pre-stripping of this pit before operations start as the ore is already exposed. There is, however, a need for pre-stripping of the plant limestone quarry to provide access, and to produce aggregates needed for road construction. The access ramp east of the Moore pit will have to be developed during pre-production to provide access to the primary crushers.
     The pit stages were chosen to facilitate the early extraction of the most profitable ore. Elevated cut-off grades were also used for this purpose. A total of 80.1 million tonnes of low-grade material is stockpiled for re-processing at the end of the pit life.
     The pit wall slopes vary from 38 degrees to 50 degrees based on testwork and analysis completed by Piteau Associates in 2004. Bench height is 10 metres. Ramps were designed with a width of 26 metres and a gradient of 10%.

- 74 -


 

     Mining equipment consists of 34 haul trucks (135 t), 3 hydraulic excavators (15 m3), and 2 front-end loaders, 4 x 200 millimetre drills and other support equipment. The same equipment will work in the ore pits and the limestone quarry. The cost of quarrying the limestone used for processing has been allocated to the milling cost.
     Mine dewatering will be an ongoing expense. Most of the dewatering will be required from sumps within the pits after heavy rain. A program of dewatering wells and in-pit dewatering holes will also be required.
     The limestone reserves for Los Quemados have been estimated from limited drill information. Limited information is available for estimating the plant and Las Lagunas limestone reserves. Five drill holes were completed in the plant limestone quarry in early 2005. Analysis of the samples indicated that the limestone from the plant quarry is not suitable for processing into slurry and lime, but can be used for building roads and dams. The limestone reserves for each area were estimated in 2005 to total 77 million tonnes. The total amount of processing and construction limestone required for the mine life is 138 million tonnes. There are numerous limestone formations in the vicinity of Pueblo Viejo. A Diamond Drill Hole program being conducted by PVDC shows that limestone reserves are still available on site, and it is assumed that the difference between requirements and actual reserves (61 million tonnes) will be obtained from other limestone formations on the property itself. Early exploration results from an area adjacent to Las Lagunas (the Lagunas Extension) are positive and indicate that a large part of the difference can be obtained from this area.
     The limestone is required for the following purposes:
    Produce limestone slurry for use in the process
 
    Produce lime from a kiln for use in the process
 
    Produce aggregate for raising the tailings dam
 
    Produce aggregate for road maintenance
     The total average amount of limestone required from the quarries is 22,500 t/d.
     All waste rock from the Moore and Monte Negro pits will be hauled to the El Llagal tailings pond to minimize/stop the generation of acid rock drainage by submerging the waste rock under the tailings and water. An 8 kilolmetres road will have to be constructed to link the pit area to the tailings pond.
Processing/Metallurgy
     The Pueblo Viejo deposit consists of the Moore and Monte Negro ore bodies, where five metallurgical ore types have been identified and defined. The ore deposits are complex and pose a particular challenge in finding an economical process for gold and silver recovery. Most of the gold and silver in the ore are intimately associated, and mostly in solid solution, with the pyrite. As a result, chemical breakdown of the sulphide minerals, as well as removal of reactive and cyanide-consuming copper and zinc minerals, is required to achieve good gold and silver recoveries. Many chemical processing techniques were investigated, but only pressure oxidation of the whole ore followed by cyanidation of gold and silver in a CIL circuit produced satisfactory and optimum results. This process is energy intensive and its economic viability depends mainly on the availability of inexpensive and reliable power.
     Gold and silver production is projected to average approximately 1.0 M oz/a and 4.4 M oz/a respectively during the first five years of operation and 0.73 M oz/a and 3.1 M oz/a respectively for the entire mine life. Approximately 6,150 t/a (13.5 M lb) of by-product copper metal will be produced from the copper recovery plant. Gold recovery is projected to vary between 87% and 95%, but will average 91.5%. Silver recovery is estimated to average 87% over the entire mine life. Average copper recovery is estimated at 88%.
     The autoclave circuit will be designed to oxidize initially an average of 1,200 t/d of sulphur, with 1,600 t/d capacity after expansion. As a result of the varying sulphur content of the mill feed, the processing rate will range from 12,000 t/d (high sulphur) to 18,000 t/d (low sulphur) to 24,000 t/d (after expansion). The rest of the process plant will be designed to handle the maximum process throughput.

- 75 -


 

     The proposed process plant will consist of the following major unit operations:
    Run-of-mine (ROM) crushing
 
    Grinding (SAG and ball milling)
 
    Pebble crushing
 
    Pressure oxidation
 
    Hot curing
 
    Counter current decantation (CCD) thickener washing
 
    Ferric precipitation
 
    Copper recovery
 
    High density sludge neutralization
 
    Silver enhancement, lime boil
 
    Oxidized slurry cooling
 
    Carbon-in-leach (CIL)
 
    Refining
 
    Cyanide destruction
 
    Tailings disposal
     In the milling process, the ore is ground to its optimum grind of 80% passing 80 µm, and pressure-oxidized in autoclaves for 60 to 75 minutes at a temperature of 230 degrees Celsius and a pressure of 3,450 kPa. The autoclave product is discharged to a flash tank where heat is released, cooling the slurry to the 105 degrees Celsius level. It will then gravity feed to the hot cure circuit where the slurry temperature is maintained at 105 to 99 degrees Celsius for 12 hours to dissolve any basic ferric sulphate that formed during autoclaving.
     The hot-cured slurry is pumped to the three-stage CCD washing circuit to remove more than 99% of the sulphuric acid and the dissolved metal sulphates from the slurry. The thickener underflow is pumped to the lime boil preheat vessel where it is reheated to 95 degrees Celsius using steam from the autoclave flash tank.
     The lime boil breaks down the jarosites to liberate the silver. The lime boil slurry is cooled to 40 degrees Celsius in a slurry cooling tower and pumped to the CIL circuit where gold and silver are extracted using cyanide and activated carbon.
     The overflow (acidic liquor) from CCD Thickener #1 is split to the autoclave flash steam quench vessels and to the iron precipitation circuit. The two streams are then recombined in the iron precipitation tanks where limestone is added to reduce the acidity and precipitate iron. The iron slurry flows to the iron precipitation settler where the iron sludge is separated and sent to the HDS circuit. The iron-free solution is treated in the copper recovery plant to recover the copper in solution. In this plant, H2S is added to precipitate the copper as CuS. The precipitate is thickened and filtered to produce market-grade copper concentrate. The copper-free solution from the copper recovery plant is treated with limestone and lime to neutralize the remaining acid and precipitate the other metal sulphates to form high density sludge (HDS). The sludge is thickened in the HDS thickener and pumped to the tailings pond along with the CIL tailings. The thickener overflow is recycled to the CCD wash circuit as dilution water.
     Loaded carbon from the CIL circuit is forwarded to the refinery for acid washing and elution. Gold and silver are recovered from the pregnant eluate by electrowinning (EW). The EW sludge is filtered, dried, and retorted to remove the mercury and smelted to produce bullion bars. The barren carbon is reactivated and recycled back to the CIL circuit.
     The CIL tailings slurry gravity-flows over the safety screens to the cyanide destruction circuit. The conventional SO2/air process will be used to reduce the cyanide content of the CIL tailings solution from more than 100 mg/L cyanide to less than 20 mg/L cyanide. The detoxified slurry, together with the HDS circuit sludge, is pumped to the tailings pond.
     The tailings storage area will be located in the El Llagal valley located approximately 3.5 kilometres south of the plant site. The tailings facility will store tailings from the CIL circuit, blended with the chemical precipitate produced by the neutralization circuit. The waste rock from the open pits will also be disposed of in this facility.

- 76 -


 

The ultimate storage capacity of the tailings impoundment facility is expected to be 383 M m3, sufficient to contain all of the tailings, waste rock and HDS precipitate to be generated over the life of the Pueblo Viejo Project, and runoff water from the design flood event.
     The tailings system facility consists of two dams, which are proposed to be rockfill dams with a saprolite core. The rockfill will provide stability and resistance to earthquake and the saprolite core will provide an impermeable barrier to retain water. The transition from the fine-grained core to rockfill will be through two filter zones of sand and gravel. The saprolite will be obtained from local borrow areas and the rockfill from the Las Lagunas limestone quarry, and possibly other areas at the plant site if suitable properties can be confirmed with additional exploration.
     The Project is situated in a seismically active area. The design of the dams at site was based on the maximum credible earthquake, with a peak ground acceleration of 0.60 grams and a magnitude of 8.2. The starter dam will be designed to provide sufficient storage capacity for 1.5 years of full-scale tailings generation, waste rock, and HDS precipitate production. Subsequent dam raises would then be constructed on an annual basis and be sized to provide storage capacity for the subsequent years’ production of tailings, waste rock, and HDS precipitate.
     In addition to solids storage, each cell in the tailings facility is sized to provide storage for an operating pond and for extreme precipitation events. Water will be pumped from the operating ponds for reclaim or treatment. In addition, an operating volume will be needed to keep waste rock and much of the tailings flooded.
     Emergency spillways are required at all times during the operating period and closure spillways will be required at the end of the mine life. The spillways located through the abutment ridges will be sufficiently large to release the 1-in-100 year rainfall event after storing the design extreme precipitation events. The closure spillways will be sized to release the 24 hour probable maximum precipitation event. The spillways will be armoured up to a sufficient distance from the dam such that any erosion of the channel will not threaten the dam structure itself.
     The diversion of fresh water from the upper reaches of the Arroyo El Llagal will benefit the tailings system by reducing input volumes during the operating period, making the pond easier to manage and reducing the amount of water requiring treatment. A small dam and pump station in the upper El Llagal valley will capture any runoff bypassing the diversion channel and will pump it up into the channel. This dam will be moved upstream or enlarged as the basin is progressively filled. Later in the mine life when the impoundment elevation reaches the elevation of the diversion channel, the pipeline from the diversion dam will be extended to bypass the tailings facility.
     The seepage through the tailings dam is expected to be modest, and any seepage water will be collected in a pond at the base of the dam and pumped back to the impoundment. In addition, monitoring wells will be used around the perimeter of the basin to monitor groundwater quality. Pumping wells will be used to capture seepage if required.
     Excess water from the tailings pond can be discharged to the Maguaca River or to the Margajita River. The Maguaca River is not the preferred option at this time, as the Dominican Government currently discharges water from the Mejita tailings dam into the Maguaca. To ensure that water discharge will meet relevant environmental standards, an additional treatment plant has been included for the eventual discharges from El Llagal tailings dam.
Limestone and Lime Plant Facilities
     The limestone and lime required for plant operations will be mined and produced on site. Ground limestone and lime will be required to neutralize the acidic liquor and to control the pH in the CIL circuit. Lime will also be used to adjust the pH of the effluent after water treatment.
     The proposed limestone and lime systems will consist of the following major components:
    Limestone primary crushing, conveying, screening, and surge bin
 
    Limestone grinding (SAG and ball milling)
 
    Lime kilns
 
    Lime slaker (ball mill)

- 77 -


 

    Lime mixing and storage system
Water Management and Supply
     The Hatillo and Hondo Reservoirs are expected to supply fresh water for the process plant. Reclaimed water from the El Llagal tailings containment pond is expected to be used only as supplementary water supply under drought and flood situations, because chlorides and gypsum in this reclaim water would build up to unacceptable levels if recycled to the process plant.
     Barge-mounted pumps at the larger Hatillo Reservoir will pump fresh water to the Hondo Reservoir for make-up purposes. Fresh water will then be pumped and piped to the camps and to the fresh water storage pond northeast of the plant site.
     Fresh water for construction at the plant, such as earthworks conditioning, is expected to be taken from the Hondo Reservoir or pumped temporarily from the Maguaca River and stored in the existing 25 metre diameter by 12 metre high fire water tank, located south of the plant. Two spillage ponds at either side of the Maguaca River are expected to be used to store water for the construction of the El Llagal dam and southern haul roads.
     Potable water is expected to be supplied by treating and chlorinating fresh water from the Hondo Reservoir. A raw water tank will be installed south of the construction camp, and is expected to remain in place in the future. The raw water tank will supply fire and potable water through a treatment plant for the camps and plant site during construction. During operations, fire and process water for the plant site will be supplied from a freshwater storage pond.
     The proposed plant site is located on top of a ridge between two drainage catchments. Where possible, runoff from the process plant will be directed to the Arroyo Margajita drainage area to keep it separate from the storm water runoff from the old facilities. Where this is not practical, collection ponds will capture the run-off before it is pumped to the new water management system or returned to the process plant to serve as make-up water.
Power Supply
     Power requirements will vary from 150 MW at a process rate of 18,000 t/d to 200 MW at 24,000 t/d. Although the situation has improved somewhat in 2006-2007, power supply from the national grid in the Dominican Republic remains unreliable and is not currently a preferred option for operation of the Pueblo Viejo Project, as the selected ore processing route requires a reliable supply of power.
     Construction power for the Project is expected to be provided by small 1 MW portable diesel-fired power plants. During mine operation, emergency power is expected to be provided by five, 3 MW diesel generators that feed power into the main substation switchgear for distribution to critical loads, such as lighting, communication and computer equipment, and process equipment necessary for preventing the sanding-out of tanks and blockage of lines that contain slurries.
     Since 2006, PVDC has been evaluating alternative power supply options, which include construction of a new dedicated power plant for the Pueblo Viejo Project, partnering with a third party interested in constructing a new power plant in the Dominican Republic, or acquiring one or more existing power generating facilities to be dedicated to the Project. A variety of potential site locations have been considered in the course of these evaluations. These evaluations and discussions with potential third party partners or suppliers continue to date.

- 78 -


 

CERRO BLANCO PROJECT, GUATEMALA (non-material property)
     The Cerro Blanco Project is located approximately 80 kilometres east of Guatemala City, near the border with El Salvador. It is situated in the department of Jutiapa, near the community of Asuncion Mita. Currently, the concept for the Cerro Blanco Project is an underground mine with conventional milling to provide a gold/silver doré product. Permitting for the project was completed in 2007 and development of a decline is planned to begin in 2008 to access the ore body for samples for finalizing plant design details. Along with the underground gold/silver mine, a geothermal power generation project is under review with a feasibility study to be completed in 2008.
RISK FACTORS
     The operations of the Corporation are speculative due to the high-risk nature of its business which is the acquisition, financing, exploration, development and operation of mining properties. These risk factors could materially affect the Corporation’s future operating results and could cause actual events to differ materially from those described in forward-looking statements relating to the Corporation.
Exploration, Development and Operating Risk
     Although Goldcorp’s activities are primarily directed towards mining operations and the development of mineral deposits, its activities also include the exploration for and development of mineral deposits.
     Mining operations generally involve a high degree of risk. Goldcorp’s operations are subject to all the hazards and risks normally encountered in the exploration, development and production of gold, silver, copper, lead and zinc including unusual and unexpected geologic formations, seismic activity, rock bursts, cave-ins, flooding and other conditions involved in the drilling and removal of material, any of which could result in damage to, or destruction of, mines and other producing facilities, damage to life or property, environmental damage and possible legal liability. Although appropriate precautions to mitigate risk will be taken, milling operations are subject to hazards such as equipment failure or failure of retaining dams around tailings disposal areas which may result in environmental pollution and consequent liability.
     The exploration for and development of mineral deposits involves significant risks which even a combination of careful evaluation, experience and knowledge may not eliminate. While the discovery of an ore body may result in substantial rewards, few properties which are explored are ultimately developed into producing mines. Major expenses may be required to locate and establish mineral reserves, to develop metallurgical processes and to construct mining and processing facilities at a particular site. It is impossible to ensure that the exploration or development programs planned by Goldcorp or any of its joint venture partners will result in a profitable commercial mining operation. Whether a mineral deposit will be commercially viable depends on a number of factors, some of which are: the particular attributes of the deposit, such as size, grade, metallurgy and proximity to infrastructure; metal prices which are highly cyclical; and government regulations, including regulations relating to prices, taxes, royalties, land tenure, land use, importing and exporting of minerals and environmental protection. The exact effect of these factors cannot be accurately predicted, but the combination of these factors may result in Goldcorp not receiving an adequate return on invested capital.
     There is no certainty that the expenditures made by Goldcorp towards the search and evaluation of mineral deposits will result in discoveries of commercial quantities of ore.
Environmental Risks and Hazards
     All phases of Goldcorp’s operations are subject to environmental regulation in the various jurisdictions in which it operates. These regulations mandate, among other things, the maintenance of air and water quality standards and land reclamation. They also set forth limitations on the generation, transportation, storage and disposal of solid and hazardous waste. Environmental legislation is evolving in a manner which will likely require stricter standards and enforcement, increased fines and penalties for non-compliance, more stringent environmental assessments of proposed projects and a heightened degree of responsibility for companies and their officers, directors and employees. There is no assurance that future changes in environmental regulation, if any, will not

- 79 -


 

adversely affect Goldcorp’s operations. Environmental hazards may exist on the properties on which Goldcorp holds interests which are unknown to Goldcorp at present and which have been caused by previous or existing owners or operators of the properties.
     Government approvals and permits are currently, and may in the future be, required in connection with Goldcorp’s operations. To the extent such approvals are required and not obtained, Goldcorp may be curtailed or prohibited from continuing its mining operations or from proceeding with planned exploration or development of mineral properties.
     Failure to comply with applicable laws, regulations and permitting requirements may result in enforcement actions thereunder, including orders issued by regulatory or judicial authorities causing operations to cease or be curtailed, and may include corrective measures requiring capital expenditures, installation of additional equipment, or remedial actions. Parties engaged in mining operations or in the exploration or development of mineral properties may be required to compensate those suffering loss or damage by reason of the mining activities and may have civil or criminal fines or penalties imposed for violations of applicable laws or regulations.
     Amendments to current laws, regulations and permits governing operations and activities of mining and exploration companies, or more stringent implementation thereof, could have a material adverse impact on Goldcorp and cause increases in exploration expenses, capital expenditures or production costs or reduction in levels of production at producing properties or require abandonment or delays in development of new mining properties.
     Production at certain of Goldcorp’s mines involves the use of sodium cyanide which is a toxic material. Should sodium cyanide leak or otherwise be discharged from the containment system then Goldcorp may become subject to liability for clean up work that may not be insured. While appropriate steps will be taken to prevent discharges of pollutants into the ground water and the environment, Goldcorp may become subject to liability for hazards that it may not be insured against. Goldcorp became a signatory to the International Cyanide Code in July 2007. For more information regarding the International Cyanide Code, the reader is referred to the International Cyanide Management Institute website located at www.cyanidecode.org.
Environmental Risks at the Alumbrera Mine
     Despite design considerations at the Alumbrera Mine, a seepage plume, characterized by elevated concentrations of calcium and sulphate, has developed in the natural groundwater downstream of the tailings facility, currently within the MAA concession. Alumbrera is committed to preserve downstream surface and ground water quality at the Vis Vis river canyon. The current pump-back system configuration keeps tailings dam process water within the mining claim, as indicated by the updated model results. Water quality monitoring results from the pumping wells and the Vis Vis monitoring network have shown that the current pump-back system configuration is effective. The advantages of this system include enhanced water utilization by recycling water and pumping it back to the process, with reduced fresh water requirements. Since the monitoring network will be expanded as planned, additional wells will be installed at the sites to be recommended by ancillary studies. Monthly monitoring practices will continue throughout the project life in order to ensure updated system reports.
     The concentrate pipeline at the Alumbrera Mine crosses areas of mountainous terrain, significant rivers, high rainfall and active agriculture. Although various control structures and monitoring programs have been implemented, any rupture of the pipeline poses an environmental risk from spillage of concentrate.
     Goldcorp did not obtain any indemnities from the vendors of its 37.5% interest in the Alumbrera Mine against any potential environmental liabilities that may arise from operations, including, but not limited to, potential liabilities that may arise from the seepage plume or a rupture of the pipeline.
Environmental Risks at the Red Lake Gold Mines
     Three main issues are being addressed by Red Lake Gold Mines, which primarily relate to historical operations. These are groundwater issues, the Balmer Lake watershed and underground arsenic trioxide storage.

- 80 -


 

     A seepage plume from the tailings storage facility at the Campbell Complex was identified in the mid 1990s. Goldcorp conducts ongoing monitoring of the groundwater downgradient of the tailings facility and reports the results to the Ontario Ministry of the Environment (the “MOE”) as part of a leachate contingency program which was established in 2005. No additional remediation has been required by the MOE at this time. In 2007, additional assessments were completed as outlined in the contingency program and a potential pump back system is being designed as an additional proactive measure. Groundwater research and monitoring programs are also being completed at the Red Lake and Cochenour facilities.
     The Balmer Lake watershed was used historically as a tertiary polishing pond and has been receiving water from the Red Lake Complex since the 1940s. In September 1999, the MOE issued a Control Order to the Red Lake and Campbell Complexes to conduct technical investigations to obtain an improved understanding of then recent elevated arsenic concentrations in Balmer Lake. These studies have been ongoing to understand the current ecosystem in the lake and to develop a long-term management plan for the watershed. Over the past several years, Red Lake Gold Mines has been successful at maintaining arsenic concentrations below the applicable discharge criteria. Site specific water quality criteria for arsenic are being developed for the watershed, which will establish the long-term water management criteria for final closure of the facilities.
     Arsenic trioxide stored underground at the Campbell mine poses a potential long-term storage risk as the material could leach into groundwater when dewatering of the mine is no longer required at closure. The current mine life at the Red Lake and Campbell Complexes is 13 years. Red Lake Gold Mines has established financial assurance to fund up to 100 years of pumping following mine closure to maintain water levels below the level of the arsenic trioxide storage facilities. Currently, a pilot scale arsenic trioxide recovery project is in progress to evaluate the feasibility of removing the arsenic from the underground workings prior to closure. If the pilot project is successful, and the arsenic trioxide is removed from the underground prior to mine closure, the long-term liability associated with closure will be removed. To date, the pilot project has demonstrated that the arsenic trioxide can be effectively processed through the process facilities. However, capacity limits may preclude the processing of all arsenic trioxide during operations. In 2008, mining planning to provide access to the second arsenic storage stope is to be completed.
     The above-noted liabilities are included in the site closure plans and associated financial assurance. Goldcorp may be required to meet additional compliance or remediation measures as legislation continues to change, which may have an impact on the financial costs of the operations.
Luismin Tailings Management Risks
     Although the design and operation of tailings containment sites in the San Dimas district complies with existing permits and legal requirements in Mexico, existing tailings containment sites do not comply with international guidelines. Tailings containment sites which existed at the time of acquisition were not subjected to comprehensive geotechnical investigation before construction, normal safety factors in dam design, seepage monitoring or control, or controls on public or wildlife access to cyanide solution ponds or pumping installations. The deficiencies with the tailings management aspect of the operations are being addressed and capital investments were initiated in 2005 to upgrade the containment structures and tailings operations to bring them in line with international guidelines. During 2007, the second and third stages of the Tayoltita tailings dam project were completed. In these stages, the height of the berm downstream of the dam was increased by placing and compacting over 621,800 m3 of borrow material. The height of the berm will continue to be raised using filtered tailing material delivered from the plant. Also during 2007, filtered tailing material was placed on a portion of the downstream berm of the San Antonio tailings dam. Placement of the filtered tailings material and installation of a roller compacted concrete cover designed to function as a three-stage spillway in case of a major flood are due to be completed during 2008.
     Goldcorp anticipates that further expenditures will be required to maintain compliance with applicable environmental regulations, which are becoming more stringent and can be expected to become more aligned with international guidelines in the future. Goldcorp may incur environmental liability for mining activities conducted both prior to and during its ownership of the Luismin operations. To the extent that Goldcorp is subject to uninsured environmental liabilities, the payment for such liabilities would reduce funds otherwise available and could have a material adverse effect on Goldcorp. Should Goldcorp be unable to fund fully the cost of remedying an

- 81 -


 

environmental problem, Goldcorp may be required to suspend operations or enter into interim compliance measures pending completion of required remediation, which could have a material adverse effect on Goldcorp.
     Goldcorp did not obtain any indemnities from the vendors of Luismin against any potential environmental liabilities, including, but not limited to, those that may arise from possible failure of the San Antonio tailings dam.
Environmental Risks at Marigold Mine and the South Arturo Project
     The old milling operations at Goldcorp’s Marigold Mine and South Arturo Project (acquired in connection with the Glamis Acquisition) have tailing impoundments that have known leakage as detected by monitoring wells. Leakage of tailings seepage solutions could cause environmental damage. Based on third party studies of these facilities and their associated seepage, Goldcorp does not believe that groundwater resources have been affected and Goldcorp has successfully completed remediation measures to halt the leakage as approved by the Nevada Department of Environmental Protection and Bureau of Land Management.
Climate Change Risks
     Governments are moving to enact climate change legislation and treaties at the international, national, state/provincial and local levels. Where legislation already exists, regulation relating to emission levels and energy efficiency are becoming more stringent. Some of the costs associated with meeting more stringent regulation can be offset by increased energy efficiency and technological innovation. However, if the current regulatory trend continues, meeting more stringent regulations is anticipated to result in increased costs.
     Sea level rise: Goldcorp’s operations are not directly threatened by current predictions of sea level rise. All of the Corporation’s operations are located well inland at elevations from 100 metres to 4,000 metres above sea level. However, changes in sea levels could affect ocean transportation and shipping facilities which are used to transport supplies, equipment and personnel to Goldcorp’s operations and products from those operations to world markets.
     Extreme weather events: Extreme weather events (such as increased frequency or intensity of hurricanes, increased snow pack, prolonged drought) have the potential to disrupt operations at the Corporation’s mines. Where appropriate, Goldcorp’s facilities have developed emergency plans for managing extreme weather conditions, however, extended disruptions to supply lines could result in interruption to production.
     Resource shortages: Goldcorp’s facilities depend on regular supplies of consumables (diesel, tires, etc.) and reagents to operate efficiently. In the event that the effects of climate change cause prolonged disruption to the delivery of essential commodities, then Goldcorp’s production efficiency is likely to be reduced.
     Goldcorp will continue to assess energy efficiency opportunities across all of its operations with the goal of reducing both costs and greenhouse gas emissions. Goldcorp will continue to address the potential physical risks of climate change by including extreme weather conditions in emergency response plans as required. Goldcorp routinely collates data on energy use and greenhouse gas emissions. These data are reported annually in the Corporation’s Sustainability Report and in its submission to the Carbon Disclosure Project.
Permitting
     Goldcorp’s operations in Argentina, Canada, the Dominican Republic, Guatemala, Honduras, Mexico and the United States are subject to receiving and maintaining permits from appropriate governmental authorities. Although Goldcorp’s mining operations currently have all required permits for their operations as currently conducted, there is no assurance that delays will not occur in connection with obtaining all necessary renewals of such permits for the existing operations, additional permits for any possible future changes to operations, or additional permits associated with new legislation. Prior to any development on any of its properties, Goldcorp must receive permits from appropriate governmental authorities. There can be no assurance that Goldcorp will continue to hold all permits necessary to develop or continue operating at any particular property.

- 82 -


 

Peñasquito Development and Marketing Risk
     The Peñasquito Project is currently at the construction stage of its development. Construction and development of the project is subject to numerous risks, including, but not limited to, delays in obtaining equipment, material and services essential to completing construction of the project in a timely manner; changes in environmental or other government regulations; currency exchange rates; labour shortages; and fluctuation in metal prices. There can be no assurance that the construction will continue in accordance with current expectations or at all.
     Concentrates containing combinations of gold, silver, lead and zinc will be produced in large quantities at Peñasquito and loaded onto highway road vehicles and/or rail cars for transport to in-country smelters or to sea ports for export to foreign smelters in markets such as Asia, Europe and North America. This type of process involves a high level of environmental and financial risk. Goldcorp could be subject to potential significant increases in road and maritime transportation charges and refinery charges. Transportation of such concentrate is also subject to numerous risks including, but not limited to, delays in delivery of shipments, road blocks, terrorism, weather conditions and environmental liabilities in the event of an accident or leak. Goldcorp could be subject to limited smelter availability and capacity and could also face the risk of a potential interruption of business from a third party beyond its control, which in both cases could have a material adverse affect on Goldcorp’s operations and revenues. There is no assurance that smelting, refining or transportation contracts for the Peñasquito products will be entered into on acceptable terms or at all.
Economic and Political Instability in Argentina
     The Alumbrera Mine is located in Argentina. There are risks relating to an uncertain or unpredictable political and economic environment in Argentina.
     In January 2008, the Argentinean Government unilaterally decided to levy export duties on mining companies operating in the country, contrary to a 1993 fiscal stability agreement with MAA, the operator of the Alumbrera Mine, guaranteeing no change to the tax regime for 30 years. Goldcorp and its partner at the Alumbrera Mine, Xstrata, are among 14 companies that have been affected by the government’s decision to eliminate exemptions from export duties. In order to continue shipping concentrate produced at Alumbrera to foreign smelters, MAA has paid export retentions of 10% under protest. MAA has initiated appropriate legal actions seeking to have the imposition of the export duties reversed. Xstrata and Goldcorp have communicated their objections to the Government’s action to President Cristina Fernandez de Kirchner and other Government officials.
     During an economic crisis in 2002-2003, Argentina defaulted on foreign debt repayments and on the repayment on a number of official loans to multinational organizations. In addition, the Government has renegotiated or defaulted on contractual arrangements. The actions of the Argentine Government with respect to the export duties and its other contractual commitments to MAA and other foreign investors indicates that the Argentine Government may alter or impose requirements or policies that may adversely affect Goldcorp’s investment in MAA.
     There also is the risk of political violence and increased social tension in Argentina and Argentina has experienced periods of civil unrest, crime and labour unrest. Roadblocks (piqueterou) by members of the local communities, unemployed people and unions can occur on most national and provincial routes without notice. There have been some minor disruptions to access routes near the mine site which to date have not materially affected the supply of goods to the mine. There is no assurance that disruptions will not occur in the future which could materially affect the supply of goods to the mine.
     Certain events could have significant political ramifications to Alumbrera in Argentina. In particular, serious environmental incidents such as contamination of groundwater and surface water downstream of the tailings dam due to uncontrolled migration of the sulphate plume or other events, may occur which would constitute a major breach of Environmental Impact Report (“EIR”) commitments.
     The Alumbrera mining prospects are owned by YMAD, a quasi-governmental mining company, pursuant to an Argentine mining law which granted YMAD such rights. YMAD has granted a mining lease to Alumbrera pursuant to the UTE Agreement (see “Description of the Business — Alumbrera Mine, Argentina — Property

- 83 -


 

Description and Location” for details regarding the UTE Agreement). Significant political changes in Argentina which impact foreign investment and mining in general, or YMAD or Alumbrera’s rights to the Alumbrera mining prospects in particular, could adversely impact MAA’s ability to operate the Alumbrera Mine.
     Certain political and economic events such as: (i) the inability of Alumbrera to obtain U.S. dollars in a lawful market of Argentina; (ii) acts or failures to act by a government authority in Argentina; and (iii) acts of political violence in Argentina, could have a material adverse effect on Alumbrera’s ability to operate the Alumbrera Mine.
Business Interruption Risks at the Alumbrera Mine
     Concentrate slurry from the processing facilities at the Alumbrera Mine is pumped via a 316-kilometre concentrate slurry pipeline through Catamarca and Tucumán Provinces to a filter plant at Cruz del Norte. Concentrates from the filter plant are shipped 830 kilometres by rail from Cruz del Norte, Tucumán to Puerto Alumbrera. The failure or rupture of the pipeline or the interruption of rail service, depending on the location of such occurrence, could result in significant interruption of operations of Alumbrera and could adversely affect Goldcorp’s financial condition and results of operations. In addition to the interruption of business during the period that the pipeline or rail line is not in service, a failure or rupture of the pipeline or an accident involving the rail service that involved environmental consequences could adversely affect the ability of Alumbrera to use these means to transport concentrate from the mine to world markets. Alternative shipping methods may not be viable for a variety of reasons.
     The Alumbrera Mine is located in a remote area of Argentina. On average, more than 2,000 people are transported by road and more than 1,200 people are transported by air, to and from the mine site every month. A serious accident involving a bus or plane could result in multiple fatalities. The disruption of these services could also result in significant disruption to the operations of Alumbrera and have an adverse effect on the financial condition and operations of Goldcorp.
Uncertainty in the Estimation of Ore/Mineral Reserves and Mineral Resources
     The figures for Ore/Mineral Reserves and Mineral Resources contained in this annual information form are estimates only and no assurance can be given that the anticipated tonnages and grades will be achieved, that the indicated level of recovery will be realized or that Ore/Mineral Reserves could be mined or processed profitably. There are numerous uncertainties inherent in estimating Ore/Mineral Reserves and Mineral Resources, including many factors beyond Goldcorp’s control. Such estimation is a subjective process, and the accuracy of any reserve or resource estimate is a function of the quantity and quality of available data and of the assumptions made and judgments used in engineering and geological interpretation. Short-term operating factors relating to the Ore/Mineral Reserves, such as the need for orderly development of the ore bodies or the processing of new or different ore grades, may cause the mining operation to be unprofitable in any particular accounting period. In addition, there can be no assurance that gold, silver or copper recoveries in small scale laboratory tests will be duplicated in larger scale tests under on-site conditions or during production.
     Fluctuation in gold, silver, copper, zinc or lead prices, results of drilling, metallurgical testing and production and the evaluation of mine plans subsequent to the date of any estimate may require revision of such estimate. The volume and grade of reserves mined and processed and recovery rates may not be the same as currently anticipated. Any material reductions in estimates of Ore/Mineral Reserves and Mineral Resources, or of Goldcorp’s ability to extract these Ore/Mineral Reserves, could have a material adverse effect on Goldcorp’s results of operations and financial condition.
Uncertainty Relating to Inferred Mineral Resources
     Inferred mineral resources that are not mineral reserves do not have demonstrated economic viability. The San Dimas Mines’ life of mine plans run from 10 to 20 years which include approximately 68% of production based on inferred mineral resources. Due to the uncertainty which may attach to inferred mineral resources, there is no assurance that inferred mineral resources will be upgraded to proven and probable mineral reserves as a result of continued exploration.

- 84 -


 

Need for Additional Mineral Reserves and Mineral Resources
     Goldcorp must continually explore to replace and expand its Mineral Reserves and Mineral Resources as its mines produce gold, silver and copper. The life-of-mine estimates included in this annual information form for each of Goldcorp’s operating mines are based on Goldcorp’s best estimate given the information available to the Corporation. These estimates may not be correct. Goldcorp’s ability to maintain or increase its annual production of gold, silver and copper depends in significant part on its ability to find new Mineral Reserves and Mineral Resources and bring new mines into production, and to expand Mineral Reserves and Mineral Resources at existing mines.
     Goldcorp’s operating mineral properties have the following estimated mine lives:
         
Property   Estimated Mine Life  
Red Lake Gold Mine
  15 years
Porcupine Mine
  8 years
Musselwhite Mine
  7 years
Marigold Mine
  9 years
Wharf Mine
  3 years
El Sauzal Mine
  3 years
Los Filos Mine
  11 years
San Dimas Mines
  22 years
Nukay Mine
  13 years
Alumbrera Mine
  9 years
Marlin Mine
  9 years
Commodity Prices
     The price of the Common Shares, Goldcorp’s financial results and exploration, development and mining activities have previously been, or may in the future be, significantly adversely affected by declines in the price of gold, silver, copper, lead and zinc. Gold, silver, copper, lead and zinc prices fluctuate widely and are affected by numerous factors beyond Goldcorp’s control such as the sale or purchase of metals by various central banks and financial institutions, interest rates, exchange rates, inflation or deflation, fluctuation in the value of the United States dollar and foreign currencies, global and regional supply and demand, and the political and economic conditions of major metals-producing countries throughout the world. The price of gold, silver, copper, lead and zinc has fluctuated widely in recent years, and future serious price declines could cause continued development of and commercial production from Goldcorp’s properties to be impracticable. Depending on the price of gold, silver, copper, lead and zinc, cash flow from mining operations may not be sufficient and Goldcorp could be forced to discontinue production and may lose its interest in, or may be forced to sell, some of its properties. Future production from Goldcorp’s mining properties is dependent on gold, silver, copper, lead and zinc prices that are adequate to make these properties economic.
     Furthermore, reserve calculations and life-of-mine plans using significantly lower gold, silver, copper, lead and zinc prices could result in material write-downs of Goldcorp’s investment in mining properties and increased amortization, reclamation and closure charges.
     In addition to adversely affecting Goldcorp’s reserve estimates and its financial condition, declining commodity prices can impact operations by requiring a reassessment of the feasibility of a particular project. Such a reassessment may be the result of a management decision or may be required under financing arrangements related to a particular project. Even if the project is ultimately determined to be economically viable, the need to conduct such a reassessment may cause substantial delays or may interrupt operations until the reassessment can be completed.
     Copper concentrate from the Alumbrera Mine is shipped to smelters in Europe, India, the Far East, Canada and Brazil. Lead and zinc concentrates will also be shipped from the Peñasquito Project. Transportation costs of

- 85 -


 

metal concentrates could increase substantially due to an increase in the price of oil or a shortage in the number of vessels available to ship concentrate to smelters.
Commodity Hedging
     Currently Goldcorp’s policy is to not hedge future gold sales, however, this policy may change in the future. Goldcorp has entered into copper hedging instruments to manage exposure to fluctuations in copper prices.
     There is no assurance that a commodity-hedging program designed to reduce the risk associated with fluctuations in metal prices will be successful. Hedging may not protect adequately against declines in the price of the hedged metal. Although hedging may protect Goldcorp from a decline in the price of the metal being hedged, it may also prevent Goldcorp from benefiting fully from price increases.
Exchange Rate Fluctuations
     Exchange rate fluctuations may affect the costs that the Corporation incurs in its operations. Gold, silver and copper are sold in United States dollars and the Corporation’s costs are incurred principally in United States dollars, Canadian dollars, Mexican pesos, Argentine pesos, Guatemalan quetzal and Honduran lempira. The appreciation of non-United States dollar currencies against the United States dollar can increase the cost of gold, silver and copper production and capital expenditures in United States dollar terms. Goldcorp has a Risk Management Policy that includes hedging to reduce the risk associated with currency fluctuations; however, Goldcorp has not entered into such types of transactions during the current or comparative periods. The Corporation has assessed this risk and has not presently adopted an active currency hedging program given the correlation between metal prices and the currencies in which the Corporation operates.
Land Title
     Although the title to the properties owned and proposed to be acquired by Goldcorp were reviewed by or on behalf of Goldcorp, no formal title opinions were delivered to Goldcorp and, consequently, no assurances can be given that there are no title defects affecting such properties. Title insurance generally is not available, and Goldcorp’s ability to ensure that it has obtained a secure claim to individual mineral properties or mining concessions may be severely constrained. Goldcorp has not conducted surveys of the claims in which it holds direct or indirect interests and, therefore, the precise area and location of such claims may be in doubt. Accordingly, Goldcorp’s mineral properties may be subject to prior unregistered liens, agreements, transfers or claims, including native land claims, and title may be affected by, among other things, undetected defects. In addition, Goldcorp may be unable to operate its properties as permitted or to enforce its rights with respect to its properties.
     Portions of Goldcorp’s mineral reserves come from unpatented mining claims in the United States. There is a risk that any of Goldcorp’s unpatented mining claims could be determined to be invalid, in which case Goldcorp could lose the right to mine mineral reserves contained within those mining claims. Unpatented mining claims are created and maintained in accordance with the General Mining Law of 1872. Unpatented mining claims are unique United States property interests, and are generally considered to be subject to greater title risk than other real property interests due to the validity of unpatented mining claims often being uncertain. This uncertainty arises, in part, out of the complex federal and state laws and regulations under the General Mining Law of 1872. Unpatented mining claims are always subject to possible challenges of third parties or contests by the federal government. The validity of an unpatented mining claim, in terms of both its location and its maintenance, is dependent on strict compliance with a complex body of federal and state statutory and decisional law.
     In recent years, the United States Congress has considered a number of proposed amendments to the General Mining Law of 1872. If adopted, such legislation, among other things, could impose royalties on gold production from unpatented mining claims located on United States federal lands, result in the denial of permits to mine after the expenditure of significant funds for exploration and development, reduce estimates of mineral reserves and reduce the amount of future exploration and development activity on United States federal lands, all of which could have a material and adverse affect on Goldcorp’s cash flow, results of operations and financial condition.

- 86 -


 

Competition
     The mining industry is competitive in all of its phases. Goldcorp faces strong competition from other mining companies in connection with the acquisition of properties producing, or capable of producing, precious and base metals. Many of these companies have greater financial resources, operational experience and technical capabilities than Goldcorp. As a result of this competition, Goldcorp may be unable to maintain or acquire attractive mining properties on terms it considers acceptable or at all. Consequently, Goldcorp’s revenues, operations and financial condition could be materially adversely affected.
Additional Capital
     The mining, processing, development and exploration of Goldcorp’s properties, may require substantial additional financing. Failure to obtain sufficient financing may result in delaying or indefinite postponement of exploration, development or production on any or all of Goldcorp’s properties or even a loss of property interest. There can be no assurance that additional capital or other types of financing will be available if needed or that, if available, the terms of such financing will be favourable to Goldcorp. Low gold prices during the five years prior to 2002 adversely affected Goldcorp’s ability to obtain financing, and low gold, silver, copper, lead and zinc prices could have similar effects in the future.
Infrastructure
     Mining, processing, development and exploration activities depend, to one degree or another, on adequate infrastructure. Reliable roads, bridges, power sources and water supply are important determinants, which affect capital and operating costs. Unusual or infrequent weather phenomena, sabotage, community, government or other interference in the maintenance or provision of such infrastructure could adversely affect Goldcorp’s operations, financial condition and results of operations.
Government Regulation
     The mining, processing, development and mineral exploration activities of Goldcorp are subject to various laws governing prospecting, development, production, taxes, labour standards and occupational health, mine safety, toxic substances, land use, water use, land claims of local people and other matters. Although Goldcorp’s mining and processing operations and exploration and development activities are currently carried out in accordance with all applicable rules and regulations, no assurance can be given that new rules and regulations will not be enacted or that existing rules and regulations will not be applied in a manner which could limit or curtail production or development. Amendments to current laws and regulations governing operations and activities of mining and milling or more stringent implementation thereof could have a substantial adverse impact on Goldcorp.
Foreign Operations
     The majority of Goldcorp’s foreign operations are currently conducted in Argentina, the Dominican Republic, Guatemala, Honduras, Mexico and the United States, and as such Goldcorp’s operations are exposed to various levels of political, economic and other risks and uncertainties. These risks and uncertainties vary from country to country and include, but are not limited to, terrorism; hostage taking; military repression; expropriation; extreme fluctuations in currency exchange rates; high rates of inflation; labour unrest; the risks of war or civil unrest; renegotiation or nullification of existing concessions, licenses, permits and contracts; illegal mining; changes in taxation policies; restrictions on foreign exchange and repatriation; and changing political conditions, currency controls and governmental regulations that favour or require the awarding of contracts to local contractors or require foreign contractors to employ citizens of, or purchase supplies from, a particular jurisdiction.
     Changes, if any, in mining or investment policies or shifts in political attitude in Argentina, the Dominican Republic, Guatemala, Honduras, Mexico and the United States may adversely affect Goldcorp’s operations or profitability. Operations may be affected in varying degrees by government regulations with respect to, but not limited to, restrictions on production, price controls, export controls, currency remittance, income taxes, expropriation of property, foreign investment, maintenance of claims, environmental legislation, land use, land claims of local people, water use and mine safety.

- 87 -


 

     Failure to comply strictly with applicable laws, regulations and local practices relating to mineral right applications and tenure, could result in loss, reduction or expropriation of entitlements, or the imposition of additional local or foreign parties as joint venture partners with carried or other interests.
     The occurrence of these various factors and uncertainties cannot be accurately predicted and could have an adverse effect on Goldcorp’s operations or profitability.
Labour and Employment Matters
     While Goldcorp has good relations with both its unionized and non-unionized employees, production at Goldcorp’s mining operations and at the Alumbrera Mine is dependant upon the efforts of Goldcorp’s and Alumbrera’s employees. In addition, relations between Goldcorp and its employees may be impacted by changes in the scheme of labour relations which may be introduced by the relevant governmental authorities in whose jurisdictions Goldcorp carries on business. Adverse changes in such legislation or in the relationship between Goldcorp or Alumbrera with its employees may have a material adverse effect on Goldcorp’s business, results of operations and financial condition.
Subsidiaries
     Goldcorp is a holding company that conducts operations through Canadian and foreign (Antiguan, Argentinian, Barbadian, Bermudian, Cayman Island, Guatemalan, Honduran, Mexican and American) subsidiaries, joint ventures and divisions, and a significant portion of its assets are held in such entities. Accordingly, any limitation on the transfer of cash or other assets between the parent corporation and such entities, or among such entities, could restrict Goldcorp’s ability to fund its operations efficiently. Any such limitations, or the perception that such limitations may exist now or in the future, could have an adverse impact on Goldcorp’s valuation and stock price.
Insurance and Uninsured Risks
     Goldcorp’s business is subject to a number of risks and hazards generally, including adverse environmental conditions, industrial accidents, labour disputes, unusual or unexpected geological conditions, ground or slope failures, cave-ins, changes in the regulatory environment and natural phenomena such as inclement weather conditions, floods, hurricanes and earthquakes. Such occurrences could result in damage to mineral properties or production facilities, personal injury or death, environmental damage to Goldcorp’s properties or the properties of others, delays in mining, monetary losses and possible legal liability.
     Although Goldcorp maintains insurance to protect against certain risks in such amounts as it considers to be reasonable, its insurance will not cover all the potential risks associated with a mining company’s operations. Goldcorp may also be unable to maintain insurance to cover these risks at economically feasible premiums. Insurance coverage may not continue to be available or may not be adequate to cover any resulting liability. Moreover, insurance against risks such as loss of title to mineral property, environmental pollution, or other hazards as a result of exploration and production is not generally available to Goldcorp or to other companies in the mining industry on acceptable terms. Goldcorp might also become subject to liability for pollution or other hazards which may not be insured against or which Goldcorp may elect not to insure against because of premium costs or other reasons. Losses from these events may cause Goldcorp to incur significant costs that could have a material adverse effect upon its financial performance and results of operations.
Acquisition Strategy
     As part of Goldcorp’s business strategy, it has sought and will continue to seek new mining and development opportunities in the mining industry. In pursuit of such opportunities, Goldcorp may fail to select appropriate acquisition candidates or negotiate acceptable arrangements, including arrangements to finance acquisitions or integrate the acquired businesses and their personnel into Goldcorp. Goldcorp cannot assure that it can complete any acquisition or business arrangement that it pursues, or is pursuing, on favourable terms, or that any acquisitions or business arrangements completed will ultimately benefit Goldcorp’s business.

- 88 -


 

Joint Ventures
     Goldcorp holds an indirect 37.5% interest in the Alumbrera Mine, the other 12.5% and 50% interests being held indirectly by Yamana Gold Inc. and Xstrata, respectively. Goldcorp holds an indirect 40% interest in the Pueblo Viejo Project, an indirect 662/3% interest in the Marigold Mine and an indirect 40% interest in the South Arturo Project, the remaining interest in each of these properties being held indirectly by Barrick Gold Corporation. Goldcorp’s interest in these properties is subject to the risks normally associated with the conduct of joint ventures. The existence or occurrence of one or more of the following circumstances and events could have a material adverse impact on Goldcorp’s profitability or the viability of its interests held through joint ventures, which could have a material adverse impact on Goldcorp’s future cash flows, earnings, results of operations and financial condition: (i) disagreement with joint venture partners on how to develop and operate mines efficiently; (ii) inability of joint venture partners to meet their obligations to the joint venture or third parties; and (iii) litigation between joint venture partners regarding joint venture matters.
Market Price of the Corporation’s Securities
     The Common Shares and the common share purchase warrants of the Corporation (the “Warrants”) are listed on the Toronto Stock Exchange (the “TSX”) and the New York Stock Exchange (the “NYSE”). Securities of mining companies have experienced substantial volatility in the past, often based on factors unrelated to the financial performance or prospects of the companies involved. These factors include macroeconomic developments in North America and globally and market perceptions of the attractiveness of particular industries. The price of the Common Shares and the Warrants are also likely to be significantly affected by short-term changes in gold, silver or copper prices or in its financial condition or results of operations as reflected in its quarterly earnings reports.
     As a result of any of these factors, the market price of the Common Shares and the Warrants at any given point in time may not accurately reflect Goldcorp’s long-term value. Securities class action litigation often has been brought against companies following periods of volatility in the market price of their securities. Goldcorp may in the future be the target of similar litigation. Securities litigation could result in substantial costs and damages and divert management’s attention and resources.
Future Sales of Common Shares by Existing Shareholders
     Sales of a large number of Common Shares in the public markets, or the potential for such sales, could decrease the trading price of the Common Shares and could impair Goldcorp’s ability to raise capital through future sales of Common Shares. Goldcorp has previously completed private placements at prices per share which are lower than the current market price of the Common Shares. Accordingly, a significant number of shareholders of Goldcorp have an investment profit in the Common Shares that they may seek to liquidate. Substantially all of the Common Shares can be resold without material restriction either in the United States, in Canada or both.
Key Executives
     Goldcorp is dependent on the services of key executives, including its President and Chief Executive Officer and a small number of highly skilled and experienced executives and personnel. The loss of these persons or Goldcorp’s inability to attract and retain additional highly skilled employees may adversely affect its business and future operations.
Conflicts of Interest
     Certain of the directors and officers of Goldcorp also serve as directors and/or officers of other companies involved in natural resource exploration and development and consequently there exists the possibility for such directors and officers to be in a position of conflict. In particular, Lawrence Bell and Douglas Holtby, directors of the Corporation, are also directors of Silver Wheaton, and Ian Telfer and Kenneth Williamson, directors of the Corporation, are also directors of Uranium One Inc. Any decision made by any of such directors and officers involving Goldcorp will be made in accordance with their duties and obligations to deal fairly and in good faith with a view to the best interests of Goldcorp and its shareholders. In addition, each of the directors is required to declare

- 89 -


 

and refrain from voting on any matter in which such directors may have a conflict of interest in accordance with the procedures set forth in the Business Corporations Act (Ontario) and other applicable laws.
DIVIDENDS
     During the three financial years ended December 31, 2007, 2006 and 2005, the Corporation has paid monthly dividends to shareholders in the amount of $0.015 per share. On February 28, 2005, in connection with the Wheaton Merger, the Corporation paid a special dividend of $0.50 per share.
     Although Goldcorp expects to continue paying an annual cash dividend, the timing and the amount of the dividends to be paid by Goldcorp will be determined by the Board of Directors of Goldcorp from time to time based upon, among other things, cash flow, the results of operations and financial condition of Goldcorp and its subsidiaries, the need for funds to finance ongoing operations, compliance with credit agreements and other instruments, and such other considerations as the Board of Directors of Goldcorp considers relevant.
DESCRIPTION OF CAPITAL STRUCTURE
     The authorized share capital of the Corporation consists of an unlimited number of Common Shares. As of March 24, 2008, 710,211,845 Common Shares were issued and outstanding. Holders of Common Shares are entitled to receive notice of any meetings of shareholders of the Corporation, to attend and to cast one vote per Common Share at all such meetings. Holders of Common Shares do not have cumulative voting rights with respect to the election of directors and, accordingly, holders of a majority of the Common Shares entitled to vote in any election of directors may elect all directors standing for election. Holders of Common Shares are entitled to receive on a pro-rata basis such dividends, if any, as and when declared by the Corporation’s board of directors at its discretion from funds legally available therefor and upon the liquidation, dissolution or winding up of the Corporation are entitled to receive on a pro-rata basis the net assets of the Corporation after payment of debts and other liabilities, in each case subject to the rights, privileges, restrictions and conditions attaching to any other series or class of shares ranking senior in priority to or on a pro-rata basis with the holders of Common Shares with respect to dividends or liquidation. The Common Shares do not carry any pre-emptive, subscription, redemption or conversion rights, nor do they contain any sinking or purchase fund provisions.

- 90 -


 

TRADING PRICE AND VOLUME
Common Shares
     The Common Shares are listed and posted for trading on the NYSE under the symbol “GG” and on the TSX under the symbol “G”. The following table sets forth information relating to the trading of the Common Shares on the TSX for the months indicated.
                         
    High   Low    
Month   (C$)   (C$)   Volume
 
January 2007
    33.95       29.20       77,840,603  
February 2007
    34.50       30.50       82,060,405  
March 2007
    31.45       27.10       89,355,945  
April 2007
    30.47       26.94       78,725,305  
May 2007
    28.41       24.01       94,051,710  
June 2007
    26.85       24.60       69,731,499  
July 2007
    29.05       25.37       86,123,899  
August 2007
    27.25       22.40       93,023,305  
September 2007
    30.75       25.01       90,232,608  
October 2007
    33.23       29.03       85,865,226  
November 2007
    34.53       30.06       89,833,569  
December 2007
    34.80       30.47       58,071,047  
     The price of the Common Shares as quoted by the TSX at the close of business on December 31, 2007 was C$33.80 and on March 24, 2008 was C$38.02.
Warrants
     The Warrants are listed and posted for trading on the NYSE under the symbol “GGWS” and on the TSX under the symbol “G.WT.G”. The following table sets forth information relating to the trading of the Warrants on the TSX for the months indicated.
                         
    High   Low    
Month   (C$)   (C$)   Volume
 
January 2007
    17.00       14.01       59,592  
February 2007
    17.50       14.50       64,566  
March 2007
    15.00       11.25       69,109  
April 2007
    13.20       11.45       101,977  
May 2007
    13.00       9.54       51,967  
June 2007
    10.49       9.20       33,281  
July 2007
    12.37       9.81       80,768  
August 2007
    11.50       7.73       73,503  
September 2007
    12.50       8.85       58,349  
October 2007
    12.50       10.50       53,966  
November 2007
    12.50       9.33       66,636  
December 2007
    10.70       8.80       39,340  
     The price of the Warrants as quoted by the TSX at the close of business on December 31, 2007 was C$10.00 and on March 24, 2008 was C$15.40.

- 91 -


 

DIRECTORS AND OFFICERS
     The following table sets forth, as of December 31, 2007, the name, province/state and country of residence, position held with the Corporation and principal occupation of each person who is a director and/or an executive officer of the Corporation.
         
Name,        
Province/State and        
Country of Residence   Position(s) with the Corporation   Principal Occupation
C. Kevin McArthur
Nevada, United States
  President, Chief Executive Officer and a Director (director since November 2006)   President and Chief Executive Officer of Goldcorp
 
       
Ian W. Telfer
British Columbia, Canada
  Chairman of the Board and a Director (director since February 2005)   Chairman of the Board of Goldcorp
 
       
Douglas M. Holtby (3)
British Columbia, Canada
  Vice Chairman of the Board and Lead Director (director since February 2005)   President and Chief Executive Officer of Arbutus Road Investments Inc. (a private investment company)
 
       
John P. Bell (2)(4)
British Columbia, Canada
  Director since February 2005   Independent Director
 
       
Lawrence I. Bell (1)(3)(4)
British Columbia, Canada
  Director since February 2005   Chairman of Canada Line (Rapid Transit) Project
 
       
Beverley A. Briscoe (1)(3)
British Columbia, Canada
  Director since April 2006   President of Briscoe Management Limited
 
       
Peter J. Dey (2)(3)
Ontario, Canada
  Director since June 2006   Chairman of Paradigm Capital Inc.
 
       
P. Randy Reifel (4)
British Columbia, Canada
  Director since November 2006   President of Chesapeake Gold Corp.
 
       
A. Dan Rovig (1)(2)
Nevada, United States
  Director since November 2006   Independent Consultant
 
       
Kenneth F. Williamson (1)(2)(3)
Ontario, Canada
  Director since November 2006   Independent Consultant
 
       
Lindsay A. Hall
British Columbia, Canada
  Executive Vice President and Chief Financial Officer   Executive Vice President and Chief Financial Officer of Goldcorp
 
       
Charles A. Jeannes
British Columbia, Canada
  Executive Vice President, Corporate Development   Executive Vice President, Corporate Development of Goldcorp
 
       
Steve P. Reid
British Columbia, Canada
  Executive Vice President and Chief Operating Officer   Executive Vice President and Chief Operating Officer of Goldcorp
 
       
Cheryl A. Sedestrom
Reno, Nevada
  Vice President, Risk Management   Vice President, Risk Management of Goldcorp
 
       
Rohan Hazelton
British Columbia, Canada
  Vice President, Finance   Vice President, Finance of Goldcorp
 
       
Colette Rustad
British Columbia, Canada
  Vice President, Controller   Vice President, Controller of Goldcorp

- 92 -


 

         
Name,        
Province/State and        
Country of Residence   Position(s) with the Corporation   Principal Occupation
Wendy Louie
British Columbia, Canada
  Vice President, Assistant Controller   Vice President, Assistant Controller of Goldcorp
 
       
Paula Rogers
British Columbia, Canada
  Vice President, Treasurer   Vice President, Treasurer of Goldcorp
 
       
Mark A. Ruus
British Columbia, Canada
  Vice President, Tax   Vice President, Tax of Goldcorp
 
       
John Allan
British Columbia, Canada
  Vice President, Sustainable Development   Vice President, Sustainable Development of Goldcorp
 
       
Gerry Atkinson
British Columbia, Canada
  Vice President, Human Resources, Corporate and Canada   Vice President, Human Resources, Corporate and Canada of Goldcorp
 
       
Robert Bryson
British Columbia, Canada
  Vice President, Engineering   Vice President, Engineering of Goldcorp
 
       
George Burns
Ontario, Canada
  Vice President, Canada and United States   Vice President, Canada and United States of Goldcorp
 
       
Ronald McLean
British Columbia, Canada
  Vice President, Human Resources, United States and Latin America   Vice President, Human Resources, United States and Latin America of Goldcorp
 
       
Tim Miller
Guatemala City, Guatemala
  Vice President, Central and South America   Vice President, Central and South America of Goldcorp
 
       
Barry Olson
Zacatecas, Mexico
  Vice President, Chief Operating
Officer, Mexico
  Vice President, Chief Operating Officer, Mexico of Goldcorp
 
       
Mark Olson
British Columbia,Canada
  Vice President, Information
Technology
  Vice President, Information Technology of Goldcorp
 
       
Charlie Ronkos
Reno, Nevada
  Vice President, Exploration   Vice President, Exploration of Goldcorp
 
       
Jeff Wilhoit
British Columbia, Canada
  Vice President, Investor Relations   Vice President, Investor Relations of Goldcorp
 
       
David Deisley
British Columbia, Canada
  Vice President and General Counsel   Vice President and General Counsel of Goldcorp
 
       
Anna M. Tudela
British Columbia, Canada
  Corporate Secretary and Director, Regulatory Compliance   Corporate Secretary and Director, Regulatory Compliance of Goldcorp
 
(1)   Member of the Audit Committee.
 
(2)   Member of the Compensation Committee.
 
(3)   Member of the Nominating and Corporate Governance Committee.
 
(4)   Member of the Sustainability, Environment, Health and Safety Committee.
     The principal occupations of each of the Corporation’s directors and executive officers within the past five years are disclosed in the brief biographies set forth below.
     C. Kevin McArthur – President, Chief Executive Officer and Director. Mr. McArthur was appointed President and Chief Executive Officer of the Corporation effective November 15, 2006. Prior thereto, he was President and Chief Executive Officer of Glamis since January 1, 1998 and served in a variety of management positions with Glamis since 1988. Prior to working with Glamis, Mr. McArthur held a variety of operating and

- 93 -


 

engineering positions with BP Minerals and Homestake Mining Company. He is a graduate of the Department of Mining Engineering at the Mackay School of Mines, the University of Nevada.
     Ian W. Telfer – Chairman and Director. Mr. Telfer was appointed Chairman of the Board of the Corporation effective November 15, 2006. Prior thereto, he was President and Chief Executive Officer of the Corporation since March 17, 2005 and February 24, 2005, respectively, and Chairman and Chief Executive Officer of Wheaton prior to such time since September 2001. Mr. Telfer has over 25 years experience in the precious metals business. He has served as a director and/or officer of a number of mining companies, including TVX Gold Inc. and Lihir Gold.
     Douglas M. Holtby – Vice Chairman of the Board and Lead Director. Mr. Holtby was appointed Vice Chairman of the Board of the Corporation and Lead Director effective November 15, 2006. Prior thereto, he was Chairman of the Board of the Corporation since October 29, 2005. Mr. Holtby is President and Chief Executive Officer of a private investment company, Arbutus Road Investments Inc. From June 1989 to June 1996, Mr. Holtby was President, Chief Executive Officer and a director of WIC Western International Communications Ltd., from 1989 to 1996, he was Chairman of Canadian Satellite Communications Inc., from 1998 to 1999, he was a Trustee of ROB.TV and CKVU, from 1974 to 1989, he was President of Allarcom Limited and, from 1982 to 1989, he was President and a shareholder of Allarcom Pay Television Limited. Mr. Holtby is a Chartered Accountant.
     John P. Bell – Director. Mr. John Bell was Canadian Ambassador to the Ivory Coast from 1984 to 1987 and then Ambassador to Brazil from 1987 to 1990. He also served as High Commissioner to Malaysia from 1993 to 1996. Mr. Bell was special advisor to the Canadian Minister of Foreign Affairs and Head of the Canadian Delegation on environment issues during the lead-up to the Earth Summit in Rio de Janeiro in June 1992, and was Canada’s chief negotiator at the Earth Summit. Mr. Bell has been Chief Federal Negotiator for the Indian Affairs and has served on several not-for-profit boards of directors. Mr. Bell is also an independent director of Taiga Building Products Ltd.
     Lawrence I. Bell – Director. Mr. Lawrence Bell is currently the Chairman of Canada Line (Rapid Transit) Project and served as the non-executive Chairman of British Columbia Hydro and Power Authority until December 2007. From August 2001 to November 2003, Mr. Bell was Chairman and Chief Executive Officer of British Columbia Hydro and Power Authority and, from 1987 to 1991, he was Chairman and Chief Executive Officer of British Columbia Hydro and Power Authority. He is also a director of International Forest Products Limited and Silver Wheaton and is former Chairman of the University of British Columbia Board of Directors. Prior to these positions, Mr. Bell was Chairman and President of the Westar Group and Chief Executive Officer of Vancouver City Savings Credit Union. In the province’s public sector, Mr. Bell has served as Deputy Minister of Finance and Secretary to the Treasury Board.
     Beverley A. Briscoe – Director. Ms. Briscoe has been President of Briscoe Management Limited since 2004. From 2003 to 2007, she was Chair of the Industry Training Authority for BC, from 1997 to 2004, she was President and owner of Hiway Refrigeration Limited, from 1994 to 1997, she was Vice President and General Manager of Wajax Industries Limited, from 1989 to 1994, she was Vice President, Finance of Rivtow Group of Companies and, from 1983 to 1989, she was Chief Financial Officer of various operating divisions of The Jim Pattison Group. Ms. Briscoe is currently a director of Duke Energy Income Fund, Ritchie Brothers Auctioneers Inc. and DTI Dental Technologies Inc. She is a Chartered Accountant and was recently elected to the Fellowship of Chartered Accountants by the BC Institute. She received her Bachelor of Commerce from the University of British Columbia.
     Peter J. Dey – Director. Mr. Dey is a well known senior corporate executive and an experienced corporate Director. He is currently Chairman of Paradigm Capital Inc., an independent investment dealer, and Chairman of Addax Petroleum Corporation. He is also a Director of Workbrain Corporation, Soulpepper Theatre Company and Alpine Canada. He is a former Chairman of the Ontario Securities Commission and former Chairman of Morgan Stanley Canada, and he was a Senior Partner of Osler, Hoskin & Harcourt. In 1994 he chaired the TSX Committee on Corporate Governance, and has since been involved with developing global corporate governance standards as Vice Chairman of the OECD Task Force on Board Room Practices, and as Chairman of the Private Sector Advisory Group of the Global Corporate Governance Forum. He holds a Masters of Laws degree from Harvard University, a Bachelor of Laws Degree from Dalhousie University, and a Bachelor of Science degree from Queen’s University.

- 94 -


 

     P. Randy Reifel – Director. Mr. Reifel was appointed to the Board in November 2006. Prior thereto, he had been a director of Glamis since June 2002 following the acquisition of Francisco Gold Corp. In 1993, Mr. Reifel founded and served as President and a director of Francisco Gold Corp. which discovered the El Sauzal gold deposit in Mexico and the Marlin gold deposit in Guatemala. Currently, he is President and a director of Chesapeake Gold Corp. that explores for precious metals in Mexico and Central America. Mr. Reifel holds a Bachelor of Commerce degree and a Masters of Science in Business Administration.
     A. Dan Rovig – Director. Mr. Rovig was appointed to the Board in November 2006. Prior thereto, he had been a director and Chairman of the Board of Glamis since November 1998. Before his appointment as Chairman, Mr. Rovig was a director and the President and Chief Executive Officer of Glamis and its subsidiaries from November 1989 to August 1997 when he retired. Prior to 1988, Mr. Rovig was an executive officer of British Petroleum Ltd., including its subsidiaries Amselco Minerals Inc. and BP Minerals America for five years. He holds a Bachelor of Science in Mining Engineering and a Masters of Science in Mineral Dressing Engineering from Montana College of Mineral Science and Technology. He is also a registered member of the Society for Mining, Metallurgy and Exploration and the Geological Society of Nevada.
     Kenneth F. Williamson – Director. Mr. Williamson was appointed a director of the Corporation effective November 15, 2006 and had been a director of Glamis prior thereto since 1999. He was Vice Chairman, Investment Banking at Midland Walwyn/Merrill Lynch Canada Inc. from 1993 to 1998. He has worked in the securities industry for more than 25 years, concentrating on financial services and the natural resource industries in the United States and Europe. Mr. Williamson is a director of a number of companies in the natural resource sector. He holds a Bachelor of Applied Science (P.Eng.) degree from the University of Toronto and a Masters in Business Administration from the University of Western Ontario.
     Lindsay Hall – Chief Financial Officer and Executive Vice President. Mr. Hall was appointed Chief Financial Officer and Executive Vice President of the Corporation on April 19, 2006 and March 3, 2006, respectively. He is the former Executive Vice President and Chief Financial Officer of Placer Dome. Mr. Hall is a Chartered Accountant with strong financial credentials, which include being Vice President of Finance at West Coast Energy, Chief Financial Officer of Duke Americas in Houston, and Treasurer of Duke Energy Inc.
     Charles Jeannes – Executive Vice President, Corporate Development. Mr. Jeannes was appointed Executive Vice President of the Corporation effective November 15, 2006 and later appointed Executive Vice President, Corporate Development of the Corporation effective January 1, 2007. From 1999 until the completion of the Glamis Acquisition, he was Executive Vice President, Administration, General Counsel and Secretary of Glamis. Prior to joining Glamis, Mr. Jeannes worked for Placer Dome, most recently as Vice President of Placer Dome North America. He holds a Bachelor of Arts degree from the University of Nevada and graduated from the University of Arizona School of Law with honours in 1983. He practiced law from 1982 until 1994 and has broad experience in mining transactions, public and private financing, permitting and international regulation.
     Steve P. Reid – Executive Vice President and Chief Operating Officer. Mr. Reid was appointed Chief Operating Officer of the Corporation effective January 1, 2007 and, prior thereto, Executive Vice President, Canada and USA effective concurrently with the completion of the Placer CLA Acquisition. Mr. Reid is a mining engineer with 30 years of extensive international experience in both the operating and business aspects of the mining industry. Prior to joining Goldcorp, he worked for Placer Dome as the Country Manager for the Canadian operations. He spent a total of 13 years working for Placer Dome, holding numerous corporate, mine management and operating roles worldwide. Mr. Reid has also worked in leadership positions for Kingsgate Consolidated and Newcrest Mining Limited, where he was responsible for running operations throughout Asia and Australia.
     Cheryl A. Sedestrom – Vice President, Risk Management. Ms. Sedestrom was appointed Vice President, Risk Management on January 1, 2007. From 2000 until the completion of the Glamis Acquisition, Ms. Sedestrom served as Vice President, Chief Financial Officer and Treasurer of Glamis. Ms. Sedestrom is a Certified Public Accountant and holds a M.B.A. in accounting as well as a B.A. in political science, both from the University of Michigan. Ms. Sedestrom has over 20 years of experience in the mining and mining-related industries with Glamis, Goldman Sachs & Co., including the J. Aron commodity-trading division, Hecla Mining Company and Coopers and Lybrand.

- 95 -


 

     Rohan Hazelton – Vice President, Finance. Mr. Hazelton was appointed Vice President, Finance of the Corporation effective November 15, 2006 and, prior thereto, he was Corporate Controller of the Corporation since March 17, 2005. Mr. Hazelton joined Wheaton in November 2002 and became Corporate Controller of Wheaton in October 2004. Prior to joining Wheaton, he worked at Arthur Andersen. He is a Chartered Accountant and holds a Bachelor of Arts in math and economics from Harvard University.
     Colette Rustad Vice President, Corporate Controller. Ms. Rustad was appointed Vice President, Corporate Controller of the Corporation effective May 2, 2007. Ms. Rustad has over 19 years experience as an international finance professional in the mining/resource/finance industries. During her 11 year tenure at Placer Dome Inc., she held senior leadership positions that included Vice President, Chief Financial Officer, Africa, based in Johannesburg; Director, Global Audit Services and Treasurer, North America. During her eight years tenure at Ernst & Young, Toronto, she specialized in both audit and tax in the financial institution and resources industries. She is a member of the Institute of Chartered Accountants of Ontario and British Columbia; completed the Advanced Management Program, The Wharton Business School, The University of Pennsylvania; and has a Bachelor of Commerce from the University of Calgary.
     Wendy Louie – Vice President, Assistant Controller. Ms. Louie served as Vice President, Controller of the Corporation from November 15, 2006 to May 2, 2007 when she was appointed Vice President, Assistant Controller. Prior to joining the Corporation, from May 2003 to May 2006, she was a Senior Tax Manager at Ernst & Young, and prior thereto, over a period of nine years, held various financial reporting positions at Duke Energy Gas Transmission (formerly Westcoast Energy Inc.), ultimately as Director of Corporate Accounting. Ms. Louie is a Chartered Accountant and holds a Bachelor of Commerce from the University of British Columbia.
     Paula Rogers – Vice President, Treasurer. Ms. Rogers has been Vice President, Treasurer of the Corporation since January 1, 2007, prior thereto she was Treasurer of the Corporation since August 15, 2005 and, prior thereto, she was Corporate Treasurer of Wheaton since October 2004. Prior to joining Wheaton, she held the positions of Assistant Treasurer, Corporate Reporting Manager and Tax Manager at Finning International Inc. over a period of nine years. Ms. Rogers is a Chartered Accountant and holds a Bachelor of Commerce from the University of British Columbia.
     Mark Ruus – Vice President, Tax. Mr. Ruus was appointed Vice President, Tax of the Corporation effective November 15, 2006, having joined the Corporation in July 2006. He is responsible for global tax planning, tax-related support of corporate development and finance activities and tax compliance. Before joining the Corporation, Mr. Ruus was Vice President, Taxation for Placer Dome where he played leading tax roles for 10 years. Prior to this he spent 14 years with Price Waterhouse (pre-merger with Coopers & Lybrand) servicing primarily international resource companies. Mr. Ruus is a Chartered Accountant and holds a Bachelor of Commerce from the University of Calgary.
     John Allan – Vice President, Sustainable Development. Mr. Allan was appointed Vice President, Sustainable Development of the Corporation effective March 7, 2007. Mr. Allan is an environmental scientist with 28 years experience in various environmental roles in the mining industry. Prior to joining the Corporation, he held the position of Group Manager, Environment with Newcrest Mining Limited for a period of eight years. He has held senior environmental roles with RGC Limited and Rio Tinto, being responsible for environmental performance of operations in Australia, South East Asia and North America.
     Gerry Atkinson – Vice President, Human Resources, Corporate and Canada. Mr. Atkinson joined the Corporation in May 2006 and was appointed Vice President, Human Resources, Corporate and Canada of the Corporation effective May 2, 2007. Mr. Atkinson has 20 years experience in senior human resources roles in the mining industry and in the oil and gas industry with Duke Energy Gas Transmission and Trans Canada Pipelines. Mr. Atkinson holds a Bachelor of Commerce from the University of Durham in England.
     Robert Bryson – Vice President, Engineering. Mr. Bryson was appointed Vice President, Engineering of the Corporation effective January 1, 2007. Prior to the completion of the Glamis Acquisition, he served one year as Vice President, Engineering of Glamis and the seven years prior to that as Glamis’ Marigold Mine Engineering Manager and then General Manager. Mr. Bryson holds a Bachelor of Science degree in Mining Engineering from

- 96 -


 

the University of Nevada. He has 27 years of experience in both the operating and engineering aspects of the mining industry with emphasis on resource and reserve reporting. He is a qualified person under NI 43-101.
     George Burns – Vice President, Canada and United States. Mr. Burns was appointed Vice President, Canada and United States of the Corporation effective August 8, 2007. Mr. Burns has over 29 years of experience in the mineral sector, including executive, operations, development and engineering leadership roles in gold, copper and coal operations. Prior to joining the Corporation, Mr. Burns was Vice President and Chief Operating Officer of Centerra Gold Inc. Mr. Burns served in various capacities for Asarco, including Vice President of Mining as well as numerous capacities for Cyprus Minerals Corporation and he began his career with the Anaconda Company in 1978. Mr. Burns received a Bachelor of Science degree in Mining Engineering from the Montana College of Mineral Science and Technology in 1982.
     Ronald McLean – Vice President, Human Resources, United States and Latin America. Mr. McLean was appointed Vice President, Human Resources, United States and Latin America of the Corporation effective May 2, 2007. From June 2006 until the completion of the Glamis Acquisition, Mr. McLean was Vice President, Human Resources of Glamis. Prior thereto, he was with Placer Dome Inc. for 11 years, the last eight years as Vice President, Latin America and United States in Santiago, Chile and subsequently in Denver, Colorado. Prior thereto, Mr. McLean spent 17 years with Cominco Ltd. as its Human Resources Manager and Superintendent at a number of operations in Canada’s arctic, Alaska and southern British Columbia.
     Tim Miller – Vice President, Central and South America. Mr. Miller was appointed Vice President, Central and South America of the Corporation effective May 2, 2007. Mr. Miller has had the responsibility for Goldcorp’s Central Amercian businesses at Marlin, San Martin and Cerro Blanco. He has a B.Sc. degree in Chemistry from the University of New Mexico and an Masters in Business Administration from Webster Universtiy. He worked with Gold Fields North America at gold mines in New Mexico and California, and spent several years working in gold mining in West Africa. He joined Glamis in 2000 and was instrumental to the permitting, design and construction of the San Martin and Marlin mines in Honduras and Guatemala.
     Barry Olson – Vice President, Chief Operating Officer, Luismin. Mr. Olson was appointed Vice President, Chief Operating Officer, Luismin, Mexico effective May 2, 2007. From August 2006 until the completion of the Glamis Acquisition, Mr. Olson was Vice President, Director, Mexican Operations of Glamis. He has a Bachelor of Science degree in Metallurgical Engineering and a Masters of Science degree in Mining Engineering from the University of Idaho. Prior to joining Glamis, from 2001 to August 2006, Mr. Olson was Vice President, General Manager for Coeur d’Alene Mines Corp. at its Rochester mine and Senior Vice President, Operations for mines in Chile and Argentina. Mr. Olson has extensive experience in design, construction and managing mines in Nevada, California, Chile and Argentina.
     Mark Olson – Vice President, Information Technology. Mr. Olson joined the Corporation in March 2006 and was appointed Vice President, Information Technology of the Corporation effective May 2, 2007. Mr. Olson is responsible for providing strategic direction, guidance and leadership in the area of information technology to all of Goldcorp’s operations. Prior to joining the Corporation, he spent seven years with Deloitte & Touche LLP in an information technology consulting role, and 10 years with Teck Cominco Limited as a mine controller where his responsibilities included information technology at specific mine sites. Mr. Olson is a Certified General Accountant.
     Charlie Ronkos – Vice President, Exploration. Mr. Ronkos was appointed Vice President, Exploration of the Corporation effective January 1, 2007. From 1999 until the completion of the Glamis Acquisition, Mr. Ronkos worked most recently as Vice President, Exploration of Glamis. He was employed with Glamis since 1992, seven of those years with Rayrock Resources Inc. prior to its acquisition by Glamis. He holds a Bachelor of Arts degree from the Wittenberg University and graduated from the University of Nevada with a Master of Science degree in 1981. His 30 year career includes assignments with Rio Algom, Battle Mountain Gold, Pegasus, Hecla and Cordex.
     Jeffrey Wilhoit – Vice President, Investor Relations. Mr. Wilhoit was appointed Vice President, Investor Relations of the Corporation effective January 1, 2007. From November 2005 until the completion of the Glamis Acquisition, Mr. Wilhoit served as Director, Investor Relations of Glamis. Prior thereto, from November 1996 to November 2005, Mr. Wilhoit served as Vice President of the Financial Relations Board (FRB), an investor relations consulting company based in Chicago, Illinois.

- 97 -


 

     David L. Deisley – Vice President and General Counsel. Mr. Deisley joined Goldcorp in September 2007. He has 20 years experience in the mining industry both as private counsel to mining clients and as an employee of Barrick Gold Corporation. Immediately prior to joining Goldcorp, Mr. Deisley served as Regional Counsel for North America for Barrick Gold Corporation. Mr. Deisley’s experience in the gold mining industry includes projects and operations in Canada, the United States of America, Argentina, Chile and Perú. Mr. Deisley is a graduate of the University of Utah College of Law.
     Anna M. Tudela – Corporate Secretary and Director, Regulatory Compliance. Ms. Tudela joined Goldcorp in June 2005, was appointed Director, Legal and Assistant Corporate Secretary on August 15, 2005 and subsequently appointed Corporate Secretary on May 2, 2007 and Director, Regulatory Compliance on September 1, 2007. She has more than 20 years of experience in the securities and corporate finance areas. She is also involved in Roundtables of the Forum for Women Entrepreneurs BC. Prior to joining Goldcorp, Ms. Tudela worked in the Securities and Corporate Finance Department of Davis LLP. Ms. Tudela was Corporate Secretary of Diamond Fields Resources Inc. from 1995 to 1996 and Director, Legal and Assistant Corporate Secretary of Silver Wheaton from July 2005 to October 2007.
     Directors are elected at each annual meeting of Goldcorp’s shareholders and serve as such until the next annual meeting or until their successors are elected or appointed.
     As at March 24, 2008, the directors and executive officers of Goldcorp, as a group, beneficially owned, directly or indirectly, or exercised control or direction over 5,057,069 Common Shares, representing less than one percent of the total number of Common Shares outstanding before giving effect to the exercise of options or warrants to purchase Common Shares held by such directors and executive officers. The statement as to the number of Common Shares beneficially owned, directly or indirectly, or over which control or direction is exercised by the directors and executive officers of Goldcorp as a group is based upon information furnished by the directors and executive officers.
Cease Trade Orders, Bankruptcies, Penalties and Sanctions
     No director or executive officer of the Corporation is, or within ten years prior to the date hereof has been, a director, chief executive officer or chief financial officer of any company (including the Corporation) that, (i) was subject to a cease trade order, an order similar to a cease trade order or an order that denied the relevant company access to any exemption under securities legislation, that was in effect for a period of more than 30 consecutive days, that was issued while the director or executive officer was acting in the capacity as director, chief executive officer or chief financial officer; or (ii) was subject to a cease trade order, an order similar to a cease trade order or an order that denied the relevant company access to any exemption under securities legislation, that was in effect for a period of more than 30 consecutive days, that was issued after the director or executive officer ceased to be a director, chief executive officer or chief financial officer and which resulted from an event that occurred while that person was acting in the capacity as director, chief executive officer or chief financial officer.
     No director or executive officer of the Corporation, or a shareholder holding a sufficient number of securities of the Corporation to affect materially control of the Corporation, (i) is, or within ten years prior to the date hereof has been, a director or executive officer of any company (including the Corporation) that, while that person was acting in that capacity, or within a year of that person ceasing to act in that capacity, became bankrupt, made a proposal under any legislation relating to bankruptcy or insolvency or was subject to or instituted any proceedings, arrangement or compromise with creditors or had a receiver, receiver manager or trustee appointed to hold its assets, other than (a) Lawrence Bell who was a director of a mining company when it filed a plan of reorganization under Chapter 11 on December 22, 1998; and (b) Ian Telfer who was Vice Chairman of a technology company when it made an assignment in bankruptcy on July 31, 2001; or (ii) has, within ten years prior to the date hereof, become bankrupt, made a proposal under any legislation relating to bankruptcy or insolvency, or become subject to or instituted any proceedings, arrangement or compromise with creditors, or had a receiver, receiver manager or trustee appointed to hold the assets of the director, executive officer or shareholder.
     No director or executive officer of the Corporation, or a shareholder holding a sufficient number of

- 98 -


 

securities of the Corporation to affect materially the control of the Corporation, has been subject to (i) any penalties or sanctions imposed by a court relating to securities legislation or by a securities regulatory authority or has entered into a settlement agreement with a securities regulatory authority; or (ii) any other penalties or sanctions imposed by a court or regulatory body that would likely be considered important to a reasonable investor in making an investment decision.
Conflicts of Interest
     To the best of Goldcorp’s knowledge, and other than as disclosed in this annual information form, there are no known existing or potential conflicts of interest between Goldcorp and any director or officer of Goldcorp, except that certain of the directors and officers serve as directors and officers of other public companies, specifically Silver Wheaton Corp. and Uranium One Inc., and therefore it is possible that a conflict may arise between their duties as a director or officer of Goldcorp and their duties as a director or officer of such other companies. See “Risk Factors — Conflicts of Interest”.
INTEREST OF MANAGEMENT AND OTHERS IN MATERIAL TRANSACTIONS
     Other than as described below and elsewhere in this annual information form, since January 1, 2005, no director, executive officer or 10% shareholder of the Corporation or any associate or affiliate of any such person or company, has or had any material interest, direct or indirect, in any transaction that has materially affected or will materially affect the Corporation or any of its subsidiaries.
     In October 2004, in connection with the Silver Wheaton Transaction, Wheaton entered into the Silver Wheaton Services Agreement with Silver Wheaton whereby Silver Wheaton has agreed to pay a monthly fee to Wheaton for the use of a portion of its office facilities and the services of its personnel. Ian Telfer, the Chairman of Goldcorp, was a director of Silver Wheaton from October 2004 to April 2006, Eduardo Luna, former Executive Vice President of Goldcorp, is Chairman of the board of directors of Silver Wheaton, and Peter Barnes, the former Executive Vice President and Chief Financial Officer of Goldcorp, is President and Chief Executive Officer of Silver Wheaton. Fees paid to Goldcorp under the Silver Wheaton Services Agreement for the year ended December 31, 2007 totalled $193,200.
     During the financial year ended December 31, 2005, the Corporation sold its holdings in three marketable securities to a company owned by Robert McEwen, the former non-Executive Chairman and Chief Executive Officer of the Corporation. These were non-brokered transactions which were executed at market value based on the average of the TSX closing price for the ten trading days prior to the sale agreements, resulting in proceeds to the Corporation totaling approximately $4 million. During the financial year ended December 31, 2005, the Corporation sold its share ownership of Lexam Explorations Inc. to a company owned by Mr. McEwen for proceeds of $300,000.
     In March 2006, the Corporation and Silver Wheaton amended the Silver Purchase Agreement, increasing the minimum number of ounces of silver to be delivered over the 25 year contract period by 100 million ounces, to 220 million ounces, and waiving any capital expenditure contributions previously required to be paid by Silver Wheaton. In consideration for these amendments, Silver Wheaton issued to the Corporation 18 million common shares, representing approximately 9.8% of the then outstanding shares of Silver Wheaton, and a $20 million one year non-interest bearing promissory note.
     In December 2006, the Corporation sold 18 million common shares of Silver Wheaton pursuant to a public offering for proceeds to the Corporation of approximately C$217.9 million. Eduardo Luna, former Executive Vice President of the Corporation, is Chairman of the board of directors of Silver Wheaton and each of Lawrence Bell and Douglas Holtby are directors of both the Corporation and Silver Wheaton.
     In April 2007, the Corporation completed the sale of the Amapari Mine and the Peak Mines to Peak Gold. As a result of the sale, Goldcorp became a holder of approximately 22% of the then outstanding common shares of Peak Gold. See “General Development of the Business – Sale of the Amapari Mine and the Peak Mines” for further details. In connection with the transaction, Julio Carvalho, the Corporation’s former Executive Vice President,

- 99 -


 

Central and South America, was appointed President and Chief Executive Officer of Peak Gold and Ian Telfer, the Corporation’s Chairman of the Board, was appointed as a director of Peak Gold.
     In July 2007, the Corporation completed the sale to Silver Wheaton of 25% of the life of mine silver production from the Peñasquito Project for a cash payment of $485 million. See “General Development of the Business – Sale of 25% of Life of Mine Silver Production from Peñasquito Project” for further details. Eduardo Luna, former Executive Vice President of the Corporation, is Chairman of the board of directors of Silver Wheaton and each of Lawrence Bell and Douglas Holtby are directors of both the Corporation and Silver Wheaton.
     In February 2008, the Corporation completed the sale of its 108 million common shares of Silver Wheaton for aggregate gross proceeds to the Corporation of C$1.566 billion. This represented the sale of all of the Corporation’s remaining interest in Silver Wheaton. See “General Development of the Business – Sale of Silver Wheaton Shares” for further details. Each of Lawrence I. Bell and Douglas M. Holtby are directors of both the Corporation and Silver Wheaton.
TRANSFER AGENT AND REGISTRAR
     The transfer agent and registrar for the Common Shares in Canada is CIBC Mellon Trust Company at its principal offices in Vancouver, British Columbia and Toronto, Ontario. The co-transfer agent and registrar for the Common Shares in the United States is Mellon Investor Services LLC at its principal offices in Jersey City, New Jersey.
     The warrant agent for the Warrants is CIBC Mellon Trust Company at its principal offices in Vancouver, British Columbia and Toronto, Ontario. The co-transfer agent and registrar for the Warrants in the United States is Mellon Investor Services LLC at its principal offices in Jersey City, New Jersey.
MATERIAL CONTRACTS
     The only material contract entered into by the Corporation within the financial year ended December 31, 2007 or before such time that is still in effect, other than in the ordinary course of business, is the $1.5 billion credit facility, available under the Corporation’s profile at www.sedar.com.
INTERESTS OF EXPERTS
     The following table sets out the individuals who are the qualified persons as defined by NI 43-101 in connection with the Mineral Reserve and Mineral Resource estimates for the Corporation’s mineral properties set out opposite their name(s) and contained in this annual information form:
     
Mineral Property   Qualified Person(s)
 
   
Red Lake Gold Mine
  Stephane Blais, P.Eng. at Red Lake Gold Mines (Mineral Reserves)
Dean Crick, M.Sc., P.Geo. at Red Lake Gold Mines (Mineral Resources)
 
   
Porcupine Mine
  Stephen Price, P.Geo. at the Porcupine Mine
Patti Nakai-Lajoie, P.Geo. at the Porcupine Mine
Imola Götz, P.Eng. at the Porcupine Mine
 
   
Musselwhite Mine
  Andrew Cheatle, P.Geo. at the Musselwhite Mine
Tim Sanford, P.Eng. at the Musselwhite Mine
 
   
Marigold Mine
  Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp
Patricia A. Maloney, P.Eng., Marigold Mining Co.

- 100 -


 

     
Mineral Property   Qualified Person(s)
 
   
Wharf Mine
  Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp
Fred H. Brown, CPG, Independent Geological Consultant
 
   
Éléonore Project
  Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp
Jacques Simoneau, P.Geo., Les Mines Opinaca Ltée
Nathalie Prud’homme, P.Geo., Les Mines Opinaca Ltée
 
   
South Arturo Project
  Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp
 
   
Imperial Project
  Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp
 
   
Los Filos Mine
  Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, S.A. de C.V.
 
   
El Sauzal Mine
  Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp
Steven Ristorcelli, P.Geo., Mine Development Associates, Inc.
 
   
San Dimas Mines
  Velasquez Spring, P.Eng., Senior Geologist, Watts, Griffis and McOuat Limited
Gordon Watts, P.Eng., Senior Associate Mineral Economist, Watts, Griffis and McOuat Limited
 
   
Nukay Mine
  Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, S.A. de C.V.
 
   
Peñasquito Project
  Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp
Fred H. Brown, CPG, Independent Geological Consultant
 
   
Alumbrera Mine
  Luis Rivera, MAusIMM at Minera Alumbrera Limited
 
   
Marlin Mine
  Michael G. Hester, FAusIMM, B.Sc., M.S., Independent Mining Consultants, Inc.
 
   
Pueblo Viejo Project
  Not been supported by a technical report prepared in accordance with NI
43-101. A technical report is being prepared by qualified persons under NI
43-101 and it will be available for review on the SEDAR website located at

www.sedar.com under the Corporation’s profile on or before May 15, 2008.
Readers are advised to refer to that technical report when it is filed.
 
   
Cerro Blanco Project
  Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp
     The following are the technical reports prepared in accordance with NI 43-101 from which certain technical information relating to the Corporation’s principal mineral projects contained in this annual information form has been derived:
1.   Red Lake Gold Mine – Dean Crick, M.Sc., P.Geo., Stephane Blais, P.Eng. and Anthony Stechishen, P.Geo. prepared a report in accordance with NI 43-101 for Goldcorp entitled “The Red Lake Gold Mines Property, Red Lake Mining Division, Northern Ontario” dated November 17, 2006.
2.   Los Filos Mine – P. John Barton, B.Sc.(Eng.), ARSM, MAusIMM, Consultant to Snowden Mining Industry Consultants Inc., Andrew F. Ross, M.Sc., P.Geo. at Snowden Mining Industry Consultants Inc., Michael G. Hester, FAusIMM, B.Sc., M.S., at Independent Mining Consultants, Inc., Daniel W. Kappes, P.Eng., B.Sc., M.Sc., President of Kappes Cassiday & Associates, and John F. Lupo, Ph.D., P.E., formerly at URS Australia Pty Ltd., prepared a report in accordance with NI 43-101 for Goldcorp entitled “Technical Report NI 43-101F1 Los Filos Project, Mexico” dated March 31, 2006.
3.   Peñasquito Project – Robert H. Bryson, MMSA, Vice President, Engineering of Goldcorp, Fred H. Brown, CPG, Independent Geological Consultant, Reynaldo Rivera, MAusIMM, Vice President, Exploration of Luismin, and Steven Ristorcelli, P.Geo., Mine Development Associates, Inc., prepared a report in accordance with NI 43-101 for Goldcorp entitled “Amended Peñasquito Project Technical Report Concepción del Oro District, Zacatecas State, México” dated December 31, 2007, as amended February 19, 2008.

- 101 -


 

4.   Alumbrera Mine – Harry Burgess, P.Eng., B. Terrence Hennessey, P.Geo. and David T. Wells, C.Eng., all at Micon International Limited, prepared a report in accordance with NI 43-101 for Wheaton River Minerals Ltd. entitled “Technical Report on Mining and Processing Assets of Peak Gold Mines, in New South Wales, Australia and Minera Alumbrera Ltd., in Argentina” dated January 2003.
5.   Marlin Mine – James S. Voorhees, P.Eng., formerly of Glamis Gold Ltd., prepared a report in accordance with NI 43-101 for Glamis Gold Ltd. entitled “Marlin Project Technical Report” dated November 11, 2003.
     Each of such reports are available on SEDAR at www.sedar.com and a summary of such reports is contained in this annual information form under “Description of the Business – Mineral Properties”.
     The technical disclosure in this annual information form with respect to the Pueblo Viejo Project has not been supported by a technical report prepared in accordance with NI 43-101. The technical report is being prepared by qualified persons under NI 43-101 and it will be available for review on the SEDAR website located at www.sedar.com under the Corporation’s profile on or before May 15, 2008. Readers are advised to refer to that technical report when it is filed.
     None of the aforementioned firms or persons held any securities of the Corporation or of any associate or affiliate of the Corporation when they prepared the reports referred to above or following the preparation of such reports nor did they receive any direct or indirect interest in any securities of the Corporation or of any associate or affiliate of the Corporation in connection with the preparation of such reports.
     None of the aforementioned firms or persons, nor any directors, officers or employees of such firms, are currently expected to be elected, appointed or employed as a director, officer or employee of the Corporation or of any associate or affiliate of the Corporation.
     Deloitte & Touche LLP are the independent registered chartered accountants of the Corporation.
AUDIT COMMITTEE
     The Corporation’s Audit Committee is responsible for monitoring the Corporation’s systems and procedures for financial reporting and internal control, reviewing certain public disclosure documents and monitoring the performance and independence of the Corporation’s external auditors. The committee is also responsible for reviewing the Corporation’s annual audited financial statements, unaudited quarterly financial statements and management’s discussion and analysis of financial results of operations for both annual and interim financial statements and review of related operations prior to their approval by the full board of directors of the Corporation.
     The Audit Committee’s charter sets out its responsibilities and duties, qualifications for membership, procedures for committee member removal and appointments and reporting to the Corporation’s board of directors. A copy of the charter is attached hereto as Schedule “A”.
     The members of the Corporation’s current Audit Committee are Beverley Briscoe (Chair), Lawrence I. Bell, A. Dan Rovig and Kenneth F. Williamson. Each of Ms. Briscoe and Messrs. Bell, Rovig and Williamson are independent and financially literate within the meaning of Multilateral Instrument 52-110 Audit Committees (“MI 52-110”). In addition to being independent directors as described above, all members of the Audit Committee must meet an additional “independence” test under MI 52-110 in that their directors’ fees are the only compensation they, or their firms, receive from the Corporation and that they are not affiliated with the Corporation. The meaning of independence under MI 52-110 is set out in Schedule “A” to the Audit Committee’s charter.
     The Audit Committee met seven times in 2007. Each of Lawrence I. Bell, Beverley A. Briscoe, A. Dan Rovig and Kenneth F. Williamson were present at all seven meetings.

- 102 -


 

Relevant Education and Experience
     Set out below is a description of the education and experience of each audit committee member that is relevant to the performance of his or her responsibilities as an audit committee member:
Beverley A. Briscoe – Ms. Briscoe has been President of Briscoe Management Limited since 2004. From 2003 to 2007, she was Chair of the Industry Training Authority for BC, from 1997 to 2004, she was President and owner of Hiway Refrigeration Limited, from 1994 to 1997, she was Vice President and General Manager of Wajax Industries Limited, from 1989 to 1994, she was Vice President, Finance of Rivtow Group of Companies and, from 1983 to 1989, she was Chief Financial Officer of various operating divisions of The Jim Pattison Group. Ms. Briscoe is currently a director of Duke Energy Income Fund, Ritchie Brothers Auctioneers Inc. and DTI Dental Technologies Inc. She is a Chartered Accountant and was recently elected to the Fellowship of Chartered Accountants by the BC Institute. She received her Bachelor of Commerce from the University of British Columbia.
Lawrence I. Bell – Mr. Lawrence Bell is currently the Chairman of Canada Line (Rapid Transit) Project and served as the non-executive Chairman of British Columbia Hydro and Power Authority until December 2007. From August 2001 to November 2003, Mr. Bell was Chairman and Chief Executive Officer of British Columbia Hydro and Power Authority and, from 1987 to 1991, he was Chairman and Chief Executive Officer of British Columbia Hydro and Power Authority. He is also a director of International Forest Products Limited and Silver Wheaton and is former Chairman of the University of British Columbia Board of Directors. Prior to these positions, Mr. Bell was Chairman and President of the Westar Group and Chief Executive Officer of Vancouver City Savings Credit Union. In the province’s public sector, Mr. Bell has served as Deputy Minister of Finance and Secretary to the Treasury Board.
A. Dan Rovig – Mr. Rovig holds a Bachelor of Science in Mining Engineering and a Masters of Science in Mineral Dressing Engineering from Montana College of Mineral Science and Technology. He is also a registered member of the Society for Mining, Metallurgy and Exploration and the Geological Society of Nevada. Prior to being appointed to the Board in November 2006, he had been a director and Chairman of the Board of Glamis since November 1998. Before his appointment as Chairman, Mr. Rovig was a director and the President and Chief Executive Officer of Glamis and its subsidiaries from November 1989 to August 1997 when he retired. Prior to 1988, Mr. Rovig was an executive officer of British Petroleum Ltd., including its subsidiaries Amselco Minerals Inc. and BP Minerals America for five years.
Kenneth F. Williamson – Mr. Williamson served on the Glamis board of directors since 1999. He was Vice Chairman, Investment Banking at Midland Walwyn/Merrill Lynch Canada Inc. from 1993 to 1998. He has worked in the securities industry for more than 25 years, concentrating on financial services and the natural resource industries in the United States and Europe. Mr. Williamson is a director of a number of companies in the natural resource sector. He holds a Bachelor of Applied Science (P.Eng.) degree from the University of Toronto and a Masters in Business Administration from the University of Western Ontario.
Pre-Approval Policies and Procedures
     The Audit Committee’s charter sets out responsibilities regarding the provision of non-audit services by the Corporation’s independent registered chartered accountants. This policy encourages consideration of whether the provision of services other than audit services is compatible with maintaining the auditor’s independence and requires Audit Committee pre-approval of permitted audit and audit-related services.

- 103 -


 

External Auditor Service Fees
Audit Fees
     The aggregate audit fees billed by the Corporation’s independent registered chartered accountants for the financial year ended December 31, 2007 were $5,661,600 (for the financial year ended December 31, 2006 – $7,226,000).
Audit-Related Fees
     The aggregate audit-related fees billed by the Corporation’s independent registered chartered accountants for the financial year ended December 31, 2007 were $Nil (for the financial year ended December 31, 2006 – $943,000 for due diligence, internal controls over financial reporting advisory services and other).
Tax Fees
     The aggregate tax fees in respect of tax compliance, tax advice and tax planning billed by the Corporation’s independent registered chartered accountants for the financial year ended December 31, 2007 were $353,700 (for the financial year ended December 31, 2006 – $1,606,500).
All Other Fees
     The aggregate non-audit fees billed by the Corporation’s independent registered chartered accountants for the financial year ended December 31, 2007 were $Nil (for the financial year ended December 31, 2006 – $Nil).
ADDITIONAL INFORMATION
     Additional information relating to the Corporation can be found on SEDAR at www.sedar.com; on the United States Securities and Exchange Commission website at www.sec.gov; or on Goldcorp’s website at www.goldcorp.com. Additional information, including directors’ and officers’ remuneration and indebtedness, principal holders of the Corporation’s securities and securities authorized for issuance under equity compensation plans is contained in the management information circular of the Corporation dated March 28, 2008 which will be available on SEDAR at www.sedar.com. Additional financial information is provided in the Corporation’s audited consolidated financial statements and management’s discussion and analysis for the financial year ended December 31, 2007.

- 104 -


 

SCHEDULE “A”
GOLDCORP INC.
AUDIT COMMITTEE CHARTER
I.   PURPOSE
 
    The Audit Committee is a committee of the Board of Directors (the “Board”) of Goldcorp Inc. (“Goldcorp” or the “Company”). The primary function of the Audit Committee is to assist the Board in fulfilling its financial reporting and controls responsibilities to the shareholders of the Company and the investment community. The external auditors will report directly to the Audit Committee. The Audit Committee’s primary duties and responsibilities are:
  A.   overseeing the integrity of the Company’s financial statements and reviewing the financial reports and other financial information provided by the Company to any governmental body or the public and other relevant documents;
 
  B.   assisting the Board in oversight of the Company’s compliance with legal and regulatory requirements;
 
  C.   recommending the appointment and reviewing and appraising the audit efforts of the Company’s independent auditor, overseeing the non-audit services provided by the independent auditor, overseeing the independent auditor’s qualifications and independence and providing an open avenue of communication among the independent auditor, financial and senior management and the Board of Directors;
 
  D.   assisting the Board in oversight of the performance of the Company’s internal audit function;
 
  E.   serving as an independent and objective party to oversee and monitor the Company’s financial reporting process and internal controls, the Company’s processes to manage business and financial risk, and its compliance with legal, ethical and regulatory requirements;
 
  F.   preparing Audit Committee report(s) as required by applicable regulators; and
 
  G.   encouraging continuous improvement of, and fostering adherence to, the Company’s policies, procedures and practices at all levels.
II.   COMPOSITION AND OPERATIONS
  A.   The Committee shall operate under the guidelines applicable to all Board committees.
 
  B.   The Audit Committee shall be comprised of at least three directors, all of whom are “independent” as such term is defined in the Board Guidelines.
 
  C.   In addition, unless otherwise authorized by the Board, no director shall be qualified to be a member of the Audit Committee if such director (i) is an “affiliated person”, as defined in Appendix One, or (ii) receives (or his/her immediate family member or the entity for which such director is a director, member, partner or principal and which provides consulting, legal, investment banking, financial or other similar services to the Company), directly or indirectly, any consulting, advisory, or other compensation from the Company other than compensation for serving in his or her capacity as member of the Board and as a member of Board committees.
 
  D.   All members shall, to the satisfaction of the Board of Directors, be “financially literate” as defined in Appendix One, and at least one member shall have accounting or related financial management expertise to qualify as a “financial expert” as defined in Appendix One.


 

  E.   If a Committee member simultaneously serves on the audit committees of more than three public companies, the Committee shall seek the Board’s determination as to whether such simultaneous service would impair the ability of such member to effectively serve on the Company’s audit committee and ensure that such determination is disclosed.
 
  F.   The Committee shall meet at least four times annually, or more frequently as circumstances require. The Committee shall meet within 45 days following the end of each of the first three financial quarters to review and discuss the unaudited financial results for the preceding quarter and the related MD&A and shall meet within 90 days following the end of the fiscal year end to review and discuss the audited financial results for the year and related MD&A prior to their publishing.
 
  G.   The Committee may ask members of management or others to attend meetings and provide pertinent information as necessary. For purposes of performing their audit related duties, members of the Committee shall have full access to all corporate information and shall be permitted to discuss such information and any other matters relating to the financial position of the Company with senior employees, officers and independent auditors of the Company.
 
  H.   As part of its job to foster open communication, the Committee should meet at least annually with management and the independent auditor in separate executive sessions to discuss any matters that the Committee or each of these groups believe should be discussed privately. In addition, the Committee or at least its Chair should meet with the independent auditor and management quarterly to review the Company’s financial statements.
 
  I.   Each of the Chairman of the Committee, members of the Committee, Chairman of the Board, independent auditors, Chief Executive Officer, Chief Financial Officer or Secretary shall be entitled to request that the Chairman of the Audit Committee call a meeting which shall be held within 48 hours of receipt of such request.
III.   RESPONSIBILITIES AND DUTIES
 
    To fulfill its responsibilities and duties the Audit Committee shall:
  A.   Create an agenda for the ensuing year.
 
  B.   Review and update this Charter at least annually, as conditions dictate.
 
  C.   Describe briefly in the Company’s annual report and more fully in the Company’s Management Information Circular the Committee’s composition and responsibilities and how they were discharged.
 
  D.   Documents/Reports Review
  i)   Review with management and the independent auditors, the Company’s interim and annual financial statements, management discussion and analysis, earnings releases and any reports or other financial information to be submitted to any governmental and/or regulatory body, or the public, including any certification, report, opinion, or review rendered by the independent auditor for the purpose of recommending their approval to the Board prior to their filing, issue or publication. The Chair of the Committee may represent the entire Committee for purposes of this review in circumstances where time does not allow the full Committee to be available.
  ii)   Review analyses prepared by management and/or the independent auditor setting forth

- A2 -


 

      significant financial reporting issues and judgments made in connection with the preparation of the financial statements, including analyses of the effects of alternative GAAP methods on the financial statements.
 
  iii)   Review the effect of regulatory and accounting initiatives, as well as off balance sheet structures, on the financial statements of the Company.
 
  iv)   Review policies and procedures with respect to directors’ and officers’ expense accounts and management perquisites and benefits, including their use of corporate assets and expenditures related to executive travel and entertainment, and review the results of the procedures performed in these areas by the independent auditor, based on terms of reference agreed upon by the independent auditor and the Audit Committee.
 
  v)   Review expenses of the Non-Executive Board Chair and CEO quarterly.
 
  vi)   Ensure that adequate procedures are in place for the review of the Company’s public disclosure of financial information extracted or derived from the issuer’s financial statements, as well as review any financial information and earnings guidance provided to analysts and rating agencies, and periodically assess the adequacy of those procedures.
E.   Independent Auditor
  i)   Recommend to the Board and approve the selection of the independent auditor, consider the independence and effectiveness and approve the fees and other compensation to be paid to the independent auditor.
 
  ii)   Monitor the relationship between management and the independent auditor including reviewing any management letters or other reports of the independent auditor and discussing any material differences of opinion between management and the independent auditor.
 
  iii)   Review and discuss, on an annual basis, with the independent auditor all significant relationships they have with the Company to determine their independence and report to the Board of Directors.
 
  iv)   Review and approve requests for any non-audit services to be performed by the independent auditor and be advised of any other study undertaken at the request of management that is beyond the scope of the audit engagement letter and related fees. Pre-approval of non-audit services is satisfied if:
  a)   The aggregate amount of non-audit services not pre-approved expected to constitute no more than 5% of total fees paid by issuer and subsidiaries to external auditor during fiscal year in which the services are provided;
 
  b)   the Company or a subsidiary did not recognize services as non-audit at the time of the engagement; and
 
  c)   the services are promptly brought to Committee’s attention and approved prior to completion of the audit.
  v)   Ensure disclosure of any specific policies or procedures adopted by the Committee to satisfy pre-approval requirements for non-audit services by the Company’s external auditor.

- A3 -


 

vi)   Review the relationship of non-audit fees to audit fees paid to the independent Auditor, to ensure that auditor independence is maintained.
 
vii)   Ensure that both the audit and non-audit fees are disclosed to shareholders by category.
 
viii)   Review the performance of the independent auditor and approve any proposed discharge and replacement of the independent auditor when circumstances warrant. Consider with management and the independent auditor the rationale for employing accounting/auditing firms other than the principal independent auditor.
 
ix)   At least annually, consult with the independent auditor out of the presence of management about significant risks or exposures, internal controls and other steps that management has taken to control such risks, and the fullness and accuracy of the organization’s financial statements. Particular emphasis should be given to the adequacy of internal controls to expose any payments, transactions, or procedures that might be deemed illegal or otherwise improper.
 
x)   Arrange for the independent auditor to be available to the Audit Committee and the full Board as needed. Ensure that the auditors report directly to the Audit Committee and are made accountable to the Board and the Audit Committee, as representatives of the shareholders to whom the auditors are ultimately responsible.
 
xi)   Oversee the work of the independent auditors engaged for the purpose of preparing or issuing an audit report or performing other audit, review or attest services.
 
xii)   Ensure that the independent auditors are prohibited from providing the following non-audit services and determining which other non-audit services the independent auditors are prohibited from providing:
  a)   bookkeeping or other services related to the accounting records or financial statements of the Company;
 
  b)   financial information systems design and implementation;
 
  c)   appraisal or valuation services, fairness opinions, or contribution-in-kind reports;
 
  d)   actuarial services;
 
  e)   internal audit outsourcing services;
 
  f)   management functions or human resources;
 
  g)   broker or dealer, investment adviser or investment banking services;
 
  h)   legal services and expert services unrelated to the audit; and
 
  i)   any other services which the Public Company Accounting Oversight Board determines to be impermissible.
xiii)   Approve any permissible non-audit engagements of the independent auditors, in accordance with applicable legislation.

- A4 -


 

F.   Financial Reporting Processes
  i)   In consultation with the independent auditor review the integrity of the organization’s financial and accounting controls and reporting processes, both internal and external.
 
  ii)   Consider the independent auditor’s judgments about the quality and appropriateness, not just the acceptability, of the Company’s accounting principles and financial disclosure practices, as applied in its financial reporting, particularly about the degree of aggressiveness or conservatism of its accounting principles and underlying estimates and whether those principles are common practices or are minority practices.
 
  iii)   Consider and approve, if appropriate, major changes to the Company’s accounting principles and practices as suggested by management with the concurrence of the independent auditor and ensure that the accountants’ reasoning is described in determining the appropriateness of changes in accounting principles and disclosure.
G.   Process Improvement
  i)   Discuss with independent auditors (i) the auditors’ internal quality-control procedures; and (ii) any material issues raised by the most recent internal quality-control review, or peer review, of the auditors, or by any inquiry of investigation by governmental or professional authorities, within the preceding five years, respecting one or more independent audits carried out by the auditors, and any steps taken to deal with any such issues.
 
  ii)   Reviewing and approving hiring policies for employees or former employees of the past and present independent auditors.
 
  iii)   Establish regular and separate systems of reporting to the Audit Committee by each of management and the independent auditor regarding any significant judgments made in management’s preparation of the financial statements and the view of each as to appropriateness of such judgments.
 
  iv)   Review the scope and plans of the independent auditor’s audit and reviews prior to the audit and reviews being conducted. The Committee may authorize the independent auditor to perform supplemental reviews or audits as the Committee may deem desirable.
 
  v)   Following completion of the annual audit and quarterly reviews, review separately with each of management and the independent auditor any significant changes to planned procedures, any difficulties encountered during the course of the audit and reviews, including any restrictions on the scope of work or access to required information and the cooperation that the independent auditor received during the course of the audit and reviews.
 
  vi)   Review any significant disagreements among management and the independent auditor in connection with the preparation of the financial statements.
 
  vii)   Where there are significant unsettled issues the Committee shall ensure that there is an agreed course of action for the resolution of such matters.
 
  viii)   Review with the independent auditor and management significant findings during the year and the extent to which changes or improvements in financial or accounting practices, as approved by the Audit Committee, have been implemented. This review should be conducted at an appropriate time subsequent to implementation of changes or

- A5 -


 

      improvements, as decided by the Committee.
  ix)   Review activities, organizational structure, and qualifications of the CFO and the staff in the financial reporting area and see to it that matters related to succession planning within the Company are raised for consideration at the full Board.
H.   Ethical and Legal Compliance
  i)   Review management’s monitoring of the Company’s system in place to ensure that the Company’s financial statements, reports and other financial information disseminated to governmental organizations, and the public satisfy legal requirements.
 
  ii)   Review, with the Company’s counsel, legal and regulatory compliance matters, including corporate securities trading policies, and matters that could have a significant impact on the organization’s financial statements.
 
  iii)   Review implementation of compliance with the Sarbanes-Oxley Act, Ontario Securities Commission requirements and other legal requirements.
 
  iv)   Ensure that the CEO and CFO provide written certification with annual and interim financial statements and MD&A and the Annual Information Form.
I.   Risk Management
  i)   Make inquires of management and the independent auditors to identify significant business, political, financial and control risks and exposures and assess the steps management has taken to minimize such risk to the Company.
 
  ii)   Ensure that the disclosure of the process followed by the Board and its committees, in the oversight of the Company’s management of principal business risks, is complete and fairly presented.
 
  iii)   Review management’s program of risk assessment and steps taken to address significant risks or exposures, including insurance coverage.
J.   General
  i)   Conduct or authorize investigations into any matters within the Committee’s scope of responsibilities. The Committee shall be empowered to retain independent counsel, accountants and other professionals to assist it in the conduct of any investigation.
 
  ii)   Establish procedures for the receipt, retention and treatment of complaints received by the Company regarding accounting, internal accounting controls, or auditing matters; and the confidential, anonymous submission by employees of concerns regarding questionable accounting or auditing matters.
 
  iii)   Ensure disclosure in the Annual Information Form if, at any time since the commencement of most recently completed financial year, the issuer has relied on any possible exemptions for Audit Committees.
 
  iv)   Perform any other activities consistent with this Charter, the Company’s Articles and By-laws and governing law, as the Committee or the Board deems necessary or appropriate.

- A6 -


 

IV.   ACCOUNTABILITY
  A.   The Committee Chair has the responsibility to make periodic reports to the Board, as requested, on audit and financial matters relative to the Company.
 
  B.   The Committee shall report its discussions to the Board by maintaining minutes of its meetings and providing an oral report at the next Board meeting.
 
  C.   The minutes of the Audit Committee should be filed with the Corporate Secretary.

- A7 -