XML 27 R18.htm IDEA: XBRL DOCUMENT v3.22.2
Commitments And Contingencies
6 Months Ended
Jun. 30, 2022
Commitments And Contingencies Disclosure [Abstract]  
Commitments and Contingencies

10. COMMITMENTS AND CONTINGENCIES

As a result of issues generated in the ordinary course of business, DESC is involved in legal proceedings before various courts and is periodically subject to governmental examinations (including by regulatory authorities), inquiries and investigations. Certain legal proceedings and governmental examinations involve demands for unspecified amounts of damages, are in an initial procedural phase, involve uncertainty as to the outcome of pending appeals or motions, or involve significant factual issues that need to be resolved, such that it is not possible for DESC to estimate a range of possible loss. For such matters that DESC cannot estimate, a statement to this effect is made in the description of the matter. Other matters may have progressed sufficiently through the litigation or investigative processes such that DESC is able to estimate a range of possible loss. For legal proceedings and governmental examinations that DESC is able to reasonably estimate a range of possible losses, an estimated range of possible loss is provided, in excess of the accrued liability (if any) for such matters. DESC maintains various insurance programs, including general liability insurance coverage which provides coverage for personal injury or wrongful death cases. Any accrued liability is recorded on a gross basis with a receivable also recorded for any probable insurance recoveries. Estimated ranges of loss are inclusive of legal fees and net of any anticipated insurance recoveries. Any estimated range is based on currently available information and involves elements of judgment and significant uncertainties. Any estimated range of possible loss may not represent DESC’s maximum possible loss exposure. The circumstances of such legal proceedings and governmental examinations will change from time to time and actual results may vary significantly from the current estimate. For current proceedings not specifically reported below, management does not anticipate that the liabilities, if any, arising from such proceedings would have a material effect on DESC’s financial position, liquidity or results of operations.

Environmental Matters

DESC is subject to costs resulting from a number of federal, state and local laws and regulations designed to protect human health and the environment. These laws and regulations affect future planning and existing operations. They can result in increased capital, operating and other costs as a result of compliance, remediation, containment and monitoring obligations.

From a regulatory perspective, DESC continually monitors and evaluates its current and projected emission levels and strives to comply with all state and federal regulations regarding those emissions. DESC participates in the SO2 and NOX emission allowance programs with respect to coal plant emissions and also has constructed additional pollution control equipment at its coal-fired electric generating plants. These actions are expected to address many of the rules and regulations discussed herein.

Air

The CAA, as amended, is a comprehensive program utilizing a broad range of regulatory tools to protect and preserve the nation's air quality. At a minimum, states are required to establish regulatory programs to meet applicable requirements of the CAA. However, states may choose to develop regulatory programs that are more restrictive. Many of DESC’s facilities are subject to the CAA’s permitting and other requirements.

ACE Rule

In July 2019, the EPA published the final rule informally referred to as the ACE Rule, as a replacement for the Clean Power Plan. The ACE Rule regulated GHG emissions from existing coal-fired power plants pursuant to Section 111(d) of the CAA and required states to develop plans by July 2022 establishing unit-specific performance standards for existing coal-fired power plants. In January 2021, the U.S. Court of Appeals for the D.C. Circuit vacated the ACE Rule and remanded it to the EPA. This decision would take effect upon issuance of the court’s mandate. In March 2021, the court issued a partial mandate vacating and remanding all parts of the ACE Rule except for the portion of the ACE Rule that repealed the Clean Power Plan. In October 2021, the U.S. Supreme Court agreed to hear a challenge of the U.S. Court of Appeals for the D.C. Circuit’s decision on the ACE Rule. In June 2022, the U.S. Supreme Court reversed the D.C. Circuit’s decision on the ACE Rule and remanded the case back to the D.C. Circuit. Until the case is resolved by the D.C. Circuit and/or the EPA issues new rulemaking, DESC cannot predict an impact to its operations, financial condition and/or cash flows.

Carbon Regulations

In August 2016, the EPA issued a draft rule proposing to reaffirm that a source’s obligation to obtain a PSD or Title V permit for GHGs is triggered only if such permitting requirements are first triggered by non-GHG, or conventional, pollutants that are regulated by the New Source Review program, and exceed a significant emissions rate of 75,000 tons per year of CO2 equivalent emissions. Until the EPA ultimately takes final action on this rulemaking, DESC cannot predict the impact to its results of operations, financial condition and/or cash flows.

In December 2018, the EPA proposed revised Standards of Performance for Greenhouse Gas Emissions from New, Modified, and Reconstructed Stationary Sources. The proposed rule would amend the previous determination that the best system of emission reduction for newly constructed coal-fired steam generating units is no longer partial carbon capture and storage. Instead, the proposed revised best system of emission reduction for this source category is the most efficient demonstrated steam cycle (e.g., supercritical steam conditions for large units and subcritical steam conditions for small units) in combination with best operating practices. The

proposed revision to the performance standards for coal-fired steam generating units remains pending. Until the EPA ultimately takes final action on this rulemaking, DESC cannot predict the impact to its results of operations, financial condition and/or cash flows.

Water

The CWA, as amended, is a comprehensive program requiring a broad range of regulatory tools including a permit program to authorize and regulate discharges to surface waters with strong enforcement mechanisms. DESC must comply with applicable aspects of the CWA programs at its operating facilities.

Regulation 316(b)

 

In October 2014, the final regulations under Section 316(b) of the CWA that govern existing facilities and new units at existing facilities that employ a cooling water intake structure and that have flow levels exceeding a minimum threshold became effective. The rule establishes a national standard for impingement based on seven compliance options, but forgoes the creation of a single technology standard for entrainment. Instead, the EPA has delegated entrainment technology decisions to state regulators. State regulators are to make case-by-case entrainment technology determinations after an examination of five mandatory facility-specific factors, including a social cost-benefit test, and six optional facility-specific factors. The rule governs all electric generating stations with water withdrawals above two MGD, with a heightened entrainment analysis for those facilities over 125 MGD. DESC has five facilities that are subject to the final regulations. DESC is also working with the EPA and state regulatory agencies to assess the applicability of Section 316(b) to five hydroelectric facilities. DESC anticipates that it may have to install impingement control technologies at certain of these stations that have once-through cooling systems. DESC is currently evaluating the need or potential for entrainment controls under the final rule as these decisions will be made on a case-by-case basis after a thorough review of detailed biological, technological, and cost benefit studies. DESC is conducting studies and implementing plans as required by the rule to determine appropriate intake structure modifications at certain facilities to ensure compliance with this rule. While the impacts of this rule could be material to DESC’s results of operations, financial condition and/or cash flows, the existing regulatory framework in South Carolina provides rate recovery mechanisms that could substantially mitigate any such impacts for DESC.

 

Effluent Limitations Guidelines

 

In September 2015, the EPA released a final rule to revise the ELG Rule. The final rule established updated standards for wastewater discharges that apply primarily at coal and oil steam generating stations. Affected facilities are required to convert from wet to dry or closed cycle coal ash management, improve existing wastewater treatment systems and/or install new wastewater treatment technologies in order to meet the new discharge limits. In April 2017, the EPA granted two separate petitions for reconsideration of the final ELG Rule and stayed future compliance dates in the rule. Also in April 2017, the U.S. Court of Appeals for the Fifth Circuit granted the EPA’s request for a stay of the pending consolidated litigation challenging the rule while the EPA addresses the petitions for reconsideration. In September 2017, the EPA signed a rule to postpone the earliest compliance dates for certain waste streams regulations in the final ELG Rule from November 2018 to November 2020; however, the latest date for compliance for these regulations was December 2023. In October 2020, the EPA released the final rule that extends the latest dates for compliance. Individual facilities’ compliance dates will vary based on circumstances and the determination by state regulators and may range from 2021 to 2028. While the impacts of this rule could be material to DESC’s results of operations, financial condition and/or cash flows, as DESC expects that wastewater treatment technology retrofits and modifications at the Williams and Wateree generating stations will be required, the existing regulatory framework in South Carolina provides rate recovery mechanisms that could substantially mitigate any such impacts for DESC.

 

Capacity Use Area

In November 2019, a new CUA was established in the counties surrounding the Cope Generating Station (Western Capacity Use Area) under the South Carolina Groundwater Use and Reporting Regulation. Under the regulation any groundwater well in a CUA that withdraws above three million gallons per month must be permitted. The Cope Generating Station is located within this new Western Capacity Use Area. Cope has been using four deep groundwater wells for cooling water and other house loads since 1996. Prior to designation of the new Western Capacity Use Area, the wells at Cope Station were only required to be registered not permitted. As a result of this designation, Cope will need to restore the surface water equipment to operable status to reduce reliance on groundwater wells. This includes completion of 316(b) requirements, (including SCDHEC BACT determination and modification of the station national pollutant discharge elimination system permit) and extensive inspection, repair and/or replacement of the associated surface water withdrawal equipment which has been idle since 1996. While the impacts of this rule change are material to DESC’s results of operations, financial condition and/or cash flows, the existing regulatory framework in South Carolina provides rate recovery mechanisms that could substantially mitigate any such impacts for DESC.

 

Waste Management and Remediation

 

The operations of DESC are subject to a variety of state and federal laws and regulations governing the management and disposal of solid and hazardous waste, and release of hazardous substances associated with current and/or historical operations. The CERCLA, as

amended, and similar state laws, may impose joint, several and strict liability for cleanup on potentially responsible parties who owned, operated or arranged for disposal at facilities affected by a release of hazardous substances. In addition, many states have created programs to incentivize voluntary remediation of sites where historical releases of hazardous substances are identified and property owners or responsible parties decide to initiate cleanups.

 

From time to time, DESC may be identified as a potentially responsible party in connection with the alleged release of hazardous substances or wastes at a site. Under applicable federal and state laws, DESC could be responsible for costs associated with the investigation or remediation of impacted sites, or subject to contribution claims by other responsible parties for their costs incurred at such sites. DESC also may identify, evaluate and remediate other potentially impacted sites under voluntary state programs. Remediation costs may be subject to reimbursement under DESC’s insurance policies, rate recovery mechanisms, or both. Except as described below, DESC does not believe these matters will have a material effect on results of operations, financial condition and/or cash flows.

 

DESC has four decommissioned manufactured gas plant sites in South Carolina that are in various states of investigation, remediation and monitoring under work plans approved by, or under review by, the SCDHEC or the EPA. DESC anticipates that activities at these sites will continue through 2025 at an estimated cost of $26 million. DESC expects to recover costs arising from the remediation work at all four sites through rate recovery mechanisms and as of June 30, 2022, deferred amounts, net of amounts previously recovered through rates and insurance settlements, totaled $38 million and are included in regulatory assets.

 

Ash Pond and Landfill Closure Costs

 

In April 2015, the EPA enacted a final rule regulating CCR landfills, existing ash ponds that still receive and manage CCRs, and inactive ash ponds that do not receive, but still store, CCRs. DESC currently has inactive and existing CCR ponds and CCR landfills subject to the final rule at 3 different facilities. This rule created a legal obligation for DESC to retrofit or close all of its inactive and existing ash ponds over a certain period of time, as well as perform required monitoring, corrective action, and post-closure care activities as necessary.

 

In December 2016, legislation was enacted that creates a framework for EPA- approved state CCR permit programs. In August 2017, the EPA issued interim guidance outlining the framework for state CCR program approval. The EPA has enforcement authority until state programs are approved. The EPA and states with approved programs both will have authority to enforce CCR requirements under their respective rules and programs. In September 2017, the EPA agreed to reconsider portions of the CCR rule in response to two petitions for reconsideration. In March 2018, the EPA proposed certain changes to the CCR rule related to issues remanded as part of the pending litigation and other issues the EPA is reconsidering. Several of the proposed changes would allow states with approved CCR permit programs additional flexibility in implementing their programs. In July 2018, the EPA promulgated the first phase of changes to the CCR rule. In August 2018, the U.S. Court of Appeals for the D.C. Circuit issued its decision in the pending challenges of the CCR rule, vacating and remanding to the EPA three provisions of the rule. Until this matter is resolved and all phases of the CCR rule are promulgated, DESC is unable to precisely estimate potential incremental impacts or costs related to existing coal ash sites in connection with future implementation of the final CCR rule. While such amounts may be material to DESC’s results of operations, financial condition and/or cash flows, the existing regulatory framework in South Carolina provides rate recovery mechanisms that could substantially mitigate any such impacts.

 

Claims and Litigation

The following describes certain legal proceedings involving DESC relating primarily to events occurring before closing of the SCANA Combination. In addition, certain legal matters which have been resolved are discussed in Note 12 to the Consolidated Financial Statements in DESC’s Annual Report on Form 10-K for the year ended December 31, 2021. No reference to, or disclosure of, any proceeding, item or matter described below shall be construed as an admission or indication that such proceeding, item or matter is material. For certain of these matters, and unless otherwise noted therein, DESC is unable to estimate a reasonable range of possible loss and the related financial statement impacts, but for any such matter there could be a material impact to its results of operations, financial condition and/or cash flows. For the matters for which DESC is able to reasonably estimate a probable loss, the Consolidated Balance Sheets at June 30, 2022 and December 31, 2021 include reserves of $124 million and $211 million, respectively, and insurance receivables of $68 million and $85 million, respectively, included within other receivables. These balances at June 30, 2022 and December 31, 2021 include $68 million and $85 million, respectively, of offsetting reserves and insurance receivables related to personal injury or wrongful death cases which are currently pending. During both the three and six months ended June 30, 2022, charges included in DESC’s Consolidated Statements of Comprehensive Income were inconsequential. During the three and six months ended June 30, 2021, DESC’s Consolidated Statements of Comprehensive Income includes charges of $10 million ($8 million after-tax) and $70 million ($53 million after-tax), respectively, included within impairment of assets and other charges.

SCANA Shareholder Litigation

In February 2018, a purported class action was filed against Dominion Energy and certain former directors of SCANA and DESC in the State Court of Common Pleas in Richland County, South Carolina (the Metzler Lawsuit). The plaintiff alleges, among other things, that defendants violated their fiduciary duties to shareholders by executing a merger agreement that would unfairly deprive

plaintiffs of the true value of their SCANA stock, and that Dominion Energy aided and abetted these actions. Among other remedies, the plaintiff seeks to enjoin and/or rescind the merger. In February 2018, Dominion Energy removed the case to the U.S. District Court for the District of South Carolina and filed a Motion to Dismiss in March 2018. In September 2019, the U.S. District Court for the District of South Carolina granted the plaintiffs’ motion to consolidate the Metzler Lawsuit with another lawsuit regarding the SCANA Merger Agreement to which DESC is not a party. In October 2019, the plaintiffs filed an amended complaint against certain former directors and executive officers of SCANA and DESC, which stated substantially similar allegations to those in the initial lawsuits as well as an inseparable fraud claim. In November 2019, the defendants filed a motion to dismiss. In April 2020, the U.S. District Court for the District of South Carolina denied the motion to dismiss. In May 2020, SCANA filed a motion to intervene, which was denied in August 2020. In September 2020, SCANA filed a notice of appeal with the U.S. Court of Appeals for the Fourth Circuit. In June 2021, the parties reached an agreement in principle to settle this case, along with a related case to which DESC was not a party, subject to court approval, with no financial impact to DESC. In June 2022, this case was dismissed in connection with court approval of the related case to which DESC was not a party.

Employment Class Actions and Indemnification

In August 2017, a case was filed in the U.S. District Court for the District of South Carolina on behalf of persons who were formerly employed at the NND Project. In July 2018, the court certified this case as a class action. In February 2019, certain of these plaintiffs filed an additional case, which case has been dismissed and the plaintiffs have joined the case filed August 2017. The plaintiffs allege, among other things, that SCANA, DESC, Fluor Corporation and Fluor Enterprises, Inc. violated the Worker Adjustment and Retraining Notification Act in connection with the decision to stop construction at the NND Project. The plaintiffs allege that the defendants failed to provide adequate advance written notice of their terminations of employment and are seeking damages, which could be as much as $100 million for 100% of the NND Project. In January 2021, the U.S. District Court for the District of South Carolina granted summary judgment in favor of SCANA, DESC, Fluor Corporation and Fluor Enterprises, Inc. In February 2021, the plaintiffs filed a notice of appeal with the U.S. Court of Appeals for the Fourth Circuit. In November 2021, the U.S Court of Appeals for the Fourth Circuit affirmed the lower court ruling. In March 2022, the deadline to file an appeal to the Supreme Court of the United States expired.

In September 2018, a case was filed in the State Court of Common Pleas in Fairfield County, South Carolina by Fluor Enterprises, Inc. and Fluor Daniel Maintenance Services, Inc. against DESC and Santee Cooper. The plaintiffs make claims for indemnification, breach of contract and promissory estoppel arising from, among other things, the defendants' alleged failure and refusal to defend and indemnify the Fluor defendants in the aforementioned case. As a result of the ruling in favor of the defendants in the aforementioned case, DESC was able to resolve Fluor’s claims for an inconsequential amount.

Governmental Proceedings and Investigations

In June 2018, DESC received a notice of proposed assessment of approximately $410 million, excluding interest, from the SCDOR following its audit of DESC’s sales and use tax returns for the periods September 1, 2008 through December 31, 2017. The proposed assessment, which includes 100% of the NND Project, is based on the SCDOR’s position that DESC’s sales and use tax exemption for the NND Project does not apply because the facility will not become operational. In December 2020, the parties reached an agreement in principle in the amount of $165 million to resolve this matter. In June 2021, the parties executed a settlement agreement which allows DESC to fund the settlement amount through a combination of cash, shares of Dominion Energy common stock or real estate with an initial payment of at least $43 million in shares of Dominion Energy common stock. In August 2021, Dominion Energy issued 0.6 million shares of its common stock to satisfy DESC’s obligation for the initial payment under the settlement agreement. In May 2022, Dominion Energy issued an additional 0.9 million shares of its common stock to partially satisfy DESC’s remaining obligation under the settlement agreement. In June 2022, DESC requested approval from the South Carolina Commission to transfer certain real estate with a total settlement value of $51 million to satisfy its remaining obligation under the settlement agreement.  In July 2022, the South Carolina Commission voted to approve the request. A final order is pending. As a result, certain of the utility and non-utility properties representing $31 million of the value to be conveyed are expected to transfer by the end of 2022 and result in a gain of approximately $20 million. The transfer of the remaining real estate remains subject to the approval of FERC. If such approval is received, the transfer of such utility and non-utility properties is expected to result in a gain of approximately $20 million upon completion.

 

Nuclear Operations

Nuclear Insurance

Other than the item discussed below, there have been no significant changes regarding DESC’s nuclear insurance as described in Note 12 to the Consolidated Financial Statements in DESC’s Annual Report on Form 10-K for the year ended December 31, 2021.

 

During the second quarter of 2022, Dominion Energy reduced the levels of nuclear property insurance coverage for the reactor site at Summer from $2.75 billion to the NRC minimum requirement of $1.06 billion. As a result of this reduction in nuclear property insurance coverage, DESC’s maximum retrospective premium assessment for the current annual policy period was reduced to $11

million. Additionally, DESC maintains an excess property insurance policy with the European Mutual Association for Nuclear Insurance which provides coverage to Summer for property damage and outage costs resulting from an event of a non-nuclear origin. Dominion Energy reduced the levels of coverage from $415 million to $1 million.