XML 21 R11.htm IDEA: XBRL DOCUMENT v3.22.0.1
Rate and Other Regulatory Matters
12 Months Ended
Dec. 31, 2021
Regulated Operations [Abstract]  
Rate and Other Regulatory Matters

3.  RATE AND OTHER REGULATORY MATTERS

Regulatory Matters Involving Potential Loss Contingencies

As a result of issues generated in the ordinary course of business, DESC is involved in various regulatory matters. Certain regulatory matters may ultimately result in a loss; however, as such matters are in an initial procedural phase, involve uncertainty as to the outcome of pending reviews or orders, and/or involve significant factual issues that need to be resolved, it is not possible for DESC to estimate a range of possible loss. For regulatory matters that DESC cannot estimate, a statement to this effect is made in the description of the matter. Other matters may have progressed sufficiently through the regulatory process such that DESC is able to estimate a range of possible loss. For regulatory matters that DESC is able to reasonably estimate a range of possible losses, an estimated range of possible loss is provided, in excess of the accrued liability (if any) for such matters. Any estimated range is based on currently available information, involves elements of judgment and significant uncertainties and may not represent DESC’s maximum possible loss exposure. The circumstances of such regulatory matters will change from time to time and actual results may vary significantly from the current estimate. For current matters not specifically reported below, management does not anticipate that the outcome from such matters would have a material effect on DESC’s financial position, liquidity or results of operations.

FERC

In June 2019, DESC submitted the 2015 Task Order as a stand-alone rate schedule, which governs DESC’s provision of retail service to the DOE at the Savannah River Site. The 2015 Task Order also includes provisions that govern the operations and maintenance of certain transmission facilities, which DESC had determined to be services that are likely subject to FERC’s jurisdiction. DESC requested that FERC accept the 2015 Task Order for filing to become effective in August 2019 and accept the refund analysis included in the filing for amounts collected under the 2015 Task Order as well as under two prior task orders commencing in 1995 and each covering ten-year periods. During the second quarter of 2019, DESC recorded a $6 million ($4 million after-tax) charge primarily within interest charges in DESC’s Consolidated Statements of Comprehensive Income (Loss). In August 2019, DESC submitted a motion to withdraw the 2015 Task Order filing and related refund analysis as requested by FERC staff. As a result, DESC recorded a $10 million ($7 million after-tax) benefit, primarily within interest charges in DESC’s Consolidated Statements of Comprehensive Income (Loss) during the third quarter of 2019, to remove previously recorded reserves.

2017 Tax Reform Act

DESC’s provision of electric transmission service is pursuant to a FERC approved formula rate. In December 2019, FERC issued an order requiring transmission providers with transmission formula rates to account for the impacts of the 2017 Tax Reform Act on rates charged to customers. The order requires companies to include a mechanism to decrease or increase their income tax allowances to account for the 2017 Tax Reform Act and any other future changes in tax law, and to submit annual information reflecting the amortization of these excess deferred income taxes. DESC submitted a proposed update to its formula rate to FERC in May 2020. This matter is pending.

Other Regulatory Matters

South Carolina Electric Base Rate Case

In August 2020, DESC filed its retail electric base rate case and schedules with the South Carolina Commission. DESC proposed a non-fuel, base rate increase of $178 million, or 7.75% based on an adjusted test year data, effective on or after the first billing cycle of March 2021. The base rate increase was proposed to recover the significant investment in assets and operating resources required to serve an expanding customer base, maintain the safety, reliability and efficiency of DESC’s system and meet increasingly stringent reliability, security and environmental requirements for the benefit of South Carolina customers.  DESC presented an earned ROE of 5.90% based upon a fully-adjusted test period. The proposed rates would provide for an earned ROE equal to the current authorized earned ROE of 10.25% established in the previous rate case in 2012.  In January 2021, the South Carolina Commission approved a proposal made by the South Carolina Office of Regulatory Staff, and agreed to by DESC and other intervenors, to stay the base rate case due to the current economic conditions and to allow the parties more time to negotiate a settlement with a final order to be issued no later than August 2021.

In July 2021, DESC, the South Carolina Office of Regulatory Staff and other parties of record filed a comprehensive settlement agreement with the South Carolina Commission for approval. The comprehensive settlement agreement provides for a non-fuel, base rate increase of $62 million (resulting in a net increase of $36 million after considering an accelerated amortization of certain excess deferred income taxes) commencing with bills issued on September 1, 2021 and an authorized earned ROE of 9.50%. Additionally, DESC has agreed to commit up to $15 million to forgive retail electric customer balances that were more than 60 days past due as of May 31, 2021, and provide $15 million for energy efficiency upgrades and critical health and safety repairs to customer homes. Pursuant to the comprehensive settlement agreement, DESC would not file a retail electric base rate case prior to July 1, 2023, such that new rates would not be effective prior to January 1, 2024, absent unforeseen extraordinary economic or financial conditions that

may include changes in corporate tax rates. In July 2021, the South Carolina Commission voted to approve the comprehensive settlement agreement and issued its final order in August 2021.

In connection with this matter, DESC recorded charges of $249 million ($187 million after-tax) reflected within impairment of assets and other charges, including $237 million of regulatory assets associated with DESC’s purchases of its first mortgage bonds during 2019 that are no longer probable of recovery under the settlement agreement, and $18 million ($14 million after-tax) reflected within other income in its Consolidated Statements of Income for the year ended December 31, 2021.

Electric – Cost of Fuel

DESC’s retail electric rates include a cost of fuel component approved by the South Carolina Commission which may be adjusted periodically to reflect changes in the price of fuel purchased by DESC.

In February 2021, DESC filed with the South Carolina Commission a proposal to increase the total fuel cost component of retail electric rates. DESC’s proposed adjustment would increase annual base fuel component recoveries by approximately $36 million and is designed to recover DESC’s current base fuel costs, net of the existing over-collected balance, over the 12-month period beginning with the first billing cycle of May 2021. In addition, DESC proposed a decrease to its variable environmental component and an increase to its distributed energy resource component. In April 2021, the South Carolina Commission approved the filing.

In February 2022, DESC filed with the South Carolina Commission a proposal to increase the total fuel cost component of retail electric rates. DESC’s proposed adjustment is designed to recover DESC’s current base fuel costs, including its existing under-collected balance, over the 12-month period beginning with the first billing cycle of May 2022. DESC also proposed to apply $66 million representing the net balance of funds associated with the monetization of the bankruptcy settlement with Toshiba Corporation following the satisfaction of liens against NND Project property recorded in regulatory liabilities, as a reduction to its under-collected base fuel cost balance. In addition, DESC proposed an increase to its variable environmental and avoided capacity cost component. The net effect is a proposed annual increase of $143 million. This matter is pending.

Electric – Other

DESC has approval for a DSM rider through which it recovers expenditures related to its DSM programs. In January 2021, DESC filed an application with the South Carolina Commission seeking approval to recover $48 million of costs and net lost revenues associated with these programs, along with an incentive to invest in such programs. In April 2021, the South Carolina Commission approved the filing. In connection with the approval of the comprehensive settlement agreement in the South Carolina base rate case discussed above, the net lost revenue component of the DSM rider was adjusted resulting in a recovery of $43 million commencing with bills issued on September 1, 2021.

In January 2022, DESC filed an application with the South Carolina Commission seeking approval to recover $60 million of costs and net lost revenues associated with these programs, along with an incentive to invest in such programs. This matter is pending.

DESC utilizes a pension costs rider approved by the South Carolina Commission which is designed to allow recovery of projected pension costs, including under-collected balances or net of over-collected balances, as applicable. The rider is typically reviewed for adjustment every 12 months with any resulting increase or decrease going into effect beginning with the first billing cycle in May. In February 2021, DESC requested that the South Carolina Commission approve an adjustment to this rider to decrease annual revenue by less than $1 million. In April 2021, the South Carolina Commission approved the filing. In February 2022, DESC requested that the South Carolina Commission approve an adjustment to this rider to decrease annual revenue by $12 million. This matter is pending.

Natural Gas Rates

In June 2021, DESC filed with the South Carolina Commission its monitoring report for the 12-month period ended March 31, 2021 with a total revenue requirement of $426 million. This represents a $9 million overall annual increase to its natural gas rates under the terms of the RSA effective with the first billing cycle of November 2021. In October 2021, the South Carolina Commission issued an order approving a total revenue requirement of $424 million effective with the first billing cycle of November 2021. This represents a $7 million overall annual increase to DESC’s natural gas rates.

In November 2021, DESC filed an application with the South Carolina Commission seeking approval to create DSM programs for DESC's residential and commercial natural gas customers and a new rider to retail gas rates for the recovery of the associated program costs and a shared savings incentive of 9.9%. The application also includes a notice of intent that DESC would seek to recover the net lost revenues resulting from the proposed DSM programs through the annual RSA proceeding. This matter is pending.

DESC's natural gas tariffs include a PGA that provides for the recovery of actual gas costs incurred, including transportation costs. DESC’s gas rates are calculated using a methodology which may adjust the cost of gas monthly based on a 12-month rolling average, and its gas purchasing policies and practices are reviewed annually by the South Carolina Commission.

Regulatory Assets and Regulatory Liabilities

Rate-regulated utilities recognize in their financial statements certain revenues and expenses in different periods than do other enterprises. As a result, DESC has recorded regulatory assets and regulatory liabilities which are summarized in the following table. Except for NND Project costs and certain other unrecovered plant costs, substantially all regulatory assets are either explicitly excluded from rate base or are effectively excluded from rate base due to their being offset by related liabilities.

 

At December 31,

 

2021

 

 

2020

 

(millions)

 

 

 

 

 

 

 

 

Regulatory assets:

 

 

 

 

 

 

 

 

NND Project costs(1)

 

$

138

 

 

 

138

 

Deferred employee benefit plan costs(2)

 

 

8

 

 

 

9

 

Other unrecovered plant(3)

 

 

16

 

 

 

14

 

DSM programs(4)

 

 

23

 

 

 

29

 

AROs(5)

 

 

2

 

 

 

2

 

Cost of fuel and purchased gas under-collections(6)

 

 

126

 

 

 

1

 

Other

 

 

48

 

 

 

36

 

Regulatory assets - current

 

 

361

 

 

 

229

 

NND Project costs(1)

 

 

2,226

 

 

 

2,364

 

AROs(5)

 

 

311

 

 

 

309

 

Cost of reacquired debt(7)

 

 

10

 

 

 

243

 

Deferred employee benefit plan costs(2)

 

 

106

 

 

 

159

 

Deferred losses on interest rate derivatives(8)

 

 

295

 

 

 

308

 

Other unrecovered plant(3)

 

 

57

 

 

 

61

 

DSM programs(4)

 

 

45

 

 

 

46

 

Environmental remediation costs(9)

 

 

30

 

 

 

20

 

Deferred storm damage costs(10)

 

 

38

 

 

 

45

 

Deferred transmission operating costs(11)

 

 

77

 

 

 

63

 

Other(12)

 

 

128

 

 

 

108

 

Regulatory assets - noncurrent

 

 

3,323

 

 

 

3,726

 

Total regulatory assets

 

$

3,684

 

 

$

3,955

 

Regulatory liabilities:

 

 

 

 

 

 

 

 

Monetization of guaranty settlement(13)

 

$

67

 

 

 

67

 

Income taxes refundable through future rates(14)

 

 

42

 

 

 

21

 

Reserve for refunds to electric utility customers(15)

 

 

113

 

 

 

128

 

Cost of fuel and purchased gas over-collections(6)

 

 

 

 

 

58

 

Derivatives(16)

 

 

18

 

 

 

 

Other

 

 

5

 

 

 

9

 

Regulatory liabilities - current

 

 

245

 

 

 

283

 

Monetization of guaranty settlement(13)

 

 

831

 

 

 

903

 

Income taxes refundable through future rates(14)

 

 

903

 

 

 

919

 

Asset removal costs(17)

 

 

570

 

 

 

564

 

Deferred gains on interest rate derivatives(8)

 

 

67

 

 

 

69

 

Reserve for refunds to electric utility customers(15)

 

 

425

 

 

 

540

 

Derivatives(16)

 

 

131

 

 

 

 

Other

 

 

9

 

 

 

10

 

Regulatory liabilities - noncurrent

 

 

2,936

 

 

 

3,005

 

Total regulatory liabilities

 

$

3,181

 

 

$

3,288

 

 

(1)

Reflects expenditures associated with the NND Project, which pursuant to the SCANA Merger Approval Order, will be recovered from electric service customers over a 20-year period ending in 2039. See Note 12 for more information.

(2)

Employee benefit plan costs have historically been recovered as they have been recorded under GAAP. Deferred employee benefit plan costs represent amounts of pension and other postretirement benefit costs which were accrued as liabilities and treated as regulatory assets pursuant to FERC guidance, and costs deferred pursuant to specific South Carolina Commission regulatory orders. DESC expects to recover deferred pension costs through utility rates over periods through 2044. DESC expects to recover other deferred benefit costs through utility rates, primarily over average service periods of participating employees up to 11 years.

(3)

Represents the carrying value of coal-fired generating units, including related materials and supplies inventory, retired from service prior to being fully depreciated. DESC is amortizing these amounts through cost of service rates following depreciation amounts that were designed to recover the retired units cost over their previous estimated remaining useful lives, which has been estimated to be through 2025. Based on current projections of remaining decommissioning costs, projected recovery is expected to extend through 2029. In addition, amounts include unrecovered costs of existing meters and equipment retired from service prior to being fully depreciated as part of the Advanced Metering Infrastructure project, which are being recovered through rates through 2028. This amount also includes certain inventory and preliminary survey and investigation charges being amortized over five years related to the transition or conversion from coal to gas fired generation at certain facilities. Unamortized amounts are included in rate base and are earning a current return.

(4)

Represents deferred costs associated with electric demand reduction programs, and such deferred costs are currently being recovered over three years through an approved rate rider.

(5)

Represents deferred depreciation and accretion expense related to legal obligations associated with the future retirement of generation, transmission and distribution properties. The AROs primarily relate to DESC’s electric generating facilities, including Summer, and are expected to be recovered over the related property lives and periods of decommissioning which may range up to approximately 105 years.

(6)

Represents amounts under- or over-collected from customers pursuant to the cost of fuel components approved by the South Carolina Commission.

(7)

In 2021, DESC recorded a charge of $237 million ($178 million after-tax) in impairment of assets and other charges, reflected in the Corporate and Other segment, to write-off the balance of a regulatory asset that is no longer probable of recovery under the settlement agreement approved in DESC’s retail electric base rate case. See South Carolina Electric Base Rate Case discussed above for more information.

(8)

Represents (i) the changes in fair value and payments made or received upon settlement of certain interest rate derivatives designated as cash flow hedges and (ii) the changes in fair value and payments made or received upon settlement of certain other interest rate derivatives not so designated. The amounts recorded with respect to (i) are expected to be amortized to interest expense over the lives of the underlying debt through 2043.The amounts recorded with respect to (ii) are expected to be similarly amortized to interest expense through 2065.

(9)

Reflects amounts associated with the assessment and clean-up of sites currently or formerly owned by DESC. Such remediation costs are expected to be recovered over periods of up to 22 years. See Note 12 for more information.

(10)

Represents storm restoration costs for which DESC expects to receive future recovery through customer rates over approximately 10 years pursuant to the settlement agreement approved in DESC’s retail electric base rate case. Unamortized amounts are included in rate base and are earning a current return.

(11)

Includes deferred depreciation and property taxes associated with certain transmission assets for which DESC expects recovery from customers through future rates over approximately 42 years pursuant to the settlement agreement approved in DESC’s retail electric base rate case. Unamortized amounts are included in rate base and earning a current return. See Note 12 for more information.

(12)

Various other regulatory assets are expected to be recovered through rates over varying periods through 2047.

(13)

Represents proceeds related to the monetization of the Toshiba Settlement. In accordance with the SCANA Merger Approval Order, this balance, net of amounts that may be required to satisfy liens, will be refunded to electric customers over a 20-year period ending in 2039. See Note 12 for more information.

(14)

Includes (i) excess deferred income taxes arising from the remeasurement of deferred income taxes in connection with the enactment of the 2017 Tax Reform Act (certain of which are protected under normalization rules and will be amortized over the remaining lives of related property, and certain of which will be amortized to the benefit of customers over prescribed periods as instructed by regulators) and (ii) deferred income taxes arising from investment tax credits, offset by (iii) deferred income taxes that arise from utility operations that have not been included in customer rates (a portion of which relate to depreciation and are expected to be recovered over the remaining lives of the related property which may range up to 85 years). See Note 7 for more information.

(15)

Reflects amounts previously collected from retail electric customers of DESC for the NND Project to be credited to customers over an estimated 11-year period effective February 2019 in connection with the SCANA Merger Approval Order. See Note 12 for more information.

(16)

For jurisdictions subject to cost-based rate regulation, changes in the fair value of derivative instruments result in the recognition of regulatory assets or regulatory liabilities as they are expected to be recovered from or refunded to customers.

(17)

Represents estimated net collections through depreciation rates of amounts to be expended for the removal of assets in the future.

 

Regulatory assets have been recorded based on the probability of their recovery. All regulatory assets represent incurred costs that may be deferred under GAAP for regulated operations. The South Carolina Commission or the FERC has reviewed and approved through specific orders certain of the items shown as regulatory assets. In addition, regulatory assets include, but are not limited to, certain costs which have not been specifically approved for recovery by one of these regulatory agencies, including deferred transmission operating costs that are the subject of regulatory proceedings as discussed in Note 12. While such costs are not currently being recovered, management believes that they would be allowable under existing rate-making concepts embodied in rate orders or applicable state law and expects to recover these costs through rates in future periods.