COMMITMENTS AND CONTINGENCIES (Details)
3 Months Ended 6 Months Ended 12 Months Ended
Jun. 30, 2017
USD ($)
Jun. 30, 2017
USD ($)
Dec. 31, 2017
Dec. 31, 2016
Environmental        
Goal For Reduced Carbon Dioxide Emissions From 2005 Levels By 2030 Under Clean Air Act   32.00%    
NPDES permit renewal permit period   five    
Nuclear Generation        
Impairment of Retained Interest $ 6.2      
Summer Station New Units [Domain]        
Nuclear Generation        
Guaranty Fee Income   $ 2.2    
SCEG        
Nuclear Insurance        
Maximum liability assessment per reactor for each nuclear incident   127,300,000    
Maximum Insurance Coverage For Each Nuclear Plant by ANI 450,000,000 450,000,000    
Federal Limit on Public Liability Claims from Nuclear Incident Approximate   13,400,000,000    
Maximum Federal Limit on Public Liability Claims Per Reactor for Each Year   18,900,000    
Maximum Federal Limit on Public Liability Claims per Reactor for each Nuclear Incident at 2/3   84,800,000    
Maximum Federal Limit on Public Liability Claims Per Incident for Each Year   $ 12,600,000    
Inflation adjustment period for nuclear insurance   5    
Maximum loss for a single nuclear incident   $ 2,750,000,000    
NEIL Maximum Insurance Coverage To Nuclear Facility For Property Damage And Outage Costs From Non-Nuclear Event   2,330,000,000    
NEIL Maximum Insurance Coverage of Accidental Property Damage 500,000,000 500,000,000    
EMANI Maximum Retrospective Premium Assessment   1,900,000    
EMANI Maximum Insurance Coverage for Summer Station Unit 1 For Property Damage And Outage Costs From Non-Nuclear Event   415,000,000    
NEIL Maximum Prosepective Insurance Premium Per Nuclear Incident   45,400,000    
NEIL Maximum Insurance Coverage to Nuclear Facility for Property Damage and Outage Costs 2,750,000,000 2,750,000,000    
Environmental        
Environmental Remediation Costs Recognized in Regulatory Assets $ 25,000,000 $ 25,000,000    
Number of MGP decommissioned sites that contain residues of byproduct chemicals 4 4    
Number Of States Required To Reduce Emissions Under CSAPR 28 28    
Site Contingency MGP Estimated Environmental Remediation Costs   $ 9,900,000    
Nuclear Generation        
Estimate of aggregate amount of subcontractor and vendor liens filed   142,000,000    
Aggregate amount of subcontractor and vendor liens paid   27,500,000    
EPC Contract Amendment, Fixed Price Option, Price For New Nuclear Construction After June 2015   3,345,000,000    
Guaranty Fee Income   1.2    
November 2016 SCPSC Approved Project Costs above SCPSC 2015 order   831,000,000    
Total New Nuclear Project Cost Nov 2016, excludes AFC and escalation $ 6,800,000,000 6,800,000,000    
Total New Nuclear Project Cost 2016, including AFC and escalation 7,700,000,000 7,700,000,000    
Public Utilities, Authorized Allowable Return on Common Equity, Percentage       10.50%
Summer Station New Units and Transmission Assets [Domain]        
Nuclear Generation        
Jointly Owned Utility Plant, Ownership Amount of Construction Work in Progress 4,900,000,000 4,900,000,000    
Summer Station New Units [Domain]        
Nuclear Generation        
jointly owned utility plant ownership, construction financing cost $ 3,800,000,000 $ 3,800,000,000    
Jointly Owned Utility Plant, Proportionate Ownership Share 55.00% 55.00%    
Estimate of aggregate amount of subcontractor and vendor liens filed   $ 258,000,000    
Aggregate amount of subcontractor and vendor liens paid   50,000,000    
Nuclear Production Tax Credits   1,400,000,000    
EPC Contract Amendment, Fixed Price Option, Price For New Nuclear Construction After June 2015   $ 6,082,000,000    
Scenario, Forecast [Member] | SCEG        
Nuclear Generation        
Public Utilities, Authorized Allowable Return on Common Equity, Percentage     10.25%