COMMITMENTS AND CONTINGENCIES Nuclear (Details) (USD $)
In Millions, unless otherwise specified
12 Months Ended
Dec. 31, 2014
Dec. 31, 2021
Dec. 31, 2020
Dec. 31, 2019
CapitalCosts [Member]        
ForecastedCapitalCostsApproved2012Order $ 4,548scg_ForecastedCapitalCostsApproved2012Order
/ scg_CapitalCostsAxis
= scg_CapitalCostsMember
     
Grossconstructioncosts [Member]        
ForecastedCapitalCostsApproved2012Order 5,755scg_ForecastedCapitalCostsApproved2012Order
/ scg_CapitalCostsAxis
= scg_GrossconstructioncostsMember
     
SCE&G        
Additional ownership in new units   0.00%scg_Additionalownershipinnewunits
/ dei_LegalEntityAxis
= scg_ScegMember
0.00%scg_Additionalownershipinnewunits
/ dei_LegalEntityAxis
= scg_ScegMember
0.00%scg_Additionalownershipinnewunits
/ dei_LegalEntityAxis
= scg_ScegMember
Total Construction Milestones 146scg_TotalConstructionMilestones
/ dei_LegalEntityAxis
= scg_ScegMember
     
Milestone Schedule Contingency Period 18      
Completed Construction Milestones 101scg_CompletedConstructionMilestones
/ dei_LegalEntityAxis
= scg_ScegMember
     
MIlestones Extended Three      
Additional ownership in new units, dollars 500scg_Additionalownershipinnewunitsdollars
/ dei_LegalEntityAxis
= scg_ScegMember
     
Summer Station New Units [Domain]        
jointly owned utility plant ownership, construction financing cost 2,425scg_Jointlyownedutilityplantownershipconstructionfinancingcost
/ us-gaap_JointlyOwnedUtilityPlantAxis
= scg_SummerStationNewUnitsDomain
     
Jointly Owned Utility Plant, Construction Delay, Preliminary Cost Estimate 660scg_JointlyOwnedUtilityPlantConstructionDelayPreliminaryCostEstimate
/ us-gaap_JointlyOwnedUtilityPlantAxis
= scg_SummerStationNewUnitsDomain
     
Jointly Owned Utility Plant, Owner's Cost Per Month Caused by Delays, Estimated $ 10scg_JointlyOwnedUtilityPlantOwnersCostPerMonthCausedbyDelaysEstimated
/ us-gaap_JointlyOwnedUtilityPlantAxis
= scg_SummerStationNewUnitsDomain