RATE AND OTHER REGULATORY MATTERS (Details) (USD $)
In Millions, unless otherwise specified
9 Months Ended 3 Months Ended 9 Months Ended 12 Months Ended 12 Months Ended 3 Months Ended 9 Months Ended 12 Months Ended 9 Months Ended 9 Months Ended 9 Months Ended
Sep. 30, 2014
Sep. 30, 2013
Dec. 31, 2013
Sep. 30, 2014
SCEG
Sep. 30, 2014
SCEG
Sep. 30, 2013
SCEG
May 01, 2015
SCEG
Dec. 31, 2013
SCEG
Dec. 31, 2012
SCEG
Mar. 31, 2014
SCEG
Mar. 31, 2013
SCEG
Mar. 31, 2012
SCEG
Dec. 31, 2013
PSNC Energy
Sep. 30, 2014
PSNC Energy
Sep. 30, 2014
Pension Costs [Member]
Dec. 31, 2013
Pension Costs [Member]
Dec. 31, 2012
Pension Costs [Member]
SCEG
Sep. 30, 2014
Pension Costs [Member]
SCEG
Dec. 31, 2013
Pension Costs [Member]
SCEG
Sep. 30, 2014
Other Regulatory Assets [Member]
Dec. 31, 2013
Other Regulatory Assets [Member]
Sep. 30, 2014
Other Regulatory Assets [Member]
SCEG
Dec. 31, 2013
Other Regulatory Assets [Member]
SCEG
Sep. 30, 2014
Deferred Pollution Control Costs
Dec. 31, 2013
Deferred Pollution Control Costs
Dec. 31, 2013
Deferred Pollution Control Costs
SCEG
Sep. 30, 2014
Franchise agreement Costs
Dec. 31, 2013
Franchise agreement Costs
Sep. 30, 2014
Franchise agreement Costs
SCEG
Dec. 31, 2013
Franchise agreement Costs
SCEG
Sep. 30, 2014
Planned major maintenance [Member]
SCEG
Sep. 30, 2014
Storm damage reserve [Member]
Rate Matters [Line Items]                                                                
Amounts Recovered Through Electric Rates to offset Nuclear Related Outage Costs         $ 17.2                                                      
Net Lost Revenues associated with DSM programs         6.6                                                      
Fuel Costs         10.3                                                      
Undercollected balance fuel               46                                                
Carrying costs on deferred income tax assets       1.6 4.1                                                      
Storm reserve applied to offset storm damage costs                                                               16.2
Carrying cost recovery (7) 0     (7) 0                                                    
Regulatory Assets, Noncurrent 1,564.0   1,360.0 1,506.0 1,506.0     1,303.0           1.1 222.0 238.0   201.0 215.0 52.0 48.0 42.0 39.0 36.0 37.0 37.0 27.0 31.0 27.0 31.0    
Number of coal fired units to be retired                 6   6                                          
Public Utilities, Percent Increase (Decrease) in Retail Electric Rates         2.80%     2.90% 2.30%                                              
Allowable return on common equity (as a percent)         11.00%                                                      
Demand Side Management Program Costs, Noncurrent                   15.4 16.9 19.6                                        
Regulatory Asset Recovery Assessments             12                                                  
Increase (decrease) in retail electric rate requested under the BLRA         66.2     67.2 52.1                                              
Public Utilities, Percent Increase (Decrease) in Retail Natural Gas Rates         0.60%       2.10%                                              
Public Utilities changes in Retail Natural Gas Rates Approved under RSA         2.6       7.5                                              
Public Utilities, Rate Calculation Basis         12-month rolling average               12                                      
Regulatory Noncurrent Asset Amortization Period                                 30 12 14 33   50                    
Amounts Recovered through Electric Rates to offset Turbine Expense                                                             18.4  
Public Utilities Base Fuel under Collected Balance Recovery Period 12       12                                                      
Defined Benefit Plan, Deferred Debit Attributable to Share of Regulatory Authority                                 63 14                            
Derivative, Gain on Derivative         17.8                                                      
Storm Damage Reserve Cost Applied         5.0                                                      
Reduction to Net Lost Revenues from DSM programs         25.00%                                                      
Reduction to DSM Program costs deferred         6.6                                                      
Number of Units retired               3                                                
Demand side management recovery period         10                                                      
Storm Damage Reserve Applied To Offset Net Lost Margin Related To DSM                                                               5.0
Amount Allowed to be Recovered through Electric Rates to Offset Incremental Storm Damage Costs         $ 100                                                     $ 100