SCEG
             
Nuclear Insurance              
Federal Limit on Public Liability Claims from Nuclear Incident Approximate $ 13,600,000,000            
Maximum Insurance Coverage for each Nuclear Plant by ANI 375,000,000            
Maximum liability assessment per reactor for each nuclear incident 127,300,000            
Maximum Federal Limit on Public Liability Claims Per Incident for Each Year 12,600,000            
Maximum yearly assessment per reactor 18,900,000            
Maximum Federal Limit on Public Liability Claims per Reactor for each Nuclear Incident at 2/3 84,800,000            
Inflation adjustment period for nuclear insurance 5            
Maximum retrospective insurance premium per nuclear incident 41,600,000            
Maximum amount of coverage to nuclear facility for property damage and outage costs 2,750,000,000            
Maximum amount of coverage for accidental property damage 500,000,000            
Maximum loss for a single nuclear incident 2,750,000,000            
Environmental              
Number of MGP decommissioned sites that contain residues of byproduct chemicals 4            
Site Contingency MGP Estimated Environmental Remediation Costs 20,200,000            
Deferred costs net of costs previously recovered through rates and insurance settlements included in regulatory assets 36,700,000            
Nuclear Generation              
Estimated cash outflow for plant costs and related transmission infrastructure costs of nuclear electric generation site 5,400,000,000            
Current ownership share in New Unit 55.00%            
Total additional ownership in new units 5.00%            
Additional ownership in new units         2.00% 2.00% 1.00%
Jointly owned plant cost of additional 5%     500,000,000        
Number of states required to reduce emissions to attain mandated levels       28      
Estimated Delay costs related to New Units 200,000,000            
Est Delay cost for new unit $ 200,000,000            
Total Construction Milestones   146          
Milestone Schedule Contingency Period   18          
Completed Construction Milestones   98          
Delayed Construction Milestones   44          
Minimum Identified Delay Period   2          
Maximum Identified Delay Period   17          
PSNC Energy
             
Environmental              
Number of MGP sites requiring cleanup 5