XML 34 R24.htm IDEA: XBRL DOCUMENT v3.23.1
Owned Inventory (Tables)
6 Months Ended
Mar. 31, 2023
Inventory Disclosure [Abstract]  
Schedule of inventory
The components of our owned inventory are as follows as of March 31, 2023 and September 30, 2022:
in thousandsMarch 31, 2023September 30, 2022
Homes under construction$724,193 $785,742 
Land under development774,994 731,190 
Land held for future development19,879 19,879 
Land held for sale20,253 15,674 
Capitalized interest113,886 109,088 
Model homes88,751 76,292 
Total owned inventory$1,741,956 $1,737,865 
Schedule of total owned inventory, by segment
Total owned inventory by reportable segment is presented in the table below as of March 31, 2023 and September 30, 2022:
in thousands
Projects in
Progress(a)
Land Held for Future DevelopmentLand Held for SaleTotal Owned
Inventory
March 31, 2023
West$889,336 $3,483 $19,577 $912,396 
East333,355 10,888  344,243 
Southeast297,505 5,508 676 303,689 
Corporate and unallocated(b)
181,628 

  181,628 
Total$1,701,824 $19,879 $20,253 $1,741,956 
September 30, 2022
West$934,309 $3,483 $14,998 $952,790 
East313,613 10,888 — 324,501 
Southeast284,424 5,508 676 290,608 
Corporate and unallocated(b)
169,966 — — 169,966 
Total$1,702,312 $19,879 $15,674 $1,737,865 
(a) Projects in progress include homes under construction, land under development, capitalized interest, and model home categories from the preceding table.
(b) Projects in progress amount includes capitalized interest and indirect costs that are maintained within our Corporate and unallocated segment.
Schedule of inventory impairments and abandonment charges, by reportable segment
The following table presents, by reportable segment, our total impairment and abandonment charges for the periods presented:
 Three Months Ended March 31,Six Months Ended March 31,
in thousands2023202220232022
Land Held for Sale:
West$ $440 $ $440 
Total impairment charges on land held for sale$ $440 $ $440 
Abandonments:
West$111 $12 $147 $12 
East — 154 — 
Southeast 483  483 
Total abandonments charges$111 $495 $301 $495 
Total impairments and abandonment charges$111 $935 $301 $935 
Summary of interests in lot option agreements
The following table provides a summary of our interests in lot option agreements as of March 31, 2023 and September 30, 2022:
March 31, 2023September 30, 2022
in thousands
Deposits and non-refundable pre-acquisition costs incurred(a)
$152,008 $142,433 
Remaining purchase price if lot option agreements are exercised$789,333 $827,600 
(a) Amount is included as a component of land under development within our owned inventory in the condensed consolidated balance sheet.