XML 51 R36.htm IDEA: XBRL DOCUMENT v3.10.0.1
Subsequent Events
12 Months Ended
Dec. 31, 2018
Subsequent Events [Abstract]  
Subsequent Events
Subsequent Events
We signed a settlement agreement with the sellers ("Claimant") of SAM on January 30, 2019 for claims arising over the timing of the earnout consideration outlined in the purchase agreement. As part of the settlement, the parties agreed that the earnout consideration would be payable during the first quarter 2020, unless earlier payment is required as per the terms of the purchase agreement, and Belden would immediately pay the Claimant $0.9 million for interest and fees incurred, which we recognized in selling, general, and administrative expenses in our 2018 financial statements.