XML 35 R25.htm IDEA: XBRL DOCUMENT v3.19.1
LEASES (Tables)
3 Months Ended
Mar. 31, 2019
Leases [Abstract]  
Schedule of Components of Lease Cost, Weighted-average Remaining Lease Term and Discount Rate The components of lease cost for the three months ended March 31, 2019 were as follows (in thousands):
Operating leases
$
509

Short-term leases
66

Total lease cost
$
575

The weighted-average remaining lease term and discount rate related to operating leases as of March 31, 2019 were as follows:
Weighted-average remaining lease term (in years)
3.4

Weighted-average discount rate
5.5
%
Schedule of Annual Scheduled Operating Lease Payments
The annual scheduled lease payments of our operating lease liabilities as of March 31, 2019 were as follows (in thousands):
Remainder of 2019
$
1,435

2020
1,566

2021
530

2022
403

2023
247

Thereafter
400

Total lease payments
$
4,581

Less: imputed interest
(474
)
Present value of lease liabilities
$
4,107