XML 297 R49.htm IDEA: XBRL DOCUMENT v3.20.1
Commitments and Contingencies (Tables)
12 Months Ended
Dec. 31, 2019
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Joint Ventures
Teekay LNG's share of commitments to fund newbuilding and other construction contract costs as at December 31, 2019 are as follows:

 
Total
2020
2021
2022
 
$
$
$
$
Consolidated LNG carriers (i)
49,652

11,979

22,382

15,291

Bahrain LNG Joint Venture (ii)
11,351

11,351



 
61,003

23,330

22,382

15,291


(i)
In June 2019, Teekay LNG entered into an agreement with a contractor to supply equipment on certain of its LNG carriers in 2021 and 2022, for an estimated installed cost of approximately $60.6 million. As at December 31, 2019, the estimated remaining cost of this installation is $49.7 million.
(ii)
Teekay LNG has a 30% ownership interest in the Bahrain LNG Joint Venture which has an LNG receiving and regasification terminal in Bahrain. The Bahrain LNG Joint Venture has secured undrawn debt financing of $34 million, of which $10 million relates to Teekay LNG's proportionate share of the commitments included in the table above.