(22) Commitments and Contingencies

We lease certain of our facilities and equipment under non-cancelable operating and finance leases. See Note 5.

We have an inventory purchase commitment with an assembling manufacturer. See Note 14.

Supply commitments totaled $55,317 and $53,562 as of December 31, 2020 and 2019, respectively. Commitments for printer assemblies and inventory items at December 31, 2020 and 2019 were $27,030 and $34,570, respectively. Commitments for operating costs and capital expenditures at December 31, 2020 and 2019 were $28,287 and $18,992, respectively.
Indemnification

In the normal course of business, we periodically enter into agreements to indemnify customers or suppliers against claims of intellectual property infringement made by third parties arising from the use of our products. Historically, costs related to these indemnification provisions have not been significant, and we are unable to estimate the maximum potential impact of these indemnification provisions on its future results of operations.

To the extent permitted under Delaware law, we indemnify our directors and officers for certain events or occurrences while the director or officer is, or was, serving at our request in such capacity, subject to limited exceptions. The maximum potential amount of future payments we could be required to make under these indemnification obligations is unlimited; however, we have directors and officers insurance coverage that may enable us to recover future amounts paid, subject to a deductible and the policy limits. There is no assurance that the policy limits will be sufficient to cover all damages, if any.

Litigation

Export Controls and Government Contracts Compliance Matter

In October 2017, we received an administrative subpoena from the Bureau of Industry and Security of the Department of Commerce (“BIS”) requesting the production of records in connection with possible violations of U.S. export control laws, including with regard to our Quickparts.com, Inc. subsidiary. In addition, while collecting information responsive to the above-referenced subpoena, our internal investigation identified potential violations of the International Traffic in Arms Regulations (“ITAR”) administered by the Directorate of Defense Trade Controls of the Department of State (“DDTC”) and potential violations of the Export Administration Regulations administered by the BIS.
On June 8, 2018 and thereafter, we submitted voluntary disclosures to BIS and DDTC identifying numerous potentially unauthorized exports of technical data. As part of our ongoing review of trade compliance risks and our cooperation with the government, on November 20, 2019, we submitted to the U.S. Treasury Department’s Office of Foreign Assets Control (“OFAC”) an initial notice of voluntary disclosure regarding potential violations of economic sanctions related to Iran. We continued to investigate this issue and filed a final disclosure with OFAC on May 20, 2020. We have and will continue to implement compliance enhancements to our export controls, trade sanctions, and government contracting compliance program to address the issues identified through our ongoing internal investigation and will cooperate with DDTC and BIS, as well as the U.S. Departments of Justice, Defense, Homeland Security and Treasury in their ongoing reviews of these matters. In connection with these ongoing reviews, in August 2020, the Company received two federal grand jury subpoenas issued by the U.S. District Court for the Northern District of Texas. The Company responded to these two subpoenas and will continue to fully cooperate with the U.S. Department of Justice in the related investigation.

In addition, on July 19, 2019, we received a notice of immediate suspension of federal contracting from the United States Air Force, pending the outcome of an ongoing investigation. The suspension applied to 3D Systems, its subsidiaries and affiliates, and was related to the potential export controls violations involving our On Demand manufacturing business described above. Under the suspension, we were generally prohibited from receiving new federal government contracts or subcontracts from any executive branch agency as described in the provisions of 48 C.F.R Subpart 9.4 of the Federal Acquisition Regulation. The suspension allowed us to continue to perform current federal contracts, and also to receive awards of new subcontracts for items under $35 and for items considered commercially available off-the-shelf items. The Air Force lifted the suspension on September 6, 2019 following the execution of a two-year Administrative Agreement with us. We are now eligible to obtain and perform U.S. government contracts and subcontracts without restrictions. Under the Administrative Agreement, we will be monitored and evaluated by independent monitors who will report to the Air Force on our compliance with the terms of the Company’s Ethics & Compliance Program, including its overall culture, government contracting compliance program, and export controls compliance program.

Although we cannot predict the ultimate resolution of these matters, we have incurred and expect to continue to incur significant legal costs and other expenses in connection with responding to the U.S. government agencies.
Other

We are involved in various other legal matters incidental to our business. Although we cannot predict the results of the litigation with certainty, we believe that the disposition of all these various other legal matters will not have a material adverse effect, individually or in the aggregate, on our consolidated results of operations, consolidated cash flows or consolidated financial position.