XML 93 R20.htm IDEA: XBRL DOCUMENT v3.3.0.814
Contingencies
9 Months Ended
Sep. 30, 2015
Commitments and Contingencies Disclosure [Abstract]  
Contingencies
Contingencies
Litigation
The Company is currently involved in certain litigation that arises in the ordinary course of business, most of which is expected to be covered by liability insurance. Management makes assumptions and estimates concerning the likelihood and amount of any potential loss relating to these matters using the latest information available. The Company records a liability for litigation if an unfavorable outcome is probable and the amount of loss or range of loss can be reasonably estimated. If an unfavorable outcome is probable and a reasonable estimate of the loss is a range, the Company accrues the best estimate within the range. If no amount within the range is a better estimate than any other amount, the Company accrues the minimum amount within the range. If an unfavorable outcome is probable but the amount of the loss cannot be reasonably estimated, the Company discloses the nature of the litigation and indicates that an estimate of the loss or range of loss cannot be made. If an unfavorable outcome is reasonably possible and the estimated loss is material, the Company discloses the nature and estimate of the possible loss of the litigation. The Company does not disclose information with respect to litigation where an unfavorable outcome is considered to be remote or where the estimated loss would not be material. Based on current expectations, such matters, both individually and in the aggregate, are not expected to have a material adverse effect on the liquidity, results of operations, business or financial condition of the Company.    
Environmental Contingencies
The Company evaluates potential loss contingencies related to environmental matters using the same criteria described above related to litigation matters. Based on current information, an unfavorable outcome concerning such environmental matters, both individually and in the aggregate, is considered to be reasonably possible. However, the Company believes its maximum potential exposure to loss would not be material to its results of operations or financial condition. The Company has a master insurance policy that provides coverage through 2022 for certain environmental claims up to $10,000 per occurrence and up to $50,000 in the aggregate, subject to deductibles and certain exclusions.
Guarantees
The Operating Partnership may guarantee the debt of a joint venture primarily because it allows the joint venture to obtain funding at a lower cost than could be obtained otherwise. This results in a higher return for the joint venture on its investment, and a higher return on the Operating Partnership’s investment in the joint venture. The Operating Partnership may receive a fee from the joint venture for providing the guaranty. Additionally, when the Operating Partnership issues a guaranty, the terms of the joint venture agreement typically provide that the Operating Partnership may receive indemnification from the joint venture partner or have the ability to increase its ownership interest. The guarantees expire upon repayment of the debt, unless noted otherwise.
The following table represents the Operating Partnership's guarantees of unconsolidated affiliates' debt as reflected in the accompanying condensed consolidated balance sheets as of September 30, 2015 and December 31, 2014:
 
 
As of September 30, 2015
 
Obligation recorded to reflect guaranty
Unconsolidated Affiliate
 
Company's
Ownership
Interest
 
Outstanding
Balance
 
Percentage
Guaranteed
by the
Operating
Partnership
 
Maximum
Guaranteed
Amount
 
Debt
Maturity
Date
(1)
 
9/30/2015
 
12/31/2014
West Melbourne I, LLC -
Phase I
 
50%
 
$
39,667

 
25%
 
$
9,917

 
Nov-2015
(2) 
$
99

 
$
101

West Melbourne I, LLC -
Phase II
 
50%
 
16,757

 
N/A
(3) 
8,700

 
Nov-2015
(2) 
87

 
87

Port Orange I, LLC
 
50%
 
59,108

 
25%
 
14,777

 
Nov-2015
(2) 
148

 
153

JG Gulf Coast Town Center,
LLC - Phase III
 
50%
 
5,248

 
—%
(4) 

 
Jul-2017
 

 

Fremaux Town Center JV,
LLC - Phase I
 
65%
 
40,530

 
15%
(5) 
6,207

 
Aug-2016
(6) 
62

 
236

Fremaux Town Center JV,
LLC - Phase II
 
65%
 
20,304

 
50%
(7) 
16,050

 
Aug-2016
(6) 
161

 
161

Ambassador Town Center JV, LLC
 
65%
 
12,063

 
100%
(8) 
46,201

 
Dec-2017
(9) 
462

 
482

Ambassador Infrastructure,
LLC
 
65%
 
5,016

 
100%
(10) 
11,700

 
Dec-2017
(9) 
177

 
177

 
 
 
 
 
 
Total guaranty liability
 
$
1,196

 
$
1,397

(1)
Excludes any extension options.
(2)
The loan has two one-year extension options, which are at the unconsolidated affiliate's election, for an outside maturity date of November 2017.
(3)
In the fourth quarter of 2014, the loan was amended and restated to add funding for the construction of Academy Sports. The guaranty was also amended to cap the maximum guaranteed amount at $8,700 unless a monetary default event occurs related to Carmike Cinema or Academy Sports. The guaranty will be reduced to 25% once Academy Sports is operational and paying contractual rent.
(4)
The guaranty was removed when the loan was refinanced in July 2015. See Note 5 for more information.
(5)
The Operating Partnership received a 1% fee for this guaranty when the loan was issued in March 2013. In the second quarter of 2015, the guaranty was reduced to 15% as the requirement of being open for one year was met, LA Fitness opened and began paying contractual rent and a debt service coverage ratio of 1.30 to 1.00 was achieved.
(6)
The loan has two one-year extension options, which are at the unconsolidated affiliate's election, for an outside maturity date of August 2018.
(7)
The Operating Partnership received a 1% fee for this guaranty when the loan was issued in August 2014. Upon completion of Phase II of the development and once certain leasing and occupancy metrics have been met, the guaranty will be reduced to 25%. The guaranty will be further reduced to 15% when Phase II of the development has been open for one year, the debt service coverage ratio of 1.30 to 1.00 is met and Dillard's is operational.
(8)
The Operating Partnership received a 1% fee for this guaranty when the loan was issued in December 2014. Once construction is complete, the guaranty will be reduced to 50%. The guaranty will be further reduced from 50% to 15% once the construction of Ambassador Town Center and its related infrastructure improvements is complete as well as upon the attainment of certain debt service and operational metrics.
(9)
The loan has two one-year extension options, which are the joint venture's election, for an outside maturity date of December 2019.
(10)
The Operating Partnership received a 1% fee for this guaranty when the loan was issued in December 2014. The guaranty will be reduced to 50% on March 1st of the year following any calendar year during which the payment-in-lieu of taxes ("PILOT") payments received by Ambassador Infrastructure and delivered to the lender are $1,200 or more, provided no event of default exists. The guaranty will be reduced to 20% when the PILOT payments are $1,400 or more, provided no event of default exists.

The Company has guaranteed the lease performance of York Town Center, LP ("YTC"), an unconsolidated affiliate in which the Company owns a 50% interest, under the terms of an agreement with a third party that owns property as part of York Town Center. Under the terms of that agreement, YTC is obligated to cause performance of the third party’s obligations as landlord under its lease with its sole tenant, including, but not limited to, provisions such as co-tenancy and exclusivity requirements. Should YTC fail to cause performance, then the tenant under the third party landlord’s lease may pursue certain remedies ranging from rights to terminate its lease to receiving reductions in rent. The Company has guaranteed YTC’s performance under this agreement up to a maximum of $22,000, which decreases by $800 annually until the guaranteed amount is reduced to $10,000. The guaranty expires on December 31, 2020.  The maximum guaranteed obligation was $15,600 as of September 30, 2015.  The Company entered into an agreement with its joint venture partner under which the joint venture partner has agreed to reimburse the Company 50% of any amounts it is obligated to fund under the guaranty.  The Company did not include an obligation for this guaranty because it determined that the fair value of the guaranty was not material as of September 30, 2015 and December 31, 2014.
Performance Bonds
The Company has issued various bonds that it would have to satisfy in the event of non-performance. The total amount outstanding on these bonds was $23,354 and $20,720 at September 30, 2015 and December 31, 2014, respectively.