12. Commitments And Contingencies
The Company is involved in certain legal and regulatory actions. Management believes that the ultimate resolution of such matters is unlikely to have a material adverse effect on the Company’s financial condition or results of operations, except as described below.
Litigation: The Company is and has been the subject of administrative actions that arise from its ownership of SL Surface Technologies, Inc. (“SurfTech”), a wholly-owned subsidiary, the assets of which were sold in November 2003. SurfTech formerly operated chrome-plating facilities in Pennsauken Township, New Jersey (the “Pennsauken Site”) and Camden, New Jersey (the “Camden Site”).
In 2006 the United States Environmental Protection Agency (the “EPA”) named the Company as a potential responsible party (a “PRP”) in connection with the remediation of the Puchack Well Field, which has been designated as a Superfund Site. The EPA has alleged that hazardous substances generated at the Company’s Pennsauken Site contaminated the Puchack Well Field. As a PRP, the Company is potentially liable, jointly and severally, for the investigation and remediation of the Puchack Well Field Superfund Site under the Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended (“CERCLA”).
The EPA is remediating the Puchack Well Field Superfund Site in two separate operable units. The first operable unit consists of an area of chromium groundwater contamination that exceeds the selected cleanup standard (“OU-1”). The second operable unit (“OU-2”) pertains to sites that are allegedly the sources of contamination for the first operable unit. The EPA advised the Company that OU-2 includes soil contamination in the immediate vicinity of the Company’s Pennsauken Site.
In September 2006, the EPA issued a Record of Decision (“ROD”) that selected a remedy for OU-1 to address the groundwater contamination. The estimated cost of the EPA selected remedy for OU-1, to be conducted over a five to ten year timeframe, was approximately $17,600,000, as stated in the ROD. In an October 2010 meeting with the EPA, the EPA informed the Company that the OU-1 remedy would be implemented in two phases. Prior to the issuance of the EPA’s ROD, the Company had retained an experienced environmental consulting firm to prepare technical comments on the EPA’s proposed remediation of the Puchack Well Field Superfund Site. In those comments, the Company’s consultant, among other things, identified flaws in the EPA’s conclusions and the factual predicates for certain of the EPA’s decisions and for the proposed selected remedy.
Following the issuance of its ROD for OU-1, in November 2006, the EPA sent another letter to the Company encouraging the Company to either perform or finance the remedial actions for OU-1 identified in the EPA’s ROD. In addition to paying for the OU-1 remediation, the EPA has sought payment of the past costs that the EPA has allegedly incurred. The Company responded to the EPA that it was willing to investigate the existence of other PRPs and to undertake the activities necessary to design a final remediation for the Superfund Site. In July 2007, the EPA refused the Company’s offer to perform the work necessary to design the remediation plan without first agreeing to assume responsibility for the full remediation of the Superfund Site. The EPA did encourage the Company to investigate the existence of other PRPs and to submit evidence thereof, if appropriate. In January 2008, the Company submitted to the EPA evidence demonstrating the existence of several other PRPs.
In subsequent meetings and discussions with the U.S. Department of Justice (“DOJ”) and the EPA, the Company was informed that estimated OU-1 remediation costs are now in the range of $30,000,000 to $40,000,000 with additional past costs incurred by the EPA related to OU-1 of approximately $17,000,000. These costs are estimates provided to the Company by the EPA and DOJ as of year-end December 31, 2010. The Company has asked the DOJ/EPA for, but has not been furnished, support for these estimates and costs.
Notwithstanding the assertions of the DOJ and the EPA, based on discussions with its attorneys and environmental engineering consultants, the Company believes the EPA’s analytical effort is far from complete for OU-1. Further, technical data has not established that offsite migration of hazardous substances from the Company’s Pennsauken Site (OU-2) caused the contamination of OU-1 of the Puchack Well Field Superfund Site. In any event, the Company now believes that it has meritorious defenses to the imposition of liability for OU-1. Based on the foregoing, the Company believes that it has significant defenses against the EPA claims and that other PRPs should be identified and brought into the legal proceedings by the DOJ to provide for the ultimate cost of remediation.
In June 2011, the EPA announced a proposed plan for “cleaning up the soil” at OU-2. The remedy proposed by the EPA is “Geochemical Fixation.” This remedy involves applying a chemical reductant to the contaminated soil to reduce hexavalent chromium by converting it to immobilized trivalent chromium. The EPA’s estimated cost for this remedy is $20,700,000 over seven years. The public comment period for the proposed plan expired on July 27, 2011. On behalf of the Company, the Company’s environmental consultants provided comments to the EPA plan on July 22, 2011. The comments included the belief that: (a) there are other PRPs responsible for chromium ground water contamination, (b) demolition of buildings for an estimated cost of $2,300,000 is not necessary for this remedy, (c) the extent and depth of the hexavalent chromium exceeds cleanup criteria, (d) the estimate for oversight costs are excessive, and (e) that significant testing be performed prior to implementing the Geochemical Fixation remedy to ensure that the remedy will satisfy all requirements with respect to ground water quality. On September 26, 2011 the EPA issued a ROD selecting the Geochemical Fixation remedy. This remedy involves mixing a reducing agent to treat soils containing concentrations of hexavalent chromium greater than 20 parts per million. The remedy also requires post-remediation sampling, site restoration and implementing a groundwater sampling and analysis program. The Company intends to have its environmental consultants play an active role in the remediation design.
The Company is currently in settlement discussions with the EPA and the DOJ regarding the remediation and past costs for both OU-1 and OU-2. This settlement currently includes , among other things, a “limited ability to pay” component, which has been provided by the EPA and the DOJ and is currently being negotiated by the Company. While the EPA and the DOJ are viewing the OU-1 and OU-2 costs in a single ability to pay analysis, the Company is considering treating OU-1 and OU-2 as two separate and distinct items. Based on the current available information, the Company has estimated a total liability for OU-1 and OU-2 combined of $11,776,000, all of which was recorded in prior years. The estimated OU-2 liability is based upon the EPA’s plan for remediation, and data from our environmental engineering consultants. The above liability is included in the total environmental accrual.
It is management’s opinion taking into account the information available to the Company as well as the significant defenses against the EPA claims and other PRPs potential responsibility that the impact of litigation and environmental administrative actions and related liabilities brought against the Company and its operations should not have a material adverse effect on its consolidated financial position or results of operations. However, the ultimate outcome of these matters, as with litigation generally, is inherently uncertain, and it is possible that some of these matters may be resolved adversely to the Company relative to the current reserves. The adverse resolution of any one or more of these matters could have a material adverse effect on the business, operating results, financial condition or cash flows of the Company.
Other
In the ordinary course of its business the Company is and may be subject to other loss contingencies pursuant to foreign and domestic federal, state and local governmental laws and regulations and maybe party to certain legal actions, frequently involving complaints by terminated employees and disputes with customers and suppliers. In the opinion of management, any such other loss contingencies are not expected to have a material adverse effect on the financial condition or results of operations of the Company.
Environmental Matters: Loss contingencies include potential obligations to investigate and eliminate or mitigate the effects on the environment of the disposal or release of certain chemical substances at various sites, such as Superfund sites and other facilities, whether or not they are currently in operation. The Company is currently participating in environmental assessments and cleanups at a number of sites and may in the future be involved in additional environmental assessments and cleanups. Based upon investigations completed to date by the Company and its independent engineering-consulting firms, management has provided an estimated accrual for all known costs believed to be probable and costs that can be reasonably estimated in the amount of $14,644,000, of which $11,779,000 is included as other long-term liabilities as of September 30, 2011. However, it is the nature of environmental contingencies that other circumstances might arise, the costs of which are indeterminable at this time due to such factors as changing government regulations and stricter standards, the unknown magnitude of cleanup costs, the unknown timing and extent of the remedial actions that may be required, the determination of the Company’s liability in proportion to other responsible parties, the divisibility of costs, and the extent, if any, to which such costs are recoverable from other parties. These other circumstances could result in additional expenses or judgments, or offsets thereto. The adverse resolution of any one or more of these other circumstances could have a material adverse effect on the business, operating results, financial condition or cash flows of the Company. Most of the Company’s environmental costs are related to discontinued operations and such costs have been recorded in discontinued operations, net of tax.
There are three sites on which the Company may incur material environmental costs in the future as a result of past activities of its former subsidiary, SurfTech. There are two Company owned sites related to its former subsidiary, SurfTech. These sites are located in Pennsauken, New Jersey (the “Pennsauken Site”) and in Camden, New Jersey (the “Camden Site”). There is also a third site, which is not owned by the Company, referred to as the “Puchack Well Field Site.” The Puchack Well Field Site and the Pennsauken Site are part of the Puchack Well Field Superfund Site.
With respect to the Camden Site, the Company has reported soil contamination and a groundwater contamination plume emanating from the site. Delineation of the soil and groundwater contamination is substantially complete. In the third quarter of 2009, pursuant to an Interim Response Action (“IRA”) Work plan approved by the New Jersey Department of Environmental Protection (“NJDEP”), the Company completed building demolition and excavated and disposed of some of the contaminated soil underlying the building’s foundation. Treatability studies for in-situ remediation of the remaining unsaturated contaminated soil were conducted in 2009. Based upon the treatability study results, our environmental consultants prepared an IRA Work plan Addendum (“IRAWA”) to implement a Phase I Pilot Study (“PIPS”), which involved injecting neutralizing chemicals into the unsaturated soil. The NJDEP approved the IRAWA, and the PIPS were implemented in November 2010. These injections have now been completed. As required by the IRAWA, our consultants have collected post-injection data for assessment of the overall success of the PIPS. Our consultants have completed the assessment of the PIPS and have indicated that the PIPS can be implemented as a full scale soil remedy to treat unsaturated contaminated soil. Also, the Company’s environmental consultants finalized an IRA Work plan Addendum II to implement a Phase II Pilot Study to treat on-site contaminated groundwater. This plan was submitted to the NJDEP in May 2011. It proposed multiple sub-surface injections of a food-grade product, into the groundwater at the down gradient property boundary, to create a “bio-barrier.” The Phase II Pilot Study would assess the ability to treat contaminated groundwater as it moves through the bio-barrier. This plan also required the collection of groundwater samples to assess the performance of the Phase II Pilot Study. To date, the Company’s consultants have not received any comments from NJDEP regarding the IRA Work plan Addendum II and permit applications necessary to implement the Phase II Pilot Study. Implementation of the Phase II Pilot Study is scheduled to occur during 2012 and 2013, depending upon approval of the plan and related permits from the NJDEP. At September 30, 2011, the Company had an accrual of $1,967,000 to remediate the Camden Site. Of this amount, the Company anticipates expenditures of approximately $30,000 for the remainder of 2011.
The Company has reported soil and groundwater contamination at the facility of SL-MTI located on its property in Montevideo, Minnesota. An analysis of the contamination has been completed and a remediation plan has been implemented at the site pursuant to the remedial action plan approved by the Minnesota Pollution Control Agency. The remaining steps under this plan are the monitoring of samples. Based on the current information, the Company believes it will incur remediation costs at this site of approximately $42,000, which has been accrued for at September 30, 2011. These costs are recorded as a component of continuing operations.
As of September 30, 2011 and December 31, 2010, environmental accruals of $14,644,000 and $14,911,000, respectively, have been recorded by the Company in accrued liabilities — other and in other long-term liabilities, as appropriate (see Notes 10 and 11).