XML 23 R12.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments and Contingencies
9 Months Ended
Sep. 30, 2017
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
7. Commitments and Contingencies

 

Post retirement obligation. As previously disclosed in filings with the Securities and Exchange Commission (“SEC”), the Company, under an employment agreement, is expected to pay post employment health related benefits to the former Executive Officer of the Company. Approximately $528,000 has been accrued as of September 30, 2017 and is reflected as Post Retirement Obligation in the accompanying balance sheet.

 

Facility Expansion. As previously disclosed, the Company has commenced a multi-year investment plan designed to consolidate the operations of the Consumer Products Group (“CPG”). The five year plan included the construction of an approximate 28,000 square foot addition, capital improvements to the existing plant, the reconfiguration of its production process within the expanded facility, and the addition of new state of the art knife-making equipment. The Company broke ground in the second quarter of 2014 and began manufacturing in the newly constructed facility in the fourth quarter of 2015. The cost of the project was approximately $4,000,000 over a five year period of which $3,432,000 was completed as of September 30, 2017 and is included in property, plant and equipment.

 

The CPG was awarded certain incentives from the County of Cattaraugus Industrial Development Agency (CCIDA) in connection with the expansion of the Company’s facility in Franklinville, New York and other proposed capital expenditures. The incentives include certain real property tax and sales tax abatements in connection with the proposed project. The Company’s CPG entered into customary lease and leaseback arrangements with the CCIDA to facilitate the various tax incentives.

 

The Company’s CPG was awarded a $300,000 grant from Cattaraugus County, New York. The grant was used towards new manufacturing equipment in connection with the proposed expansion project. As part of the terms of the Grant Contract with Cattaraugus County, the Company’s CPG has agreed to maintain certain employment levels for a period of five years from the date of the agreement, March 13, 2014. If the employment levels are not maintained, the Company will be required to repay the grant proceeds on a prorated basis. The Company has maintained the required employment levels as of September 30, 2017.