COMMITMENTS
The Company leases land, office space, data center facilities and equipment used in connection with its operations under various operating leases, many of which contain escalation clauses. The Company is also committed to pay a portion of the related operating expenses under a data center lease agreement. These operating expenses are not included in the table below.
Future minimum payments under operating lease agreements are as follows:
Years Ending December 31,
 
(In thousands)
2017
 
$
31,834

2018
 
31,661

2019
 
24,316

2020
 
18,523

2021
 
13,239

Thereafter
 
189,070

Total
 
$
308,643


Expenses charged to operations under these agreements are $49.3 million, $39.4 million and $41.2 million for the years ended December 31, 2016, 2015 and 2014, respectively.
The Company's most significant operating lease is a seventy-seven year land lease for IAC's headquarters building in New York City and approximates 57% of the future minimum payments due under all operating lease agreements in the table above.
The Company also has funding commitments that could potentially require its performance in the event of demands by third parties or contingent events as follows:
 
Amount of Commitment Expiration Per Period
 
Less Than
1 Year
 
1-3
Years
 
3-5
Years
 
More Than
5 Years
 
Total
Amounts
Committed
 
(In thousands)
Purchase obligations
$
10,581

 
$
10,000

 
$

 
$

 
$
20,581

Letters of credit and surety bonds
768

 
63

 

 
1,437

 
2,268

Total commercial commitments
$
11,349

 
$
10,063

 
$

 
$
1,437

 
$
22,849


The purchase obligations principally include a web hosting commitment. The letters of credit support the Company's casualty insurance program.