Schedule of Lease Cost
The Company's finance lease liabilities consisted of the following as of June 30, 2023 and December 31, 2022 (in thousands):
CreditorLoan TypeJune 30, 2023December 31, 2022
MathesonFinance Lease$44,739 $45,311 
PlaqueminesFinance Lease1,096 1,169 
Harvey Ford Finance Lease43 47 
DLL financialFinance Lease21 — 
Centerpoint BlakelyFinance Lease23,711 — 
$69,610 $46,527 
The following table summarizes the lease cost recognized in our consolidated statements of operations (in thousands):
Three Months Ended June 30,Six Months Ended June 30,
Lease Cost Type2023202220232022
Amortization of finance lease ROU assets$984 $780 $1,769 $808 
Interest on lease liabilities1,551 1,366 2,934 1,378 
Net finance lease costs$2,535 $2,146 $4,703 $2,186 
The following table summarizes the operating lease costs recognized (in thousands):
Three Months Ended June 30,Six Months Ended June 30,
Lease Cost Type2023202220232022
Operating lease cost$4,962 $1,530 $8,032 $2,964 
Variable lease cost609 306 869 351 
Short-term lease cost181 2,114 2,110 3,978 
Net lease cost$5,752 $3,950 $11,011 $7,293 
The following table summarizes the supplemental cash flow information related to leases as follows (in thousands):
Six Months Ended June 30,
Lease Cost Type20232022
Cash paid for amounts included in the measurement of liabilities
Payments on financing lease$908 $402 
Payments on operating lease$8,032 $3,819 
Non-cash supplemental amounts
ROU assets obtained from new finance lease liabilities$23,990 $45,096 
ROU assets obtained from new operating lease liabilities$38,945 $— 
The weighted average remaining lease terms and discount rates for all of our operating leases were as follows as of June 30, 2023:
Remaining lease term and discount rate:June 30, 2023
Weighted average remaining lease terms (years)
   Lease facilities4.95
   Lease equipment3.60
   Lease plant16.52
   Lease railcar2.14
Weighted average discount rate
   Lease facilities9.26 %
   Lease equipment11.90 %
   Lease plant12.24 %
   Lease railcar8.47 %
Schedule of Finance Lease, Liability, Fiscal Year Maturity
Future maturities of finance lease obligations, as of June 30, 2023, are summarized as follows (in thousands):
Period Ended June 30,
Amount Due
2024$8,409 
20258,409 
20268,404 
20278,400 
202827,330 
Thereafter61,152 
Total lease payments122,104 
Less: interest(52,494)
Present value of financing lease liabilities$69,610 
Schedule of Maturities of Operating Lease Liabilities
Maturities of our lease liabilities for all operating leases are as follows as of June 30, 2023 (in thousands):
For the period ending June 30,FacilitiesEquipmentPlantRailcarTotal
2024$535 $16,776 $7,421 $856 $25,588 
2025418 13,579 7,421 654 22,072 
2026333 5,058 7,421 485 13,297 
2027300 5,058 7,440 306 13,104 
2028300 2,185 7,477 49 10,011 
Thereafter1,300 — 83,553 — 84,853 
Total lease payments3,186 42,656 120,733 2,350 168,925 
Less: interest(952)(6,136)(69,098)(237)(76,423)
Present value of operating lease liabilities$2,234 $36,520 $51,635 $2,113 $92,502