XML 41 R10.htm IDEA: XBRL DOCUMENT v2.4.0.8
COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS
6 Months Ended
Jun. 30, 2014
COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS [Abstract]  
COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS
4. COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS

Costs and estimated earnings in excess of billings on uncompleted contracts consist of:

 
June 30, 2014
 
U.S
   
 
Government
Commercial
Total
       
Costs incurred on uncompleted
     
contracts
$283,389,597
$74,375,964
$357,765,561
Estimated earnings
54,647,673
33,817,544
88,465,217
Sub-total
338,037,270
108,193,508
446,230,778
Less billings to date
295,396,600
77,617,027
373,013,627
Costs and estimated earningsin excess of billings on uncompleted contracts
  $42,640,670            $30,576,481      $73,217,151

 
December 31, 2013
 
 
U.S.
   
 
Government
Commercial
Total
Costs incurred on uncompleted
     
contracts
$259,050,407
$62,502,116
$321,552,523
Estimated earnings
95,590,879
30,694,605
126,285,484
Sub-total
354,641,286
93,196,721
447,838,007
Less billings to date
272,783,120
62,733,921
335,517,041
Costs and estimated earnings in excess of billings on uncompleted contracts
$81,858,166
$30,462,800
$112,320,966

The above amounts are included in the accompanying balance sheets under the following captions at June 30, 2014 and December 31, 2013:

 
June 30, 2014
December 31, 2013
Costs and estimated earnings in excess of billings on
   
uncompleted contracts
$ 73,560,852
$ 112,597,136
Billings in excess of costs and estimated earnings on
   
uncompleted contracts
 (343,701)
 (276,170)
     
Totals
$ 73,217,151
$ 112,320,966

U.S. Government Contracts includes contracts directly with the U.S. Government and Government subcontracts.

Revisions in the estimated gross profits on contracts and contract amounts are made in the period in which the circumstances requiring the revisions occur. During the six months ended June 30, 2014 and 2013, the effect of such revisions in total estimated contract profits resulted in a decrease to the total gross profit to be earned on the contracts of approximately $41,820,000 and $2,797,000, respectively, from that which would have been reported had the revised estimates been used as the basis of recognition of contract profits in prior years. Approximately 95% of the decrease in the six months ended June 30, 2014 is the result of a change in estimate on the Company's A-10 program, discussed in Note 1.

Although management believes it has established adequate procedures for estimating costs to complete on uncompleted open contracts, it is possible that additional significant costs could occur on contracts prior to completion.