XML 27 R15.htm IDEA: XBRL DOCUMENT v2.3.0.15
Regulatory Matters
9 Months Ended
Sep. 30, 2011
Regulatory Matters [Abstract] 
Regulatory Matters [Text Block]
11.  Regulatory Matters
 
Kinder Morgan Interstate Gas Transmission Pipeline - Franklin to Hastings Expansion Project
 
KMIGT has filed a prior notice request to expand and replace certain mainline pipeline facilities to create up to 10,000 dekatherms per day of firm transportation capacity to serve an ethanol plant located near Aurora, Nebraska.  The estimated cost of the facilities is $18.4 million.  The project was constructed and went into service on April 14, 2011.
 
FERC Natural Gas Fuel Tracker Proceedings
 
Trailblazer Pipeline Company LLC
 
On April 28, 2011, the FERC issued an Order Rejecting Tariff Record and Denying Waiver in Trailblazer Pipeline Company LLC's annual fuel tracker filing at Docket No. RP11-1939-000.  The order required Trailblazer to make a compliance filing for its annual Expansion Fuel Adjustment Percentage (EFAP) pursuant to its tariff.  In its previous two annual tracker filings, Trailblazer received authorization by the FERC to defer collection of its fuel deferred account until a future period by granting a waiver of various fuel tracker provisions.  In the Docket No. RP11-1939 filing, Trailblazer again asked for tariff waivers that would defer the collection of its fuel deferred account to a future period, which the FERC denied.  Trailblazer has filed for rehearing of the FERC's April 28, 2011 order, which is pending before the FERC.
 
On May 2, 2011, Trailblazer filed to re-determine its EFAP in compliance with the April 28, 2011 order, implementing a revised EFAP rate of 8.14%, which included the proposed recovery of the deferred account.  On May 18, 2011, the FERC issued an order rejecting the May 2, 2011 filing, on the basis that the filing to implement a revised EFAP must be accomplished as a new proceeding, not as a compliance filing.  Trailblazer has filed for rehearing of the May 18, 2011 order, which is also pending before the FERC.
 
On June 3, 2011, Trailblazer filed in a new proceeding, Docket No. RP11-2168-000, revised tariff records to redetermine its EFAP, with a proposed effective date of July 1, 2011.  Trailblazer included three EFAP rate options.  In addition, under two of the options, Trailblazer proposed to continue to defer collection of the deferred account until a future date.  In an order dated July 1, 2011, referred to in this Note as the July 1 Order, the FERC rejected the two options to defer recovery of the deferred account and accepted the option that included recovery of the entire deferred account.  Specifically, the FERC approved an EFAP rate of 8.69%, subject to refund, effective July 1, 2011 and established hearing proceedings to determine the appropriate throughput, revenue and cost data to use for determining the EFAP and the composition, accounting and proposed recovery methodology for amounts in the deferred account.  In the July 1 Order, the FERC determined that Trailblazer could not charge negotiated rate shippers a fuel rate above the caps established in their negotiated rate agreements with Trailblazer and that operation of the cap was not an issue for hearing.  As a result of this determination, Trailblazer recognized a $13.1 million operating expense in the second quarter of 2011 for the amount of the deferred costs that is potentially attributable to the negotiated rate shippers.  Trailblazer sought rehearing of the July 1 Order, and a prehearing conference held on July 14, 2011 established a procedural schedule that results in a hearing in April 2012.  Trailblazer continues to pursue full recovery of the amount reserved pursuant to the Docket No. RP11-2168-000 proceeding.  Trailblazer has been engaged in settlement discussions with the active parties to this proceeding and has reached an agreement in principle with such parties.  As a result, on October 7, 2011, Trailblazer filed a motion to suspend the procedural schedule for 15 days to allow the parties to resolve the remaining issues in this proceeding and avoid the need for a hearing.  The Chief Judge granted Trailblazer's motion to suspend the procedural schedule and required a status report on the timing for filing the settlement by October 28, 2011.  Given that the parties continue to finalize the settlement documents, Trailblazer will file to continue to suspend the procedural schedule for another 15-day period.  Upon execution of the necessary settlement documents, Trailblazer will file a motion to terminate the hearing procedure.
 
On July 25, 2011, Trailblazer filed, in Docket No. RP11-2295-000, to apply the EFAP rate to additional classes of shippers, including interruptible transportation, backhaul transportation, and overrun transportation to be  effective September 1, 2011.  On August 31, 2011, the FERC issued an order rejecting Trailblazer's proposed tariff records on the basis that the tariff changes are contrary to Trailblazer's Docket No. RP10-492-000 Settlement and violate the prohibition against retroactive ratemaking by proposing to charge shippers for under-recoveries that occurred prior to the effective date of the tariff provision.  Trailblazer has filed for rehearing of the August 31, 2011 order, which is pending before the FERC.  Furthermore, Trailblazer does not expect the entire fuel tracker proceedings discussed above to have a material adverse impact on its business, financial position, results of operations or cash flows.
 
Rockies Express Pipeline LLC
 
On March 1, 2011, Rockies Express Pipeline LLC made its annual filing to revise its fuel lost and unaccounted for percentage, referred to as its FL&U rate, applicable to its shippers effective April 1, 2011.  In this filing, Rockies Express requested an increase in its FL&U rate due to a decline in the price of natural gas used to index its FL&U rate that had resulted in a fuel tracker receivable balance as of December 31, 2010.  Rockies Express proposed two options to allow it to recover these costs.
 
On March 30, 2011, the FERC notified Rockies Express that it had rejected the first option and that the second option, while accepted effective April 1, 2011, was under further FERC review.  This event caused Rockies Express to reconsider the recoverability of a portion of its fuel tracker receivable balance that would have been recovered from one shipper. Therefore, in the first quarter of 2011, Rockies Express reduced its fuel tracker receivable balance by $8.2 million and  recorded the same amount as additional operations and maintenance expense.