Subsequent to April 30, 2024, the Company sold approximately 38.6 million shares of its common stock under the Amended Sales Agreement at an average price of $0.84 per share, resulting in gross proceeds of approximately $32.3 million before deducting sales commissions and fees, and net proceeds to the Company of approximately $31.7 million after deducting sales commissions and fees totaling approximately $0.6 million. As of the date of this report, approximately $261.4 million of shares remained available for sale under the Amended Sales Agreement.

Long-Term Service Agreement with Gyeonggi Green Energy Co., Ltd.

On May 28, 2024, the Company and Gyeonggi Green Energy Co., Ltd. (“GGE”) entered into a long-term service agreement (the “LTSA”) with respect to GGE’s 58.8 MW fuel cell power platform in Hwaseong-si, Korea (the “GGE Platform”). The GGE Platform is comprised of 21 SureSource 3000 molten carbonate fuel cells (each a “Plant”). Each Plant is comprised of two 1.4-MW carbonate fuel cell modules.  Pursuant to the LTSA, GGE and the Company have agreed that (i) GGE will purchase from the Company 42 1.4-MW carbonate fuel cell modules to replace existing fuel cell modules at the GGE Platform, (ii) the Company will provide certain balance of plant replacement components if and to

the extent the parties reasonably determine existing components should be replaced, and (iii) the Company will provide long term operations and maintenance services for the GGE Platform.  The total amount payable by GGE under the LTSA for the 42 replacement fuel cell modules, balance of plant replacement components, and service is $159.6 million USD, with payments to be made over time as such replacement fuel cell modules are commissioned and the service obligations under the LTSA for such Plants commence.

Pursuant to the LTSA, the Company will provide various performance guarantees for each Plant related to power generation, fuel consumption, water consumption and heat production. If a Plant fails to achieve such performance requirements, the Company may be required to compensate GGE for such underperformance.

The Company’s service obligations under the LTSA will commence with respect to individual Plants as the Company replaces each Plant’s existing fuel cell modules and commissions the replacement fuel cell modules.  The term of the LTSA with respect to each Plant will continue for seven years from the date of commissioning of the replacement fuel cell modules for such Plant.  Commissioning of the first six 1.4-MW replacement fuel cell modules is expected to be completed in the fall of calendar year 2024, with an additional 30 1.4-MW replacement fuel cell modules expected to be commissioned throughout the course of calendar year 2025, and the remaining six 1.4-MW replacement fuel cell modules expected to be commissioned in the first half of calendar year 2026.