Tax Equity Financing

Note 4. Tax Equity Financing

The Company closed on a tax equity financing transaction in August 2021 with East West Bank for the 7.4 MW Groton Project located on the U.S. Navy Submarine Base in Groton, CT, also known as the Submarine Force. East West Bank’s tax equity commitment totals $15 million. 

This transaction was structured as a “partnership flip”, which is a structure commonly used by tax equity investors in the financing of renewable energy projects. Under this partnership flip structure, a partnership, in this case Groton Station Fuel Cell Holdco, LLC (the “Groton Partnership”) was organized to acquire from FuelCell Energy Finance II, LLC, a wholly-owned subsidiary of the Company, all outstanding equity interests in Groton Station Fuel Cell, LLC (the “Groton Project Company”) which in turn owns the Groton Project and is the party to the power purchase agreement and all project agreements. At the closing of the transaction, the Groton Partnership is owned by East West Bank, holding Class A Units, and Fuel Cell Energy Finance Holdco, LLC, a subsidiary of FuelCell Energy Finance, LLC, holding Class B Units.  The acquisition of the Groton Project Company by the Groton Partnership was funded in part by an initial draw from East West Bank and funds contributed downstream to the Groton Partnership by the Company. The initial closing occurred on August 4, 2021, upon the satisfaction of certain conditions precedent (including the receipt of an appraisal and confirmation that the Groton Project would be eligible for the investment tax credit under Section 48 of the Internal Revenue Code of 1986, as amended).  In connection with the initial closing, the Company was able to draw down $3.0 million, of which approximately $0.8 million was used to pay closing costs including appraisal fees, title insurance expenses and legal and consulting fees. The Company is eligible to draw the remaining amount of the commitment, approximately $12 million, once the Groton Project achieves commercial operation.  When such funds are drawn down, the funds will be distributed upstream to the Company, as a reimbursement of prior construction costs incurred by the Company. The Company recognized a loss of $30 thousand for the fiscal year ended October 31, 2021 which is attributable to the noncontrolling interest reflecting the 1% conditional withdrawal.

Under most partnership flip structures, tax equity investors agree to receive a minimum target rate of return, typically on an after-tax basis. Prior to receiving a contractual rate of return or a date specified in the contractual arrangements, East West Bank will receive substantially all of the non-cash value attributable to the Groton Project, which includes accelerated depreciation and Section 48(a) investment tax credits; however, the Company will receive a majority of the cash distributions (based on the operating income of the Groton Project), which are paid quarterly. After East West Bank receives its contractual rate of return, the Company will receive approximately 95% of the cash and tax allocations. The

Company (through a separate wholly owned entity) may enter into a back leverage debt financing transaction and use the cash distributions from the Groton Partnership to service the debt.