XML 42 R30.htm IDEA: XBRL DOCUMENT v2.4.0.6
Inventories (Tables)
12 Months Ended
Oct. 31, 2012
Inventories [Abstract]  
Schedule of Inventory, Current [Table Text Block]
The components of inventory at October 31, 2012 and 2011 consisted of the following:
 
 
2012
 
2011
Raw materials
 
$
17,683

 
$
18,303

Work-in-process (1)
 
30,018

 
21,798

Net inventory
 
$
47,701


$
40,101

(1) Work-in-process includes the standard components of inventory that are used to build typical modules or stack components that are intended to be used in future power plant orders. Included in Work-in-process as of October 31, 2012 is $11.3 million of completed standard components ready to be incorporated into power plants and deployed upon receipt of customer orders.