8. Leases, Licensed Technology and Other Commitments

Facility Leases

The Company conducts the majority of its operations in a 100,000 square foot office and laboratory facility under a non-cancelable operating lease that extends to July 2019 with two consecutive five-year renewal options. The Company maintains an outstanding letter of credit of $1.4 million in accordance with the terms of the amended lease. In May 2012, the Company entered into a three-year operating lease agreement for an additional 26,000 square feet of office space which was extended to August 2016. Future non-cancelable minimum annual rental payments through July 2019 under these leases are $7.0 million in 2016, $6.0 million in 2017, $6.1 million in 2018, $3.6 million in 2019 and $0 in 2020.

Binney Street, Cambridge, Massachusetts

In January 2013, the Company entered into a lease agreement for approximately 244,000 square feet of laboratory and office space in two adjacent, connected buildings which are under construction in Cambridge, Massachusetts. Under the terms of the original lease, the Company leased all of the rentable space in one of the two buildings and a portion of the available space in the second building. In September 2013, the Company entered into a lease amendment to lease all of the remaining space, approximately 142,000 square feet, in the second building, for an aggregate of 386,000 square feet in both buildings. The terms of the lease amendment were consistent with the terms of the original lease. Construction of the core and shell of the building was completed in March 2015 at which time construction of tenant improvements in the building commenced. Construction of the tenant improvements is expected to be completed in the second half of 2016.

In connection with this lease, the landlord is providing a tenant improvement allowance for the costs associated with the design, engineering, and construction of tenant improvements for the leased facility. The tenant improvements will be in accordance with the Company’s plans and include fit-out of the buildings to construct appropriate laboratory and office space, subject to approval by the landlord. To the extent the stipulated tenant allowance provided by the landlord is exceeded, the Company is obligated to fund all costs incurred in excess of the tenant allowance. The scope of the planned tenant improvements do not qualify as “normal tenant improvements” under the lease accounting guidance. Accordingly, for accounting purposes, the Company is the deemed owner of the buildings during the construction period.

As construction progresses, the Company records the project construction costs incurred as an asset. To the extent that the cost is incurred by the landlord or incurred by the Company and reimbursed by the landlord, the Company records a corresponding increase to facility lease obligation included in long-term debt on the consolidated balance sheet. Upon completion of the buildings, the Company will determine if the asset and corresponding financing obligation should continue to be carried on its consolidated balance sheet under the relevant accounting guidance. Based on the current terms of the lease, the Company expects to continue to be the deemed owner of the buildings upon completion of the construction period. As of December 31, 2015, the Company has recorded construction in progress of $246.7 million and a facility lease obligation of $231.7 million.

The initial term of the lease is for 15 years from substantial completion of the core and shell of the buildings, which occurred in March 2015, with options to renew for three terms of five years each at market-based rates. The base rent is subject to increases over the term of the lease. Based on the original and amended leased space, the future non-cancelable minimum annual lease payments under the lease are $8.7 million, $25.5 million, $31.0 million, $31.5 million and $32.1 million in 2016, 2017, 2018, 2019 and 2020, respectively and $325.3 million in total thereafter, plus the Company’s share of the facility operating expenses and other costs that are reimbursable to the landlord under the lease.

The Company maintains a letter of credit as security for the lease of $9.2 million, which is supported by restricted cash.

In August 2015, the Company entered into a sublease agreement for approximately 160,000 square feet of the total leased space in the Binney Street facility. The sublease has an initial term of 10 years from the rent commencement date, which is expected to be in the third quarter of 2016 with an option to extend for the remainder of the initial term of the Company’s underlying lease. The sublease rent is subject to increases over the term of the lease. Based on the agreement, during the initial term the non-cancelable minimum annual sublease payments by calendar year beginning upon the rent commencement date of the sublease are approximately $5.3 million in 2016, $10.7 million in 2017, $10.9 million in 2018, $11.1 million in 2019 and $11.3 million in 2020 and $65.6 million in total thereafter, plus the subtenant’s share of the facility operating expenses.

Lausanne, Switzerland

In January 2013, the Company entered into a lease agreement for approximately 22,000 square feet of office space in a building, which the Company occupied in 2014. The term of the lease is for ten years, with options for extension of the term and an early termination at the Company’s option after five years. Future non-cancelable minimum annual lease payments under their lease are expected to be approximately $1.0 million in 2016, 2017, 2018 and 2019, $1.1 million in 2020 and $3.2 million in total thereafter.

Total rent expense for the leases described above as well as other Company leases for 2015, 2014 and 2013 was $9.6 million, $7.6 million and $6.1 million, respectively. Contingent rent for 2015, 2014 and 2013 was $0.8 million, $0.7 million and $0.7 million, respectively. Total future non-cancelable minimum annual rental payments for the leases described above as well as other Company leases, for the next five years and thereafter are $17.5 million, $32.6 million, $38.1 million, $36.2 million, $33.1 million and $328.5 million, respectively.

Licensed Technology

The Company has entered into agreements with several universities under which the Company has received exclusive licenses to technology and intellectual property. The agreements, which are generally cancelable by the Company, provide for the payment of license fees and/or minimum payments, which are generally creditable against future royalties. Fees paid by the Company amounted to $0.5 million in 2015, $0.5 million in 2014 and $0.1 million in 2013, and are expected to amount to $0.8 million in 2016, $2.9 million in 2017, $0.1 million in 2018, $0.1 million in 2019, and $0.1 million in 2020. In addition, the agreements provide for payments upon the achievement of certain milestones in product development. The agreements also require the Company to fund certain costs associated with the filing and prosecution of patent applications.

Other Commitments

The Company has entered into employment agreements with each of the officers of the Company. The agreements for these officers have remaining terms as of December 31, 2015 extending through the end of 2016 and 2017, providing for aggregate base salaries of $15.8 million for 2016 and $2.5 million for 2017, and $0.7 million in 2018.