Note 12 – Commitments and Contingencies

We are subject to various claims and legal proceedings with respect to matters such as governmental regulations, and other actions arising out of the normal course of business. Management believes that the resolution of these matters will not have a material adverse effect on our financial position, results of operations, or cash flow.

On August 17, 2010, we completed the Cliffstar Acquisition which included contingent consideration of up to $55.0 million. The first $15.0 million of the contingent consideration was paid upon the achievement of milestones in certain expansion projects in 2010. The remainder of the contingent consideration was to be calculated based on the achievement of certain performance measures during the fiscal year ended January 1, 2011. During 2011, Cott made interim payments to the seller equal to $29.6 million, which was net of a $4.7 million refund due to Cott and included $0.9 million in settlement of certain of the seller’s objections to the calculation of the contingent consideration.

In 2011, the seller of Cliffstar raised certain objections to the performance measures used to calculate the contingent consideration, and the parties commenced the dispute resolution mechanism provided for in the asset purchase agreement. The seller’s claims for an additional $12.1 million in contingent consideration were submitted to binding arbitration pursuant to the asset purchase agreement and favorably resolved by payment by Cott in February 2013 of approximately $0.6 million.

We had $11.5 million in standby letters of credit outstanding as of June 29, 2013 (June 30, 2012 – $11.0 million).