Note 7. Commitments and Contingencies

Lease Commitments

The Company leases certain of its domestic and foreign facilities and certain office equipment under non-cancelable lease agreements. The lease agreements generally require the Company to pay property taxes, insurance, maintenance and repair costs. Rent expenses were $58.1 million, $49.7 million and $45.2 million in fiscal 2011, 2010 and 2009, respectively. The Company charges operating lease payments to expense using the straight-line method. The Company subleases portions of its facilities and records sublease payments as a reduction of rent expense.

On October 15, 2011, the Company agreed to lease two office buildings to be constructed in Mountain View, California. Once construction is complete, the buildings together will provide approximately 341,000 square feet. The buildings may be enlarged up to a total size of approximately 440,000 square feet by mutual agreement of Synopsys and the lessor. The lease of such premises begins upon the later of March 1, 2015 or six months after construction is substantially completed and expires approximately 15 years thereafter and can be extended for an additional 19 years after such initial expiration. We may terminate the lease by exercising a separate option to purchase the property (i) at any time prior to January 13, 2012 or (ii) if the lessor fails to obtain financing. We may also terminate the lease if, under certain circumstances, the lessor fails to commence construction by June 1, 2013 or substantially complete construction of the buildings by March 1, 2015.

Anticipated future minimum lease payments on all non-cancelable operating leases with a term in excess of one year, net of sublease income, as of October 31, 2011 are as follows:

 

                         
     Minimum
Lease
Payments
     Sublease Income      Net  
     (in thousands)  

Fiscal Year

                          

2012

   $ 45,839       $ 703       $ 45,136   

2013

     35,894         670         35,224   

2014

     31,302         137         31,165   

2015

     20,256         —           20,256   

2016

     25,690         —           25,690   

Thereafter

     309,661         —           309,661   
    

 

 

    

 

 

    

 

 

 

Total

   $ 468,642       $ 1,510       $ 467,132   
    

 

 

    

 

 

    

 

 

 

 

Legal Proceedings

The Company is subject to routine legal proceedings, as well as demands, claims and threatened litigation that arise in the normal course of its business. The ultimate outcome of any litigation is uncertain and unfavorable outcomes could have a negative impact on the Company's results of operations and financial condition. Regardless of outcome, litigation can have an adverse impact on the Company because of the defense costs, diversion of management resources and other factors.

In connection with the Company's definitive agreement to acquire Magma Design Automation, Inc. (Magma), on December 5, 2011, December 9, 2011, and December 13, 2011, purported Magma stockholders filed shareholder class action lawsuits against Magma, Magma's directors and the Company.

On December 5, 2011, plaintiff Dynetix Design Solutions, Inc. filed a patent infringement lawsuit against the Company.

We currently do not anticipate that a loss associated with these lawsuits is probable or reasonably estimable. See Note 14 for further information regarding these lawsuits.