(9) Leases

 

The Company’s operating lease portfolio is comprised of operating leases for office, warehouse space and equipment. Certain of the Company’s leases include one or more options to renew or terminate the lease at the Company’s discretion. The Company regularly evaluates the renewal and termination options and when they are reasonably certain of exercise, includes the renewal or termination option in our lease term.

 

As of June 30, 2021, the operating lease right-of-use “ROU” asset had a balance of $1,785 which is included in the “Operating lease right-of-use assets” line item of these condensed consolidated financial statements and current and non-current lease liabilities related to the ROU asset of $499 and $1,523 respectively. As of December 31, 2020, the ROU asset had a balance of $1,827 which is included in the “Operating lease right-of-use assets” line item of these condensed consolidated financial statements and current and non-current lease liabilities related to the ROU asset of $431 and $1,651 respectively. These are included in the “Current portion of operating lease obligations” and “Long-term operating lease obligations, net of current portion” line items of these condensed consolidated financial statements. The discount rates used for leases accounted for under ASC 842 are based on an interest rate yield curve developed for the leases in the Company’s portfolio.

 

The office leases contain variable lease payments which consist primarily of rent escalations based on an established index or rate and taxes, insurance, and common area or other maintenance costs, which are paid based on actual costs incurred by the lessor.

 

Quantitative information regarding the Company’s leases is as follows:

 

                         
   Three Months Ended June 30,   Six Months Ended June 30, 
   2021   2020   2021   2020 
Components of lease cost                
Finance lease cost components:                    
Amortization of finance lease assets  $14   $20   $28   $37 
Interest on finance lease liabilities   5    10    11    21 
Total finance lease costs  $19   $30   $39   $58 
Operating lease cost components:                    
Operating lease cost  $146   $145   $290   $285 
Variable lease cost   29    56    60    83 
Short-term lease cost   11    10    21    12 
Total operating lease costs   186    211    371    380 
Total lease cost  $205   $241   $410   $438 

 

Supplemental cash flow information related to leases is as follows for the six months period ended June 30:       

 

   2021   2020 
Cash paid for amounts included in the measurement of lease liabilities:        
 Operating cash outflow from operating leases  $368   $346 
           
Weighted-average remaining lease term-finance leases (in years)   1.1    1.7 
Weighted-average remaining lease term-operating leases (in years)   2.9    2.7 
Weighted-average discount rate-finance leases   9.3%   9.3%
Weighted-average discount rate-operating leases   13.4%   14.6%

 

The future maturities of the Company’s finance and operating leases as of June 30, 2021 is as follows: 

 

       Finance Leases   Operating Leases   Total  
2021   $ 96   $ 374   $ 470  
2022     109     761     870  
2023     5     747     752  
2024         636     636  
2025         42     42  
2026 and thereafter         2     2  
Total payments   $ 210   $ 2,562   $ 2,772  
Less amounts representing interest     (12 )   (540 )   (552 )
Total minimum payments required:   $ 198   $ 2,022   $ 2,220  

 

The future maturities of the Company’s finance and operating leases as of June 30, 2020 is as follows:

 

       Finance Leases   Operating Leases   Total  
2020   $ 119   $ 344   $ 463  
2021     196     701     897  
2022     109     720     829  
2023     5     705     710  
2024         595     595  
2025 and thereafter         1     1  
Total payments   $ 429   $ 3,066   $ 3,495  
Less amounts representing interest     (39 )   (798 )   (837 )
Total minimum payments required:   $ 390   $ 2,268   $ 2,658