Major classes of utility plant as of December 31 are as follows:







 

 

 

 

 



 

 

 

 

 

Electric plant in service:

2017

 

2016

Steam production plant

$

101,116,277 

 

$

101,116,277 

Hydroelectric production plant

 

33,659,129 

 

 

33,659,129 

Other production plant

 

287,765,474 

 

 

287,404,484 

Transmission plant

 

296,018,078 

 

 

282,040,969 

Distribution plant

 

315,862,812 

 

 

294,641,485 

General plant

 

55,164,994 

 

 

54,982,432 

Unclassified electric plant in service1

 

60,294,349 

 

 

83,457,981 

Intangible plant1

 

5,455,371 

 

 

5,455,371 

Beluga River Natural Gas Field (BRU Asset & ARO)

 

47,927,331 

 

 

47,927,331 

Other1

 

1,828,409 

 

 

1,828,409 

Total electric plant in service

 

1,205,092,224 

 

 

1,192,513,869 

Construction work in progress

 

17,952,573 

 

 

18,455,940 

Total electric plant in service and construction work in progress

$

1,223,044,797 

 

$

1,210,969,809 



1Unclassified electric plant in service consists of complete unclassified general plant, generation plant, transmission plant and distribution plant. Depreciation of unclassified electric plant in service has been included in functional plant depreciation accounts in accordance with the anticipated eventual classification of the plant investment. Intangible plant represents Chugach's share of a Bradley Lake transmission line financed internally. Other represents Electric Plant Held for Future Use.