Acquisitions Acquisitions
12 Months Ended
Dec. 31, 2023
Business Combinations [Abstract]  
Acquisitions Disclosures [Text Block] ACQUISITIONS
Rexford — On October 2, 2023, the Company, through its subsidiary Rexford 1 Holdings, LLC., entered into an agreement for the purchase of 100% of the membership interests in 20SD 8me LLC., a 300 MW solar and 240 MW BESS project. The transaction was accounted for as an asset acquisition of variable interest entities that did not meet the definition of a business. The assets acquired and liabilities assumed were recorded at their fair values, which equaled the fair value of the consideration paid of approximately $253 million, including contingent consideration of $4 million. The nature of the assets acquired is largely tangible as they relate to construction in progress, along with typical working capital items and certain equipment.
We estimated the fair value of the construction in progress at approximately $282 million, using a discounted cash flow valuation methodology. The cash flow assumptions align with executed contracts, and incorporate forward energy pricing curves after the expiration date of such contracts. The cash flow and discount rates assumptions are considered Level 3 inputs. The contingent consideration will be updated quarterly with any prospective changes in fair value recorded through earnings. Rexford is reported in the Renewables SBU reportable segment.
Petersburg Solar Project — On August 31, 2023, the Company entered into agreements for project development and for the purchase of 100% of the membership in Petersburg Energy Center, LLC, a 250 MW solar and BESS project. The transaction was accounted for as an asset acquisition of variable interest entities that did not meet the definition of a business. The assets acquired and liabilities assumed were recorded at their fair values, which equaled the fair value of the consideration paid of approximately $49 million. Petersburg Solar Project is reported in the Utilities SBU reportable segment.
Calhoun — On July 18, 2023, the Company entered into an agreement for the purchase of 100% of the membership interests in Calhoun County Solar Project, LLC., which holds a late development-stage 125 MW solar project. The transaction was accounted for as an asset acquisition of variable interest entities that did not meet the definition of a business. The assets acquired and liabilities assumed were recorded at their fair values, which equaled the fair value of the consideration paid of approximately $64 million, including contingent consideration of $42 million. The estimated fair value of the contingent consideration for Calhoun was determined using probability-weighted discounted cash flows based on internal forecasts, which are considered Level 3 inputs. The probability of achieving the milestone payment used to calculate the acquisition date fair value of the contingent consideration was 99%. Payments under the contingent consideration arrangement are largely binary and thus, a single probability of achieving the milestone was applied in the calculation of fair value. The contingent consideration will be updated quarterly with any prospective changes in fair value recorded through earnings. Calhoun is reported in the Renewables SBU reportable segment.
Bellefield — On June 5, 2023, the Company entered into an agreement for the purchase of 100% of the membership interests in the Bellefield projects, consisting of two late development-stage solar and BESS projects of 1 GW each. The transaction was accounted for as an asset acquisition of variable interest entities that did not meet the definition of a business. The Company agreed to make total cash payments including reimbursement of development and equipment costs of up to approximately $449 million, a portion of which is contingent upon future milestones and price adjustments. This contingent consideration will be updated quarterly with any prospective changes in fair value recorded through earnings.
The assets acquired and liabilities assumed were recorded at their fair values, which equaled the fair value of the consideration to be paid of approximately $358 million, including cash paid of $165 million, contingent consideration of $165 million, and deferred payments of $28 million. The significant assets acquired include project development intangibles, land option intangibles, deposits made towards integral equipment purchases, and typical working capital items.
We estimated the fair value of the project development intangibles at approximately $200 million, using a discounted cash flow valuation methodology. The cash flow assumptions align with executed contracts, and incorporate forward energy pricing curves after the expiration date of such contracts. The cash flow assumptions and discount rates are considered Level 3 inputs.
We estimated the fair value of the land option intangibles at approximately $82 million, by comparing the intrinsic value (estimated using a sales comparison approach for purchase options and an income capitalization method for lease options) and the strike price of each option.
The estimated fair value of the contingent consideration of Bellefield was determined using probability-weighted discounted cash flows based on internal forecasts, which are considered Level 3 inputs. The weighted average probability of achieving the development milestones used to calculate the acquisition date fair value of the contingent consideration was 91.9%. Payments under the contingent consideration arrangements are largely binary and thus, a single probability of achieving the milestone was applied in the calculation of fair value. The contingent consideration will be updated quarterly with any prospective changes in fair value recorded through earnings. Bellefield is reported in the Renewables SBU reportable segment.
Bolero Solar Park — On June 9, 2023, the Company, through its subsidiary AES Andes S.A., acquired 100% of the equity interests in Helio Atacama Tres SpA, owner of the Bolero photovoltaic power plant for consideration of $114 million. The transaction was accounted for as an asset acquisition that did not meet the definition of a business. As Helio Atacama Tres is not a VIE, any difference between the fair value of the assets and consideration transferred will be allocated to PP&E on a relative fair value basis. Helio Atacama Tres is reported in the Energy Infrastructure SBU reportable segment.
Cubico II — On November 30, 2022, the Company, through its subsidiary AES Brasil Energia S.A ("AES Brasil") acquired 100% of shares of an operational wind complex comprised of (i) Ventos de São Tomé Holding S.A., (ii) Ventos de São Tito Holdings S.A., and (iii) REB Empreendimentos e Administradora de Bens S.A. The transaction was accounted for as an asset acquisition that did not meet the definition of a business. The assets acquired and liabilities assumed were recorded at their relative fair values. The total purchase price for the acquisition was $185 million. The Cubico II wind complex is recorded in the Renewables SBU reportable segment.
Agua Clara — On June 17, 2022, the Company, through its subsidiaries AES Dominicana Renewable Energy and AES Andres DR, S.A., acquired 100% of the equity interests in Agua Clara, S.A.S., a wind project, for consideration of $98 million. The transaction was accounted for as an asset acquisition that did not meet the definition of a business. As Agua Clara is not a VIE, any difference between the fair value of the assets and consideration transferred was allocated to PP&E on a relative fair value basis. Agua Clara is reported in the Renewables SBU reportable segment.
Tunica Windpower, LLC — On June 17, 2022, the Company entered into an agreement for the purchase of 100% of the membership interests in Tunica Windpower, LLC. The transaction was accounted for as an asset acquisition of variable interest entities that did not meet the definition of a business. The assets acquired and liabilities assumed were recorded at their fair values, which equaled the fair value of the consideration paid of approximately $22 million, including contingent consideration of $7 million. The contingent consideration will be updated quarterly with any prospective changes in fair value recorded through earnings. Tunica Windpower is reported in the Renewables SBU reportable segment.
Windsor PV1, LLC — On May 27, 2022, the Company entered into an agreement for the purchase of 100% of the membership interests in Windsor PV1, LLC, an early development-stage solar project. The transaction was accounted for as an asset acquisition of variable interest entities that did not meet the definition of a business. The assets acquired and liabilities assumed were recorded at their fair values, which equaled the fair value of the consideration paid of approximately $17 million, including contingent consideration of $5 million. The contingent consideration will be updated quarterly with any prospective changes in fair value recorded through earnings. Windsor is reported in the Renewables SBU reportable segment.
New York Wind — In November 2021, AES Clean Energy Development, LLC completed the acquisition of Cogentrix Valcour Intermediate Holdings, LLC for $352 million cash consideration, including customary purchase price adjustments, plus the assumption of $126 million of non-recourse debt. The transaction includes operating wind assets spread across six sites and will complement AES Clean Energy’s existing operating and development solar and energy storage assets in the state of New York. The transaction was accounted for as a business combination, therefore, the assets acquired and liabilities assumed at acquisition date were recorded at their fair values, which resulted in the recognition of $199 million of goodwill. This goodwill represents the potential opportunity to repower the acquired assets and thus obtain additional cash flows upon repowering. The Company recorded preliminary amounts for the purchase price allocation in 2021.
In the first quarter of 2022, the Company finalized the purchase price allocation related to the acquisition of Cogentrix Valcour Intermediate Holdings, LLC. There were no significant adjustments made to the preliminary purchase price allocation recorded in the fourth quarter of 2021 when the acquisition was completed. New York Wind is reported in the Renewables SBU reportable segment.
Hardy Hills Solar — In December 2021, AES Indiana completed the acquisition of Hardy Hills solar project, which included assets of $52 million primarily consisting of project development intangibles. The transaction was accounted for as an asset acquisition of a variable interest entity that did not meet the definition of a business; therefore, the individual assets and liabilities were recorded at their fair values. A $6 million gain was recorded in Other income on the Consolidated Statement of Operations for the difference between the consideration transferred and the assets and liabilities recognized. The total consideration included $3 million of contingent consideration dependent on the amount of certain future costs incurred by the project. Hardy Hills Solar is reported in the Utilities SBU reportable segment.
Community Energy — In December 2021, AES Clean Energy Development, LLC completed the acquisition of Community Energy, LLC for $217 million cash consideration, including customary purchase price adjustments, plus the assumption of $38 million of non-recourse debt. At closing, the Company made a cash payment of $232 million, which included $15 million of the assumed non-recourse debt. The transaction was accounted for as a business combination; therefore, the assets acquired and liabilities assumed at the acquisition date were recorded at their fair values, which resulted in the recognition of $90 million of goodwill.
In the first quarter of 2022, the Company finalized the purchase price allocation related to the acquisition of Community Energy, LLC. There were no significant adjustments made to the preliminary purchase price allocation recorded in the fourth quarter of 2021 when the acquisition was completed. Community Energy is reported in the Renewables SBU reportable segment.
sPower Projects — In December 2021, AES Clean Energy Development Holdings, LLC entered into an agreement with AIMCo, our minority partner in AES Clean Energy Development, LLC and our partner in the sPower equity method investment. As part of this transaction, AES acquired an additional 25% ownership interest in specifically identified projects of sPower from AIMCo, in exchange for a 25% ownership interest in the Mountain View and Laurel Mountain wind operating projects, plus $28 million cash.
The transaction was accounted for as an asset acquisition. The sPower projects received were remeasured at their acquisition-date fair values, resulting in the recognition of a $35 million gain, recorded in Other Income on the Consolidated Statement of Operations. See Note 8Investments in and Advances to Affiliates for further information. The Company recorded $3 million in additional paid-in-capital, representing the difference between the fair value of the consideration transferred and the recognition of the noncontrolling interest.
Subsequent to the closing of the transaction, AES holds a 75% ownership interest in the Mountain View and Laurel Mountain wind operating projects and a 75% ownership interest in specifically identified projects of sPower through its ownership of AES Clean Energy Development, LLC, and 50% ownership interest in the sPower equity method investment. AIMCo holds the remaining 25% minority interest in AES Clean Energy Development, LLC and 50% ownership interest in sPower. sPower is reported in the Renewables SBU reportable segment.
Serra Verde Wind Project — In July 2021, AES Brasil completed the acquisition of the Serra Verde Wind Project for $18 million, including contingent consideration and working capital adjustment, with the last annual installment ended on July 19, 2023. The transaction was accounted for as an asset acquisition of variable interest entities that did not meet the definition of a business; therefore, the consideration transferred, plus transaction costs were allocated to the individual assets acquired and liabilities assumed based on their relative fair values. Serra Verde is reported in the Renewables SBU reportable segment.
Cajuína Wind Project — In May 2021, AES Brasil completed the acquisition of the Cajuína Wind Project phase I for $22 million, and in July 2021, AES Brasil completed the acquisition of the Cajuína Wind Project phase II for $24 million plus $3 million of contingent consideration paid in October, 2022. The cash payments were negotiated in four annual installments and the last payments will occur on March 31, 2024 and on July 29, 2024, respectively. These transactions were accounted for as asset acquisitions of variable interest entities that did not meet the definition of a business; therefore, the consideration transferred, plus transaction costs were allocated to the individual assets acquired and liabilities assumed based on their relative fair values. Cajuína is reported in the Renewables SBU reportable segment.
Cubico I — In April 2021, AES Brasil completed the acquisition of the Cubico I wind complex, which includes the Mandacaru and Salinas facilities, for $109 million, subject to customary working capital adjustments. The transaction was accounted for as an asset acquisition, therefore the consideration transferred, plus transaction costs, were allocated to the individual assets acquired and liabilities assumed based on their relative fair values. Cubico I is reported in the Renewables SBU reportable segment.
AES Clean Energy Development — In February 2021, the Company substantially completed the merger of the sPower and AES Renewable Holdings development platforms to form AES Clean Energy Development, which will serve as the development vehicle for all future renewables projects in the U.S. As part of the transaction, AES acquired an additional 25% ownership interest in the sPower development platform from AIMCo, our existing partner in the sPower equity method investment, in exchange for a 25% ownership interest in specifically identified development entities of AES Renewable Holdings, certain future exit rights in the new partnership, and $7 million of cash.
The sPower development platform was carved-out of AES’ existing equity method investment. AES’ basis in the portion of assets transferred was $102 million, and the contribution to AES Clean Energy Development resulted in a corresponding decrease in the carrying value of the sPower investment.
During the first quarter of 2021, the sPower development assets transferred were remeasured at their acquisition-date preliminary fair values, resulting in the recognition of a $36 million gain, recorded in Other income on the Consolidated Statement of Operations. The Company recorded $81 million in Goodwill as of the acquisition date, representing the difference between the fair value of the consideration transferred, the noncontrolling interest in the sPower development platform, and the acquisition-date fair value of the Company’s previously held equity interest and the fair value of the identifiable assets acquired and liabilities assumed.
During the second quarter of 2021, the Company recorded measurement period adjustments as result of additional facts and circumstances that existed as of the date of the acquisition but were not yet known as of the time of the valuation performed in the first quarter of 2021. As a result, the estimated acquisition-date carrying value and fair values of the sPower development assets transferred were increased, which resulted in the recognition of an additional $178 million gain, for an updated gain of $214 million. Furthermore, the estimated goodwill as of the acquisition date was reduced to $45 million, as a result of adjustments to the fair value of the consideration paid and updates to the fair values of separately identifiable intangible assets. The Company finalized the purchase price allocation in the third quarter of 2021, which did not result in any material measurement period adjustments.
Subsequent to the closing of the transaction, AES holds a 75% ownership interest in AES Clean Energy Development. AIMCo holds the remaining 25% minority interest along with certain partnership rights, though currently not in effect, that would enable AIMCo to exit in the future. AIMCo’s minority interest is recorded as temporary equity in Redeemable stock of subsidiaries on the Consolidated Balance Sheets. See Note 16Redeemable Stock of Subsidiaries for further information. AES Clean Energy Development is reported in the Renewables SBU reportable segment.
Great Cove Solar— In January 2021 and May 2021, AES Clean Energy Development, LLC completed the acquisitions of Great Cove I and II, respectively. The fair value of the initial consideration paid to acquire Great Cove I and Great Cove II was $13 million and $24 million, which included contingent consideration liabilities of $6 million and $22 million, respectively. These acquisitions were accounted for as asset acquisitions of variable interest entities that did not meet the definition of a business; therefore, the assets acquired and liabilities assumed were recorded at their fair values, which equaled the fair value of the consideration. During the third quarter of 2021, the contingent liabilities which related primarily to certain price adjustment features were remeasured, resulting in contingent consideration assets of $2 million and $12 million for Great Cove I and Great Cove II, respectively. This remeasurement resulted in a gain of $32 million recorded in Other income in the Consolidated Statement of Operations during the third quarter of 2021. In October 2021, the Company amended the agreement, resulting in the reclassification of the previously contingent consideration assets to Prepaid expenses. In December 2021, the Company acquired Community Energy, LLC (as further described above), and such remaining prepaid amounts were written off to Other income in the Consolidated Statement of Operations. Great Cove Solar is reported in the Renewables SBU reportable segment.