XML 25 R11.htm IDEA: XBRL DOCUMENT v3.23.2
Revenue
12 Months Ended
Jun. 30, 2023
Revenue from Contract with Customer [Abstract]  
Revenue from Contract with Customer [Text Block] Revenue
Remaining Performance Obligations
We had $459.7 million of remaining performance obligations yet to be satisfied as of June 30, 2023. We expect to recognize approximately $381.0 million of our remaining performance obligations as revenue within the next twelve months.
Contract Balances
Contract terms with customers include the timing of billing and payment, which usually differs from the timing of revenue recognition. As a result, we carry contract assets and liabilities in our balance sheet. These contract assets and liabilities are calculated on a contract-by-contract basis and reported on a net basis at the end of each period and are classified as current. We present our contract assets in the balance sheet as Costs and Estimated Earnings in Excess of Billings on Uncompleted Contracts ("CIE"). CIE consists of revenue recognized in excess of billings. We present our contract liabilities in the balance sheet as Billings on Uncompleted Contracts in Excess of Costs and Estimated Earnings ("BIE"). BIE consists of billings in excess of revenue recognized. The following table provides information about CIE and BIE:

June 30,
2023
June 30,
2022
Change
(In thousands)
Costs and estimated earnings in excess of billings on uncompleted contracts$44,888 $44,752 $136 
Billings on uncompleted contracts in excess of costs and estimated earnings(85,436)(65,106)(20,330)
Net contract liabilities$(40,548)$(20,354)$(20,194)

The difference between the beginning and ending balances of our CIE and BIE primarily results from the timing of revenue recognized relative to its billings. The amount of revenue recognized during the fiscal year ended June 30, 2023 that was included in the prior period BIE balance was $57.9 million. This revenue consists primarily of work performed during the period on contracts with customers that had advance billings.
Progress billings in accounts receivable at June 30, 2023 and June 30, 2022 included retentions to be collected within one year of $16.3 million and $16.1 million, respectively. Contract retentions collectable beyond one year are included in Other assets, non-current in the Consolidated Balance Sheets and totaled $10.0 million as of June 30, 2023 and $4.0 million as of June 30, 2022.
Unpriced Change Orders and Claims
As of June 30, 2023 and June 30, 2022, costs and estimated earnings in excess of billings on uncompleted contracts included revenue for unpriced change orders and claims of $9.7 million and $8.9 million, respectively. The amounts ultimately realized may be different than the recorded amounts resulting in adjustments to future earnings. Generally we expect collection of amounts related to unpriced change orders and claims within twelve months. However, customers may not pay these amounts until final resolution of related claims, which may extend beyond one year.
Disaggregated Revenue
Revenue disaggregated by reportable segment is presented in Note 13 - Segment Information. The following series of tables presents revenue disaggregated by geographic area where the work was performed and by contract type:

Geographic Disaggregation:

Fiscal Years Ended
June 30,
2023
June 30,
2022
June 30,
2021
(In thousands)
United States$720,140 $640,512 $604,739 
Canada61,691 63,045 61,703 
Other international13,189 4,223 6,956 
Total$795,020 $707,780 $673,398 


Contract Type Disaggregation:

Fiscal Years Ended
June 30,
2023
June 30,
2022
June 30,
2021
(In thousands)
Fixed-price contracts$419,426 $421,188 $444,042 
Time and materials and other cost reimbursable contracts375,594 286,592 229,356 
Total$795,020 $707,780 $673,398 
Revisions in Estimates
Fiscal 2023
During fiscal 2023, unfavorable changes in the estimated recovery of change orders and increased forecasted costs to complete and closeout certain midstream gas processing capital work in the Process and Industrial Facilities segment resulted in a $12.6 million reduction of gross profit during the fiscal year. These charges were primarily the result of the client not approving adequate compensation to us for the impact that excessive scope changes had on our ability to progress the work according to forecast and for the impacts of global supply chain issues and inflation. We have accrued the full expected loss for the work, which is now mechanically complete.
Fiscal 2022
Our results of operations were materially impacted by an increase in the forecasted costs to complete a midstream gas processing project in the Process and Industrial Facilities segment. The project reduced gross profit by $8.7 million during fiscal 2022. The increase in forecasted costs was primarily due to poor performance of a now terminated subcontractor, which required rework, as well as supply chain and cost escalation issues. This project has since reached mechanical completion.
In fiscal 2022, our results of operations were materially impacted by an increase in the costs required to complete a thermal energy storage tank repair and maintenance project in the Storage and Terminal Solutions segment, which resulted in a decrease in gross profit of $6.3 million during the fiscal year. We achieved substantial completion on this project in fiscal 2022.
During fiscal 2022, our results of operations were materially impacted by changes in the forecasted costs to complete two large capital projects in the Utility and Power Infrastructure segment and an unfavorable settlement of a claim with a customer in the same segment. Increases in the forecasted costs to complete the first project resulted in the project reducing gross profit by $3.6 million during fiscal 2022. Increased forecasted costs to the complete the second capital project resulted in the project reducing gross profit by $2.2 million during the fourth quarter of fiscal 2022 and $0.1 million during fiscal 2022. We recognized $78.1 million of revenue on this project during fiscal 2022 at a near break-even margin as a result of the change in estimate. Both projects reached substantial completion in fiscal 2023. The unfavorable settlement of a claim with a customer reduced gross profit by $2.1 million.
Fiscal 2021
Our results of operations in fiscal 2021 were materially impacted by increases in the forecasted costs to complete a large capital project in the Utility and Power Infrastructure segment. The project reduced gross profit by $5.8 million in fiscal 2021. This project reached substantial completion in fiscal 2023.

During the fourth quarter of fiscal 2021, we reached a settlement on a contract dispute over the construction of a crude oil terminal. The project's financial impact for the fiscal year ended June 30, 2021 was a $2.9 million reduction to gross profit in the Storage and Terminal Solutions segment. The settlement resulted in a cash receipt of $8.9 million in the first quarter of fiscal 2022, which enabled us to avoid future legal costs and litigation risk.

During the third quarter of fiscal 2021, we achieved mechanical completion of a large crude oil terminal project, demobilized from the project site and completed its assessment of additional recovery of unpriced change orders. The project's financial impact for the fiscal year ended June 30, 2021 was a $3.8 million reduction to gross profit in the Storage and Terminal Solutions segment.