XML 26 R11.htm IDEA: XBRL DOCUMENT v3.22.2.2
Revenue
12 Months Ended
Jun. 30, 2022
Revenue from Contract with Customer [Abstract]  
Revenue from Contract with Customer [Text Block] Revenue
Remaining Performance Obligations
We had $484.2 million of remaining performance obligations yet to be satisfied as of June 30, 2022. We expect to recognize approximately $389.9 million of our remaining performance obligations as revenue within the next twelve months.
Contract Balances
Contract terms with customers include the timing of billing and payment, which usually differs from the timing of revenue recognition. As a result, we carry contract assets and liabilities in our balance sheet. These contract assets and liabilities are calculated on a contract-by-contract basis and reported on a net basis at the end of each period and are classified as current. We present our contract assets in the balance sheet as Costs and Estimated Earnings in Excess of Billings on Uncompleted Contracts ("CIE"). CIE consists of revenue recognized in excess of billings. We present our contract liabilities in the balance sheet as Billings on Uncompleted Contracts in Excess of Costs and Estimated Earnings ("BIE"). BIE consists of billings in excess of revenue recognized. The following table provides information about CIE and BIE:

June 30,
2022
June 30,
2021
Change
(In thousands)
Costs and estimated earnings in excess of billings on uncompleted contracts$44,752 $30,774 $13,978 
Billings on uncompleted contracts in excess of costs and estimated earnings(65,106)(53,832)(11,274)
Net contract liabilities$(20,354)$(23,058)$2,704 
The difference between the beginning and ending balances of our CIE and BIE primarily results from the timing of revenue recognized relative to its billings. The amount of revenue recognized during the fiscal year ended June 30, 2022 that was included in the prior period BIE balance was $49.2 million. This revenue consists primarily of work performed during the period on contracts with customers that had advance billings.
Progress billings in accounts receivable at June 30, 2022 and June 30, 2021 included retentions to be collected within one year of $16.1 million and $19.9 million, respectively. Contract retentions collectable beyond one year are included in other assets in the Consolidated Balance Sheets and totaled $4.0 million as of June 30, 2022 and $3.1 million as of June 30, 2021.
Disaggregated Revenue
Revenue disaggregated by reportable segment is presented in Note 13 - Segment Information. The following series of tables presents revenue disaggregated by geographic area where the work was performed and by contract type:

Geographic Disaggregation:

Fiscal Years Ended
June 30,
2022
June 30,
2021
June 30,
2020
(In thousands)
United States$640,512 $604,739 $1,020,083 
Canada63,045 61,703 70,133 
Other international4,223 6,956 10,722 
Total$707,780 $673,398 $1,100,938 


Contract Type Disaggregation:

Fiscal Years Ended
June 30,
2022
June 30,
2021
June 30,
2020
(In thousands)
Fixed-price contracts$421,188 $444,042 $685,559 
Time and materials and other cost reimbursable contracts286,592 229,356 415,379 
Total$707,780 $673,398 $1,100,938 

Typically, we assume more risk with fixed-price contracts since increases in cost to perform the work may not be recoverable. However, these types of contracts typically offer higher profits than time and materials and other cost reimbursable contracts when completed at or below the costs originally estimated. The profitability of time and materials and other cost reimbursable contracts is typically lower than fixed-price contracts and is usually less volatile than fixed-price contracts since the profit component is factored into the rates charged for labor, equipment and materials, or is expressed in the contract as a percentage of the reimbursable costs incurred.
Revisions in Estimates
Our results of operations were materially impacted by an increase in the forecasted costs to complete a midstream gas processing project in the Process and Industrial Facilities segment. The project reduced gross profit by $8.7 million during fiscal 2022. The increase in forecasted costs was primarily due to poor performance of a now terminated subcontractor, which required rework, as well as supply chain and escalation issues, in order to meet our client's expectations. We expect to complete the project during the second quarter of fiscal 2023.
Our results of operations were materially impacted by changes in the forecasted costs to complete two large capital projects in the Utility and Power Infrastructure segment. Improved project execution on the first project resulted in an increase in gross profit of $2.2 million during the second half of fiscal 2022. However, increases in the forecasted costs to complete this project during the first half of fiscal 2022 resulted in the project reducing gross profit by $3.6 million during fiscal 2022. The increase in forecasted costs during the first half of the fiscal year was principally due to unexpected equipment repairs during commissioning that delayed the scheduled completion and increased the estimated costs to complete. We achieved a critical performance milestone during the second quarter of fiscal 2022, which significantly reduced our financial exposure on the project.
Increased forecasted costs to the complete the second project resulted in the project reducing gross profit by $2.2 million during the fourth quarter of fiscal 2022 and $0.1 million during fiscal 2022. We recognized $78.1 million of revenue on this project during the year at a near break-even margin as a result of the change in estimate. The increase in forecasted costs was the result of higher than anticipated subcontractor costs and labor costs as the project neared completion. We expect to complete the project during the second quarter of fiscal 2023.
Our results of operations were materially impacted by an increase in the costs required to complete a thermal energy storage tank repair and maintenance project in the Storage and Terminal Solutions segment, which resulted in a decrease in gross profit of $6.3 million in fiscal 2022. The increase in costs was primarily due to changes in repair scope, expanded client weld testing and associated schedule delays. We achieved substantial completion on this project in the fourth quarter of fiscal 2022.