Revenue Recognition
Adoption of New Revenue Recognition Standard
The Company adopted ASU No. 2014-09, Revenue from Contracts with Customers (Topic 606) on July 1, 2018. The standard outlines a single comprehensive model for entities to use in accounting for revenue arising from contracts with customers and supersedes most current revenue recognition guidance, including industry-specific guidance, and is applicable to all of the Company's contracts with customers. The core principle of the revenue model is that "an entity recognizes revenue to depict the transfer of promised goods or services to customers in an amount that reflects the consideration to which the entity expects to be entitled in exchange for those goods or services." The Company used the modified retrospective method of application. Under the modified retrospective method, revenue recognized on completed contracts is not restated, however contracts in progress are accounted for as if they were under this new standard at inception. Any difference between historical revenue and revenue under the new standard is recorded as a cumulative effect adjustment to retained earnings as of the date of adoption. The cumulative impact of adopting Topic 606 was immaterial and did not require an adjustment to retained earnings. See Note 2 – Revenue for new disclosures required as a result of adopting Topic 606.
General Information about our Contracts with Customers
Our revenues come from contracts to provide engineering, procurement, construction, repair and maintenance and other services. Our engineering, procurement and construction services are usually provided in association with capital projects, which commonly are fixed price contracts and are billed based on project milestones. Our repair and maintenance services typically are cost reimbursable or time and material based contracts and are billed monthly or, for projects of short duration, at the conclusion of the project. The elapsed time from award to completion of performance may be in excess of one year for capital projects.
Step 1: Contract Identification
We do not recognize revenue unless we have identified a contract with a customer. A contract with a customer exists when it has approval and commitment from both parties, the rights and obligations of the parties are identified, payment terms are identified, the contract has commercial substance, and collectibility is probable. We also evaluate whether a contract should be combined with other contracts and accounted for as one single contract. This evaluation requires judgment and could change the timing of the amount of revenue and profit recorded for a given period.
Step 2: Identify Performance Obligations
Next, we identify each performance obligation in the contract. A performance obligation is a promise to provide a distinct good or service or a series of distinct goods or services to the customer. Revenue is recognized separately for each performance obligation in the contract. Many of our contracts have one clearly identifiable performance obligation. However, many of our contracts provide the customer an integrated service that includes two or more of the following services: engineering, procurement, fabrication, construction, repair and maintenance services. For these contracts, we do not consider the integrated services to be distinct within the context of the contract when the separate scopes of work combine into a single commercial objective or capability for the customer. Accordingly, we generally identify one performance obligation in our contracts. The determination of the number of performance obligations in a contract requires significant judgment and could change the timing of the amount of revenue and profit recorded for a given period.
Step 3: Determine Contract Price
After determining the performance obligations in the contract, we determine the contract price. The contract price is the amount of consideration we expect to receive from the customer for completing the performance obligation(s). In a fixed price contract, the contract price is a single lump-sum amount. In reimbursable and time and materials based contracts, the contract price is determined by the agreed upon rates or reimbursements for time and materials expended in completing the performance obligations(s) in the contract.
A number of our contracts contain various cost and performance incentives and penalties that can either increase or decrease the contract price. These variable consideration amounts are generally earned or incurred based on certain performance metrics, most commonly related to project schedule or cost targets. We estimate variable consideration at the most likely amount of additional consideration to be received (or paid in the case of penalties), provided that meeting the variable condition is probable. We include estimated amounts of variable consideration in the contract price to the extent it is probable that a significant reversal of cumulative revenue recognized will not occur when the uncertainty associated with the variable consideration is resolved. Our estimates of variable consideration and determination of whether to include estimated amounts in the contract price are based largely on an assessment of our anticipated performance and all information (historical, current and forecasted) that is reasonably available to us. We reassess the amount of variable consideration each accounting period until the uncertainty associated with the variable consideration is resolved. Changes in the assessed amount of variable consideration are accounted for prospectively as a cumulative adjustment to revenue recognized in the current period.
Step 4: Assign Contract Price to Performance Obligations
After determining the price of the contract, we assign the contract price to the performance obligation(s) in the contract. Since nearly all of our contracts have only one performance obligation, all of the contract price is assigned to the single performance obligation. If a contract has multiple performance obligations, we assign the contract price to each performance obligation based on the stand-alone selling prices of the distinct services that comprise each performance obligation.
Step 5: Recognize Revenue as Performance Obligations are Satisfied
We record revenue for contracts with our customers as we satisfy the contracts' performance obligations. We recognize revenue on performance obligations associated with fixed price contracts for engineering, procurement and construction services over time since these services create or enhance assets the customer controls as they are being created or enhanced. We measure progress of satisfying these performance obligations by using the percentage-of-completion method, which is based on costs incurred to date compared to the total estimated costs at completion, since it best depicts the transfer of control of assets being created or enhanced to the customer.
We recognize revenue over time for reimbursable and time and material based repair and maintenance contracts since the customer simultaneously receives and consumes the benefit of those services as we perform work under the contract. As a practical expedient allowed under ASC 606, we record revenue for these contracts in the amount to which we have a right to invoice for the services performed provided that we have a right to consideration from the customer in an amount that corresponds directly with the value of the performance completed to date.
Costs incurred may include direct labor, direct materials, subcontractor costs and indirect costs, such as salaries and benefits, supplies and tools, equipment costs and insurance costs. Indirect costs are charged to projects based upon direct costs and overhead allocation rates per dollar of direct costs incurred or direct labor hours worked. Typically, customer contracts will include standard warranties that provide assurance that products and services will function as expected. The Company does not sell separate warranties.
We have numerous contracts that are in various stages of completion which require estimates to determine the forecasted costs at completion. Due to the nature of the work left to be performed on many of our contracts, the estimation of total cost at completion for fixed price contracts is complex, subject to many variables and requires significant judgment. Estimates of total cost at completion are made each period and changes in these estimates are accounted for prospectively as cumulative adjustments to revenue recognized in the current period. If estimates of costs to complete fixed price contracts indicate a loss, a provision is made through a contract write-down for the total loss anticipated.
Change Orders
Contracts are often modified through change orders, which are changes to the agreed upon scope of work. Most of our change orders, which may be priced or unpriced, are for goods or services that are not distinct from the existing contract due to the significant integration of services provided in the context of the contract and are accounted for as if they were part of that existing contract. The effect of a change order on the contract price and our measure of progress for the performance obligation to which it relates, is recognized as an adjustment to revenue on a cumulative catch-up basis. For unpriced change orders, we estimate the increase or decrease to the contract price using the variable consideration method described in the Step 3: Determine Contract Price paragraph above. Unpriced change orders are more fully discussed in Note 7 - Commitments and Contingencies.
Claims
Sometimes we seek claims for amounts in excess of the contract price for delays, errors in specifications and designs, contract terminations, change orders in dispute or other causes of additional costs incurred by us. Recognition of amounts as additional contract price related to claims is appropriate only if there is a legal basis for the claim. The determination of our legal basis for a claim requires significant judgment. We estimate the change to the contract price using the variable consideration method described in the Step 3: Determine Contract Price paragraph above. Claims are more fully discussed in Note 7 - Commitments and Contingencies.