XML 46 R33.htm IDEA: XBRL DOCUMENT v3.7.0.1
Revisions in Estimates (Details)
$ in Millions
3 Months Ended
Mar. 31, 2017
USD ($)
project
Sep. 30, 2016
USD ($)
Mar. 31, 2016
USD ($)
project
Change in Accounting Estimates      
Impact From Affirmative Claim Recovery Estimate $ 1.8   $ 2.8
Impact From Estimated Recovery of Backcharge Claims (0.3)   0.0
Construction Segment      
Change in Accounting Estimates      
Change in Accounting Estimate Amount Considered Significant to Individual Project Gross Profit 1.0   1.0
Downward Estimate Changes | Construction Segment | Minimum      
Change in Accounting Estimates      
Range Of Effect On Gross Profit 0.0   0.0
Downward Estimate Changes | Construction Segment | Maximum      
Change in Accounting Estimates      
Range Of Effect On Gross Profit $ 0.0   $ 0.0
Downward Estimate Changes | Large Project Construction Segment      
Change in Accounting Estimates      
Number of Projects with Estimate Changes | project 5   2
Increase (Decrease) on Project Profitability $ (13.0)   $ (5.2)
Downward Estimate Changes | Large Project Construction Segment | Minimum      
Change in Accounting Estimates      
Range Of Effect On Gross Profit (1.3)   (2.1)
Downward Estimate Changes | Large Project Construction Segment | Maximum      
Change in Accounting Estimates      
Range Of Effect On Gross Profit (4.7)   $ (3.1)
Upward Estimate Changes | Construction Segment      
Change in Accounting Estimates      
Number of Projects with Estimate Changes | project     1
Upward Estimate Changes | Construction Segment | Minimum      
Change in Accounting Estimates      
Range Of Effect On Gross Profit 0.0   $ 1.7
Upward Estimate Changes | Construction Segment | Maximum      
Change in Accounting Estimates      
Range Of Effect On Gross Profit $ 0.0   $ 1.7
Upward Estimate Changes | Large Project Construction Segment      
Change in Accounting Estimates      
Number of Projects with Estimate Changes | project 0   2
Increase (Decrease) on Project Profitability $ 0.0   $ 2.4
Upward Estimate Changes | Large Project Construction Segment | Minimum      
Change in Accounting Estimates      
Range Of Effect On Gross Profit 0.0   1.0
Upward Estimate Changes | Large Project Construction Segment | Maximum      
Change in Accounting Estimates      
Range Of Effect On Gross Profit 0.0   1.4
Net Upward Estimate Changes | Construction Segment      
Change in Accounting Estimates      
Increase (Decrease) on Project Profitability     1.7
Net Upward Estimate Changes | Large Project Construction Segment      
Change in Accounting Estimates      
Increase (Decrease) on Project Profitability (13.0)   (2.8)
Contracts Accounted for under Percentage of Completion [Member] | Large Project Construction Segment | Noncontrolling Interest [Member]      
Change in Accounting Estimates      
Increase (Decrease) on Project Profitability (1.6)   0.0
Estimated costs recorded in prior period      
Change in Accounting Estimates      
Impact From Affirmative Claim Recovery Estimate (0.9)   1.7
Revisions to estimated total contract costs      
Change in Accounting Estimates      
Impact From Affirmative Claim Recovery Estimate $ 2.7   $ 1.1
Sales Revenue, Net      
Change in Accounting Estimates      
Misstatement in prior period filing   $ 4.9  
Gross Profit      
Change in Accounting Estimates      
Misstatement in prior period filing   $ 1.6