XML 46 R33.htm IDEA: XBRL DOCUMENT v3.5.0.2
Revisions in Estimates (Details)
$ in Millions
3 Months Ended 6 Months Ended
Jun. 30, 2016
USD ($)
project
Jun. 30, 2015
USD ($)
project
Jun. 30, 2016
USD ($)
project
Jun. 30, 2015
USD ($)
project
Change in Accounting Estimate [Line Items]        
Impact From Affirmative Claim Recovery Estimate $ 17.4   $ 20.2  
Impact from estimated recovery of backcharge claims     7.6 $ 0.0
Construction [Member]        
Change in Accounting Estimate [Line Items]        
Change in Accounting Estimate Amount Considered Significant to Individual Project Gross Profit $ 1.0 $ 1.0 $ 1.0 $ 1.0
Downward Estimate Change [Member] | Construction [Member]        
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes | project 1 2 2 2
Increase (Decrease) on Project Profitability $ (1.0) $ (2.6) $ (2.5) $ (2.6)
Downward Estimate Change [Member] | Construction [Member] | Minimum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit (1.0) (1.1) (1.2) (1.2)
Downward Estimate Change [Member] | Construction [Member] | Maximum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit $ (1.0) $ (1.5) $ (1.3) $ (1.4)
Downward Estimate Change [Member] | Large Project Construction [Member]        
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes | project 4 3 4 4
Increase (Decrease) on Project Profitability $ (14.6) $ (5.7) $ (20.1) $ (9.8)
Downward Estimate Change [Member] | Large Project Construction [Member] | Minimum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit (2.2) (1.2) (3.4) (1.4)
Downward Estimate Change [Member] | Large Project Construction [Member] | Maximum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit $ (5.9) $ (2.4) $ (6.4) $ (3.4)
Upward Estimate Change [Member] | Construction [Member]        
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes | project 0 1 0 4
Increase (Decrease) on Project Profitability $ 0.0 $ 1.3 $ 0.0 $ 6.9
Upward Estimate Change [Member] | Construction [Member] | Minimum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit 0.0 1.3 0.0 1.0
Upward Estimate Change [Member] | Construction [Member] | Maximum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit $ 0.0 $ 1.3 $ 0.0 $ 2.3
Upward Estimate Change [Member] | Large Project Construction [Member]        
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes | project 2 2 4 3
Increase (Decrease) on Project Profitability $ 9.8 $ 4.6 $ 12.3 $ 7.3
Upward Estimate Change [Member] | Large Project Construction [Member] | Minimum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit 2.9 2.3 1.2 2.1
Upward Estimate Change [Member] | Large Project Construction [Member] | Maximum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit 6.9 2.3 6.9 2.9
Contracts Accounted for under Percentage of Completion [Member] | Large Project Construction [Member] | Noncontrolling Interest [Member]        
Change in Accounting Estimate [Line Items]        
Increase (Decrease) on Project Profitability (3.6) (0.5)   (1.0)
Net Downward Estimate Change [Member] | Construction [Member]        
Change in Accounting Estimate [Line Items]        
Increase (Decrease) on Project Profitability (1.0) (1.3) (2.5)  
Net Downward Estimate Change [Member] | Large Project Construction [Member]        
Change in Accounting Estimate [Line Items]        
Increase (Decrease) on Project Profitability (4.8) (1.1) (7.8) (2.5)
Net Upward Estimate Change [Member] | Construction [Member]        
Change in Accounting Estimate [Line Items]        
Increase (Decrease) on Project Profitability       4.3
no material associated cost [Member] | customer [Member]        
Change in Accounting Estimate [Line Items]        
Impact From Affirmative Claim Recovery Estimate $ 2.1   4.9 $ 9.7
Revisions to Estimated Total Contract Costs [Member] [Member] | customer [Member]        
Change in Accounting Estimate [Line Items]        
Impact From Affirmative Claim Recovery Estimate   $ 0.0 $ 15.3