XML 28 R9.htm IDEA: XBRL DOCUMENT v3.3.0.814
Revisions in Estimates
9 Months Ended
Sep. 30, 2015
Change in Accounting Estimate [Abstract]  
Revisions in Estimate
Revisions in Estimates
Our profit recognition related to construction contracts is based on estimates of costs to complete each project. These estimates can vary significantly in the normal course of business as projects progress, circumstances develop and evolve, and uncertainties are resolved. We recognize revenue associated with unapproved change orders and, effective in the first quarter of 2015, affirmative claims against customers to the extent the related costs have been incurred, the amount can be reliably estimated and recovery is probable. Prior to 2015, we recognized revenue on affirmative claims against customers when we had a signed agreement. See Note 1 for further discussion.
We recognize revisions to estimated total costs as soon as the obligation to perform is determined. When we experience significant changes in our estimates of costs to complete, we undertake a process that includes reviewing the nature of the changes to ensure that there are no material amounts that should have been recorded in a prior period rather than as a revision in estimates for the current period. In our review of these changes for the three and nine months ended September 30, 2015 and 2014, we did not identify any amounts that should have been recorded in a prior period. We use the cumulative catch-up method applicable to construction contract accounting to account for revisions in estimates. Under this method, revisions in estimates are accounted for in their entirety in the period of change. There can be no assurance that we will not experience future changes in circumstances or otherwise be required to revise our profitability estimates.
Revenue in an amount equal to cost incurred is recognized if there is not sufficient information to determine the estimated profit on the project with a reasonable level of certainty. The gross profit impact from projects that reached initial profit recognition is not considered to be a change in estimate for purposes of the tables below and is therefore excluded. During the three and nine months ended September 30, 2015, the gross profit impact from projects that reached initial profit recognition was $8.3 million and $21.6 million, respectively. During the three and nine months ended September 30, 2014, the gross profit impact from projects that reached initial profit recognition was $21.4 million and $50.0 million, respectively.
Construction
The net changes in project profitability from revisions in estimates, both increases and decreases that individually had an impact of $1.0 million or more on gross profit were net increases of $3.7 million and $9.4 million for the three and nine months ended September 30, 2015, respectively. The net changes for the three and nine months ended September 30, 2014 were net decreases of $1.0 million and $9.3 million, respectively. The projects are summarized as follows:

Increases
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
(dollars in millions)
 
2015
 
 
2014
 
 
2015
 
 
2014
Number of projects with upward estimate changes
 
1

 
 

 
 
7

 
 
2

Range of increase in gross profit from each project, net
$
5.1

 
$

 
$
1.0 - 5.0

 
$
1.1 - 1.2

Increase to project profitability
$
5.1

 
$

 
$
15.3

 
$
2.3



The increases during the three and nine months ended September 30, 2015 were due to settlements of outstanding issues with contract owners and lower costs than anticipated, as well as estimated cost recovery from claims during the nine months. The increases during the nine months ended September 30, 2014 were due to owner-directed scope changes and lower costs than originally anticipated.

Decreases
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
(dollars in millions)
 
2015
 
 
2014
 
 
2015
 
 
2014
Number of projects with downward estimate changes
 
1

 
 
1

 
 
3

 
 
5

Range of reduction in gross profit from each project, net
$
1.4

 
$
1.0

 
$
1.5 - 2.3

 
$
1.7 - 2.9

Decrease to project profitability
$
1.4

 
$
1.0

 
$
5.9

 
$
11.6



The decreases during the three and nine months ended September 30, 2015 and 2014 were due to additional costs and lower productivity than originally anticipated.

Large Project Construction
The net changes in project profitability from revisions in estimates, both increases and decreases that individually had an impact of $1.0 million or more on gross profit were net increases of $5.1 million and $1.8 million for the three and nine months ended September 30, 2015, respectively. The net changes for the three and nine months ended September 30, 2014 were a net decrease of $8.5 million and a net increase of $25.9 million, respectively. Amounts attributable to non-controlling interests were $1.4 million and $0.3 million of the net increases for the three and nine months ended September 30, 2015, respectively, and were $1.8 million of the net decrease and $5.8 million of the net increase for the three and nine months ended September 30, 2014, respectively. The projects are summarized as follows:
Increases
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
(dollars in millions)
 
2015
 
 
2014
 
 
2015
 
 
2014
Number of projects with upward estimate changes
 
4

 
 
2

 
 
7

 
 
9

Range of increase in gross profit from each project, net
$
1.0 - 3.9

 
$
1.3 - 3.8

 
$
1.5 - 5.1

 
$
1.1 - 11.8

Increase to project profitability
$
9.4

 
$
5.1

 
$
19.9

 
$
43.0


The increases during the three and nine months ended September 30, 2015 were due to settlements of outstanding issues with contract owners and owner-directed scope changes, as well as estimated cost recovery from claims during the nine months. The increases during the three and nine months ended September 30, 2014 were due to higher productivity than originally anticipated, owner-directed scope changes and settlements of outstanding issues with contract owners.
Decreases
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
(dollars in millions)
 
2015
 
 
2014
 
 
2015
 
 
2014
Number of projects with downward estimate changes
 
2

 
 
3

 
 
5

 
 
3

Range of reduction in gross profit from each project, net
$
1.8 - 2.6

 
$
2.0 - 7.0

 
$
2.6 - 4.6

 
$
1.3 - 13.9

Decrease to project profitability
$
4.3

 
$
13.6

 
$
18.1

 
$
17.1


The decreases during the three and nine months ended September 30, 2015 and 2014 were due to additional costs and lower productivity than originally anticipated.