Revisions in Estimates (Details)
$ in Millions
3 Months Ended 9 Months Ended
Sep. 30, 2015
USD ($)
project
Sep. 30, 2014
USD ($)
project
Sep. 30, 2015
USD ($)
project
Sep. 30, 2014
USD ($)
project
Change in Accounting Estimate [Line Items]        
Amount Considered Significant to Individual Project Gross Profit $ 8.3 $ 21.4 $ 21.6 $ 50.0
Construction [Member]        
Change in Accounting Estimate [Line Items]        
Amount Considered Significant to Individual Project Gross Profit     1.0  
Increase (Decrease) on Project Profitability (3.7) 1.0 (9.4) 9.3
Large Project Construction [Member]        
Change in Accounting Estimate [Line Items]        
Amount Considered Significant to Individual Project Gross Profit     1.0  
Contracts Accounted for under Percentage of Completion [Member] | Large Project Construction [Member]        
Change in Accounting Estimate [Line Items]        
Increase (Decrease) on Project Profitability (5.1) 8.5 (1.8) (25.9)
Contracts Accounted for under Percentage of Completion [Member] | Large Project Construction [Member] | Noncontrolling Interest [Member]        
Change in Accounting Estimate [Line Items]        
Increase (Decrease) on Project Profitability $ 1.4 $ (1.8) $ 0.3 $ (5.8)
Upward Estimate Change [Member] | Construction [Member]        
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes | project 1 0 7 2
Increase (Decrease) on Project Profitability $ (5.1) $ 0.0 $ (15.3) $ (2.3)
Upward Estimate Change [Member] | Construction [Member] | Minimum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit (5.1) 0.0 (1.0) (1.1)
Upward Estimate Change [Member] | Construction [Member] | Maximum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit $ (5.1) $ 0.0 $ (5.0) $ (1.2)
Upward Estimate Change [Member] | Large Project Construction [Member]        
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes | project 4 2 7 9
Increase (Decrease) on Project Profitability $ (9.4) $ (5.1) $ (19.9) $ (43.0)
Upward Estimate Change [Member] | Large Project Construction [Member] | Minimum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit (1.0) (1.3) (1.5) (1.1)
Upward Estimate Change [Member] | Large Project Construction [Member] | Maximum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit $ (3.9) $ (3.8) $ (5.1) $ (11.8)
Downward Estimate Change [Member] | Construction [Member]        
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes | project 1 1 3 5
Increase (Decrease) on Project Profitability $ 1.4 $ 1.0 $ 5.9 $ 11.6
Downward Estimate Change [Member] | Construction [Member] | Minimum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit 1.4 1.0 1.5 1.7
Downward Estimate Change [Member] | Construction [Member] | Maximum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit $ 1.4 $ 1.0 $ 2.3 $ 2.9
Downward Estimate Change [Member] | Large Project Construction [Member]        
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes | project 2 3 5 3
Increase (Decrease) on Project Profitability $ 4.3 $ 13.6 $ 18.1 $ 17.1
Downward Estimate Change [Member] | Large Project Construction [Member] | Minimum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit 1.8 2.0 2.6 1.3
Downward Estimate Change [Member] | Large Project Construction [Member] | Maximum [Member]        
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit $ 2.6 $ 7.0 $ 4.6 $ 13.9