The projects are summarized as follows:

Increases
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
(dollars in millions)
 
2015
 
 
2014
 
 
2015
 
 
2014
Number of projects with upward estimate changes
 
1

 
 

 
 
7

 
 
2

Range of increase in gross profit from each project, net
$
5.1

 
$

 
$
1.0 - 5.0

 
$
1.1 - 1.2

Increase to project profitability
$
5.1

 
$

 
$
15.3

 
$
2.3

Decreases
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
(dollars in millions)
 
2015
 
 
2014
 
 
2015
 
 
2014
Number of projects with downward estimate changes
 
1

 
 
1

 
 
3

 
 
5

Range of reduction in gross profit from each project, net
$
1.4

 
$
1.0

 
$
1.5 - 2.3

 
$
1.7 - 2.9

Decrease to project profitability
$
1.4

 
$
1.0

 
$
5.9

 
$
11.6

Large Project Construction [Member]  
Change in Accounting Estimate [Line Items]  
Schedule of Change in Accounting Estimate
Decreases
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
(dollars in millions)
 
2015
 
 
2014
 
 
2015
 
 
2014
Number of projects with downward estimate changes
 
2

 
 
3

 
 
5

 
 
3

Range of reduction in gross profit from each project, net
$
1.8 - 2.6

 
$
2.0 - 7.0

 
$
2.6 - 4.6

 
$
1.3 - 13.9

Decrease to project profitability
$
4.3

 
$
13.6

 
$
18.1

 
$
17.1

The projects are summarized as follows:
Increases
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
(dollars in millions)
 
2015
 
 
2014
 
 
2015
 
 
2014
Number of projects with upward estimate changes
 
4

 
 
2

 
 
7

 
 
9

Range of increase in gross profit from each project, net
$
1.0 - 3.9

 
$
1.3 - 3.8

 
$
1.5 - 5.1

 
$
1.1 - 11.8

Increase to project profitability
$
9.4

 
$
5.1

 
$
19.9

 
$
43.0