The projects are summarized as follows:
Increases
 
 
Three Months Ended March 31,
(dollars in millions)
 
2015
 
 
2014
Number of projects with upward estimate changes
 
2

 
 
5

Range of increase in gross profit from each project, net
$
1.1 - 1.9

 
$
1.3 - 7.9

Increase in project profitability
$
3.0

 
$
16.1

Decreases
 
 
Three Months Ended March 31,
(dollars in millions)
 
2015
 
 
2014
Number of projects with downward estimate changes
 
3

 
 
2

Range of reduction in gross profit from each project, net
$
1.1 - 1.3

 
$
3.4 - 4.5

Decrease in project profitability
$
3.8

 
$