Revisions in Estimates (Details) (USD $)
3 Months Ended 6 Months Ended
Jun. 30, 2014
Jun. 30, 2013
Jun. 30, 2014
Jun. 30, 2013
Change in Accounting Estimate [Line Items]        
Amount Considered Significant to Individual Project Gross Profit $ 24,500,000 $ 8,700,000 $ 28,600,000 $ 15,200,000
Financial Effect on Future Periods 0   0  
Construction [Member]
       
Change in Accounting Estimate [Line Items]        
Amount Considered Significant to Individual Project Gross Profit 1,000,000      
Increase (Decrease) on Project Profitability 1,400,000 500,000 8,300,000 300,000
Contracts Accounted for under Percentage of Completion [Member] | Large Project Construction [Member]
       
Change in Accounting Estimate [Line Items]        
Increase (Decrease) on Project Profitability 25,700,000 8,700,000 34,500,000 17,900,000
Contracts Accounted for under Percentage of Completion [Member] | Large Project Construction [Member] | Noncontrolling Interest [Member]
       
Change in Accounting Estimate [Line Items]        
Increase (Decrease) on Project Profitability 8,200,000 400,000 7,500,000 1,400,000
Upward Estimate Change [Member] | Construction [Member]
       
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes 0 1 0 2
Range Of Effect On Gross Profit 0 (1,600,000) 0  
Increase (Decrease) on Project Profitability 0 1,600,000 0 3,100,000
Upward Estimate Change [Member] | Construction [Member] | Minimum [Member]
       
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit       (1,400,000)
Upward Estimate Change [Member] | Construction [Member] | Maximum [Member]
       
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit       (1,700,000)
Upward Estimate Change [Member] | Large Project Construction [Member]
       
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes 6 5 9 5
Increase (Decrease) on Project Profitability 28,000,000 15,800,000 41,300,000 31,900,000
Upward Estimate Change [Member] | Large Project Construction [Member] | Minimum [Member]
       
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit (1,100,000) (1,300,000) (1,100,000) (1,500,000)
Upward Estimate Change [Member] | Large Project Construction [Member] | Maximum [Member]
       
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit (19,700,000) (8,300,000) (16,300,000) (16,100,000)
Downward Estimate Change [Member] | Construction [Member]
       
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes 1 1 5 2
Range Of Effect On Gross Profit (1,400,000) (2,100,000)    
Increase (Decrease) on Project Profitability 1,400,000 2,100,000 8,300,000 3,400,000
Downward Estimate Change [Member] | Construction [Member] | Minimum [Member]
       
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit     1,100,000 1,000,000
Downward Estimate Change [Member] | Construction [Member] | Maximum [Member]
       
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit     2,200,000 2,400,000
Downward Estimate Change [Member] | Large Project Construction [Member]
       
Change in Accounting Estimate [Line Items]        
Number of Projects with Estimate Changes 1 2 1 2
Range Of Effect On Gross Profit (2,300,000)   (6,800,000)  
Increase (Decrease) on Project Profitability (2,300,000) (7,100,000) (6,800,000) (14,000,000)
Downward Estimate Change [Member] | Large Project Construction [Member] | Minimum [Member]
       
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit   2,800,000   5,200,000
Downward Estimate Change [Member] | Large Project Construction [Member] | Maximum [Member]
       
Change in Accounting Estimate [Line Items]        
Range Of Effect On Gross Profit   $ 4,300,000   $ 8,800,000