Change in Accounting Estimate [Line Items]                      
Revenue Recognition, Percentage of Completion, Recognition Threshold                 25.00%    
Initial gross profit impact from projects exceeding threshold $ 49,751,000 $ 55,858,000 [1] $ 49,596,000 [2] $ 30,058,000 $ 56,808,000 $ 101,099,000 $ 51,916,000 $ 24,936,000 $ 185,263,000 $ 234,759,000 $ 247,963,000
Financial Effect on Future Periods 0               0    
Amount Considered Significant on Individual Project Gross Profit 1,000,000                 1,000,000  
Construction Contract Backlog, Percent 2.00%               2.00%    
Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Increase (Decrease) on Project Profitability                 1,700,000 18,100,000 6,200,000
Construction [Member] | Maximum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Total Contract Value 75,000,000               75,000,000    
Large Project Construction [Member] | Minimum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Total Contract Value 75,000,000               75,000,000    
Contracts Accounted for under Percentage of Completion [Member] | Large Project Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Increase (Decrease) on Project Profitability                 25,500,000 64,600,000 8,900,000
Contracts Accounted for under Percentage of Completion [Member] | Large Project Construction [Member] | Noncontrolling Interest [Member]
                     
Change in Accounting Estimate [Line Items]                      
Increase (Decrease) on Project Profitability                 (5,600,000) 3,100,000 2,800,000
Upward Estimate Change [Member] | Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Initial gross profit impact from projects exceeding threshold                 9,100,000 16,400,000 55,400,000
Increase (Decrease) on Project Profitability                 16,100,000 8,100,000 13,600,000
Number of Projects with Estimate Changes                 6 6 7
Upward Estimate Change [Member] | Construction [Member] | Minimum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Range Of Effect On Gross Profit                 1,100,000 1,000,000 1,000,000
Upward Estimate Change [Member] | Construction [Member] | Maximum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Range Of Effect On Gross Profit                 3,700,000 1,700,000 3,500,000
Upward Estimate Change [Member] | Large Project Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Increase (Decrease) on Project Profitability                 77,500,000 92,000,000 28,300,000
Number of Projects with Estimate Changes                 7 10 9
Upward Estimate Change [Member] | Large Project Construction [Member] | Minimum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Range Of Effect On Gross Profit                 2,600,000 1,000,000 1,100,000
Upward Estimate Change [Member] | Large Project Construction [Member] | Maximum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Range Of Effect On Gross Profit                 34,000,000 24,500,000 6,900,000
Downward Estimate Change [Member] | Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Increase (Decrease) on Project Profitability                 (17,800,000) (26,200,000) (7,400,000)
Number of Projects with Estimate Changes                 5 9 4
Downward Estimate Change [Member] | Construction [Member] | Minimum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Range Of Effect On Gross Profit                 (1,000,000) (1,000,000) (1,400,000)
Downward Estimate Change [Member] | Construction [Member] | Maximum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Range Of Effect On Gross Profit                 (6,900,000) (6,600,000) (2,600,000)
Downward Estimate Change [Member] | Large Project Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Increase (Decrease) on Project Profitability                 (52,000,000) (27,400,000) (19,400,000)
Number of Projects with Estimate Changes                 5 1 5
Downward Estimate Change [Member] | Large Project Construction [Member] | Minimum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Range Of Effect On Gross Profit                 (1,900,000) (27,400,000) (1,200,000)
Downward Estimate Change [Member] | Large Project Construction [Member] | Maximum [Member]
                     
Change in Accounting Estimate [Line Items]                      
Range Of Effect On Gross Profit                 $ (23,500,000) $ (27,400,000) $ (5,100,000)
Not, Complete or Substantially Complete [Member] | Downward Estimate Change [Member] | Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Number of Projects with Estimate Changes                 2    
Complete or Substantially Complete [Member] | Downward Estimate Change [Member] | Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Number of Projects with Estimate Changes                 3    
Contract 1, that was not complete or substantially complete [Member] | Not, Complete or Substantially Complete [Member] | Downward Estimate Change [Member] | Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Percent Complete 85.20%               85.20%    
Contract 2, that was not complete or substantially complete [Member] | Not, Complete or Substantially Complete [Member] | Downward Estimate Change [Member] | Construction [Member]
                     
Change in Accounting Estimate [Line Items]                      
Percent Complete 86.20%               86.20%    
[1] Net income for the quarter ended September 30 is approximately $2.1 million ($3.0 million pre-tax) higher than the amount previously reported in our Quarterly Report Form 10-Q for the quarterly period ended September 30, 2013 of $4.5 million. The pre-tax adjustments were primarily related to (i) an over-accrual of pre-bid costs which affected selling, general and administrative expenses and accrued and other current liabilities in the amount of $1.4 million and (ii) a revision in equipment-related costs, which affected cost of revenue and property and equipment in the amount of $1.6 million.
[2] Net income for the quarter ended June 30 is approximately $1.4 million ($1.9 million pre-tax) lower than the amounts previously reported in our Form 10-Q for the quarter period ended June 30, 2013 of $3.2 million. The pre-tax adjustments were primarily related to equipment-related costs of $1.7 million.